{"schema_version":1,"layer":"air","reviewed_on":"2026-10-28","coverage_note":"Generator counts documented in selected permits, not a complete state or national count. A construction or operation permit does not prove equipment installation, operating hours, measured emissions or a data center opening.","items":[{"id":"air-ga-amazon-atl068-atl078-20250818","kind":"generator_permit","subject":"Amazon ATL068 and ATL078, Lithia Springs","state_codes":["ga"],"scope":"One dated permit jointly covers two colocated campuses. 188 is a combined permitted generator inventory, not observed operation or a per building count.","fields":{"status":{"value":"permitted","source_ids":["ga-final-op29644"],"scope":"Issued permit dated August 18, 2025, not observed operation or a finding that this is the latest unamended authorization.","locator":"Cover issuance heading and signed disposition"},"issued_on":{"value":"2025-08-18","source_ids":["ga-final-op29644"],"scope":"Permit issuance, not installation, energization or opening.","locator":"Cover issuance date"},"permit_identifier":{"value":"7374-097-0101-S-01-0","source_ids":["ga-final-op29644"],"scope":"Exact identifier of this dated permit.","locator":"Cover and page headings"},"facility_address":{"value":"1456 Trae Lane, Lithia Springs, Georgia 30122, Douglas County","source_ids":["ga-final-op29644"],"scope":"Facility address from permit cover. The separate Virginia mailing address is not the generator location.","locator":"Cover facility address"},"generator_count":{"value":188,"source_ids":["ga-final-op29644"],"scope":"Combined permitted inventory across two campuses, not 188 at each campus, an installed count or complete Georgia census.","locator":"Cover authorization paragraph","unit":"generators","measurement_role":"permitted_equipment"},"equipment_scope":{"value":"Two colocated campuses, ATL068 and ATL078: 180 critical generators and eight house, boost pump station and security generators.","source_ids":["ga-final-op29644"],"scope":"Cover total 188; critical source range 1 through 180, six house units and one each boost pump station and security. No individual building quantity or grid load assigned.","locator":"Cover and conditions2.10 and2.11"},"fuel":{"value":"Diesel, including biodiesel; maximum 15 ppm sulfur, with the specified cetane or aromatic content conditions.","source_ids":["ga-final-op29644"],"scope":"Permitted fuel, not fuel actually purchased or burned.","locator":"Condition2.6, printed page2"},"federal_operating_limits":{"value":"Maintenance checks and readiness testing have a 100 hour annual allowance with stated petition or required testing provisions. Nonemergency operation is limited to 50 hours annually, included within that 100 hours.","source_ids":["ga-final-op29644"],"scope":"Per generator. Included in 100 hours, not an additional 50. Separate state conditions and the most stringent condition still apply. No actual annual hours admitted.","locator":"Conditions1.5 and2.7.b,c"},"financial_dispatch_exception":{"value":"Peak shaving and nonemergency demand response are generally excluded. A narrow financial arrangement exception requires balancing authority or system operator dispatch, local reliability purpose, specified protocols, limited service scope and records.","source_ids":["ga-final-op29644"],"scope":"All condition2.7.c.i requirements must be met together. Not a general right to sell power or provide demand response.","locator":"Condition2.7.c.i, printed page3"},"state_operating_categories":{"value":"House, pump and security standby criteria include less than 200 hours yearly. Critical standby criteria include less than 500 hours yearly and May through September testing only between 10 p.m. and 4 a.m. Engines that cannot meet the standby definitions face separate ozone season NOx requirements.","source_ids":["ga-final-op29644"],"scope":"Conditional Georgia categories per generator, not an unconditional 500 hour cap for every unit. The alternate NOx standard is 80 ppm at 15 percent oxygen, dry basis, during May 1 through September 30. Federal permit conditions also apply.","locator":"Conditions2.10 and2.11, printed pages4 and5"},"emission_ceiling":{"value":"Across the permitted generator inventory, NOx and CO each have a 99.9 ton ceiling per 12 consecutive months; VOC has a 24.9 ton ceiling over the same rolling period.","source_ids":["ga-final-op29644"],"scope":"Permit ceilings for the listed generators, not measured emissions or an air quality impact estimate.","locator":"Conditions2.1,2.2 and2.3"},"actual_started_on":{"value":null,"source_ids":["ga-final-op29644"],"scope":"No observed generator startup or facility opening date established by this permit.","locator":"Review limit","unknown_reason":"No observed generator startup or facility opening date established by this permit."},"measured_emissions":{"value":null,"source_ids":["ga-final-op29644"],"scope":"No measured emissions, fuel use, compliance finding or actual operating hours admitted.","locator":"Review limit","unknown_reason":"No measured emissions, fuel use, compliance finding or actual operating hours admitted."},"atlas_record_id":{"value":null,"source_ids":["ga-final-op29644"],"scope":"Two campus permit scope has not been independently joined to an exact Atlas building or parcel.","locator":"Identity review hold","unknown_reason":"Two campus permit scope has not been independently joined to an exact Atlas building or parcel."},"later_amendments":{"value":null,"source_ids":["ga-final-op29644"],"scope":"Later permits, amendments, stays and current compliance outcomes require separate review.","locator":"Dated source scope","unknown_reason":"Later permits, amendments, stays and current compliance outcomes require separate review."}}},{"id":"air-ga-amazon-atl089-20260629","kind":"generator_permit","subject":"Amazon ATL089 campus, Covington, issued June 2026 generator permit","state_codes":["ga"],"scope":"One actual dated permit authorizes 321 emergency generators. Inventory, conditional operating and reporting requirements, narrative conflicts and actual outcomes remain separate. No observed operation or statewide count completeness implied.","fields":{"status":{"value":"permitted","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Actual issued permit, not observed operation or a finding that no later amendment exists.","locator":"Signed cover and issue heading"},"historical_permit_basis":{"value":"Historical issued permit","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"This is a dated June 2026 issued instrument. A current source inventory or operating observation requires separate review.","locator":"Signed cover"},"issued_on":{"value":"2026-06-29","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Permit issuance, separate from application, narrative date, proposed installation and actual startup.","locator":"Cover issue heading"},"application_on":{"value":"2025-09-19","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Date of application 29883 as cited by the final permit, not its approval date.","locator":"Cover application reference"},"permit_identifier":{"value":"7374-217-0078-E-01-0","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Exact dated permit identity.","locator":"Cover and page headings"},"facility_address":{"value":"11145 Alcovy Road, Covington, Georgia 30054, Newton County","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Permit facility address. The Virginia mailing address is separate and no Atlas building or parcel identity join is made.","locator":"Cover facility address"},"airs_identifier":{"value":"04-13-217-00078","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Actual signed permit AIRS identity. The narrative carries a different number, disclosed separately.","locator":"Cover AIRS heading"},"generator_count":{"value":321,"source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Total expressly authorized in the permit, not installed units, an operational count, grid MW or a statewide census.","locator":"Cover authorization and printed page 9 equation explanation","unit":"generators","measurement_role":"permitted_equipment"},"equipment_scope":{"value":"316 critical emergency generators plus five ancillary building emergency generators, in groups of two, two and one.","source_ids":["ga-atl089-final-op29883-20260629","ga-atl089-final-narrative-on29883"],"scope":"Narrative identifies the source groups corresponding to the final permit source ranges. Proposed 2026 installation is not proof of installation. Storage tanks are not added to the generator count.","locator":"Permit conditions 2.10 and 2.11; narrative PDF 1 and 2"},"narrative_identity_conflict":{"value":"The narrative heading names ATL089 and application 29883 but gives AIRS 149 00013; repeated page headers name ATL086.","source_ids":["ga-atl089-final-op29883-20260629","ga-atl089-final-narrative-on29883","ga-atl089-modern-public-search-20261023"],"scope":"The signed permit and current public search name ATL089, AIRS 217 00078 and this exact permit. The conflicting narrative labels are disclosed, not silently corrected, treated as a second facility or used to make an Atlas identity join.","locator":"Permit cover; public search single result; narrative PDF 1 and repeated headings"},"narrative_chronology":{"value":"Narrative heading dated November 3, 2025; its final addendum describes public review from March 4 to April 6, 2026 and comments received on April 6.","source_ids":["ga-atl089-final-narrative-on29883"],"scope":"No invented separate addendum posting date. Narrative recommendation is separate from actual June 29 issuance. Appendix A is referenced but not included in the captured eleven pages and is not reviewed.","locator":"Narrative PDF 1, 10 and 11"},"fuel":{"value":"Diesel including biodiesel, maximum sulfur 15 ppm and either minimum cetane index 40 or maximum aromatic content 35 volume percent.","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Permitted fuel specification, not fuel actually purchased, stored or burned.","locator":"Conditions 2.6 and 2.12"},"hour_limits":{"value":"Condition 2.3 bars more than 500 hours per year for any listed engine. The critical engine standby category requires less than 500 hours per year, while the ancillary standby category requires less than 200 hours per year.","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Condition 7.5 requires a monthly calculation of the rolling twelve month hours. Federal emergency use wording does not cancel these separate permit conditions; the most stringent condition controls. Engines outside the state standby definitions face the separate ozone season NOx requirement. No actual hours or entitlement to 500 hours for every unit is established.","locator":"Conditions 1.5, 2.3, 2.7(a), 2.10, 2.11 and 7.5"},"federal_nonemergency_limits":{"value":"Maintenance and readiness testing have a 100 hour calendar year allowance with specified petition or required testing provisions. Nonemergency operation has a 50 hour calendar year limit included within the 100 hours.","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"The 50 hours are not an additional allowance. Federal allowances remain subject to the separate state permit conditions and most stringent condition. No actual testing, dispatch or annual hours verified.","locator":"Condition 2.7(b) and (c)"},"financial_dispatch_exception":{"value":"A narrow financial arrangement exception requires all five conditions for system operator dispatch, local reliability purpose, specified protocols, limited service scope and dispatch records.","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Peak shaving and nonemergency demand response are generally excluded. This is not a general permission to sell power or an observed dispatch.","locator":"Condition 2.7(c)(i)(A) through (E)"},"seasonal_testing":{"value":"Critical engine routine testing and maintenance from May through September must occur between 10 p.m. and 4 a.m.; other months allow any time of day.","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Conditional permit operating schedule, not an actual testing record or proof of compliance.","locator":"Condition 2.11(c)"},"emission_ceiling":{"value":"NOx and CO each have a 249.9 ton ceiling per twelve consecutive months across the listed generator inventory.","source_ids":["ga-atl089-final-op29883-20260629","ga-atl089-final-narrative-on29883"],"scope":"Permit limits, not measured releases, ambient concentrations, avoided pollution or actual customer load. Narrative potential emissions table has no actual values and its dashes are not converted to zero.","locator":"Conditions 2.1, 2.2 and 7.3; narrative PDF 3"},"control_requirements":{"value":"Critical engines have SCR and catalyzed diesel particulate filter requirements when exhaust temperature reaches 572 degrees Fahrenheit, with startup, shutdown and malfunction exceptions.","source_ids":["ga-atl089-final-op29883-20260629","ga-atl089-final-narrative-on29883"],"scope":"The narrative distinguishes controlled and uncontrolled operation. Control requirements are not proof of controls installed or operating continuously. No emission reduction or health outcome calculated.","locator":"Conditions 4.2 through 4.4 and 5.2; narrative PDF 3"},"startup_and_title_v":{"value":"Startup notice is due within fifteen days after startup. A complete Title V permit application is required within twelve months after any emergency generator starts.","source_ids":["ga-atl089-final-op29883-20260629"],"scope":"These are duties triggered by an actual startup date. No startup, completed notice, application, issued Title V permit or calendar deadline is inferred from the construction permit.","locator":"Conditions 7.1 and 8.3"},"current_permit_validity":{"value":null,"source_ids":["ga-atl089-final-op29883-20260629"],"scope":"Later amendments, stays or rescission and current unamended validity are not independently reviewed.","locator":"Dated permit review boundary","unknown_reason":"Later amendments, stays or rescission and current unamended validity are not independently reviewed."},"actual_installed_equipment":{"value":null,"source_ids":["ga-atl089-final-op29883-20260629"],"scope":"No actual installed generator inventory is verified.","locator":"Dated permit review boundary","unknown_reason":"No actual installed generator inventory is verified."},"actual_generation":{"value":null,"source_ids":["ga-atl089-final-op29883-20260629"],"scope":"No actual generation, served electric demand or generator operating hours are reviewed.","locator":"Dated permit review boundary","unknown_reason":"No actual generation, served electric demand or generator operating hours are reviewed."},"actual_started_on":{"value":null,"source_ids":["ga-atl089-final-op29883-20260629"],"scope":"No actual startup, energization or opening date is verified.","locator":"Dated permit review boundary","unknown_reason":"No actual startup, energization or opening date is verified."},"measured_emissions":{"value":null,"source_ids":["ga-atl089-final-op29883-20260629"],"scope":"No emissions measurement, fuel use, compliance or health outcome is reviewed.","locator":"Dated permit review boundary","unknown_reason":"No emissions measurement, fuel use, compliance or health outcome is reviewed."},"atlas_record_id":{"value":null,"source_ids":["ga-atl089-final-op29883-20260629"],"scope":"No independently verified Atlas facility, building or parcel identity join is made.","locator":"Dated permit review boundary","unknown_reason":"No independently verified Atlas facility, building or parcel identity join is made."}}},{"id":"air-ga-amazon-atl057-20230921-context","kind":"permit_context","subject":"Amazon ATL057 dated permit and separate equipment plan","state_codes":["ga"],"scope":"Issued September 2023 permit terms and a separate seven unit narrative plan. The signed instrument gives no numerical inventory. Planned equipment, future phases, rolling operating limits and unknown actual outcomes remain distinct.","fields":{"status":{"value":"permitted","source_ids":["ga-atl057-issued-op28844-20230921"],"scope":"Actual dated permit issuance only. No observed construction, generator installation, energization or operating status is inferred.","locator":"Signed cover and issue heading"},"planned_inventory_basis":{"value":"Issued permit with separate narrative equipment plan","source_ids":["ga-atl057-issued-op28844-20230921","ga-atl057-narrative-on28844-20230921"],"scope":"The signed instrument states no numerical generator inventory. The narrative plan is retained separately and excluded from the table of numerical permitted inventories.","locator":"Permit cover and full conditions; narrative purpose and equipment list"},"issued_on":{"value":"2023-09-21","source_ids":["ga-atl057-issued-op28844-20230921"],"scope":"Actual issuance date, separate from application, narrative heading, public advisory and proposed installation dates.","locator":"Signed cover"},"application_on":{"value":"2023-04-06","source_ids":["ga-atl057-issued-op28844-20230921","ga-atl057-narrative-on28844-20230921"],"scope":"Application date cited by the signed permit. The narrative separately says received the same date.","locator":"Permit cover; narrative page 1"},"facility_address":{"value":"New Boyd Road, Duluth, Georgia 30024, Forsyth County","source_ids":["ga-atl057-issued-op28844-20230921"],"scope":"Dated permit facility address. The Herndon mailing address is separate. No parcel, building or Atlas record identity is joined.","locator":"Permit cover"},"permit_identifier":{"value":"7374 117 0093 B 01 0","source_ids":["ga-atl057-issued-op28844-20230921"],"scope":"Permit identifier components shown with spaces for readability. The original linked instrument retains its punctuation.","locator":"Permit cover"},"airs_identifier":{"value":"04 13 117 00093","source_ids":["ga-atl057-issued-op28844-20230921"],"scope":"AIRS identity components in the signed cover, separate from equipment count or an Atlas identity join.","locator":"Permit cover"},"planned_generator_count":{"value":7,"source_ids":["ga-atl057-narrative-on28844-20230921"],"scope":"Narrative application requests seven diesel emergency generators. This is a proposed equipment inventory, not a numerical inventory expressly stated by the signed permit or installed equipment.","locator":"Narrative page 1 purpose of application and equipment list on pages 1 and 2","unit":"generators","measurement_role":"proposed_equipment"},"equipment_plan":{"value":"One 0.6 MW house generator and six 2.5 MW generators. The plan places the house generator and two larger units in August 2023, two more in August 2028 and two in August 2037.","source_ids":["ga-atl057-narrative-on28844-20230921"],"scope":"Original plan ratings and months are retained without summing grid capacity or treating any date as actual installation. No current completion, revised phase or operating observation is verified.","locator":"Narrative background and equipment list, pages 1 and 2"},"hour_limits":{"value":"Condition 2.3 limits total operation to no more than 200 hours per generator during any twelve consecutive months.","source_ids":["ga-atl057-issued-op28844-20230921"],"scope":"This rolling total is not 200 maintenance hours plus unrestricted emergency hours. Condition 1.5 says the most stringent conflicting condition prevails. No actual operating hours are reviewed.","locator":"Permit conditions 1.5 and 2.3"},"federal_operation_conditions":{"value":"Condition 2.4 describes emergency use without a federal emergency time limit and generally allows 100 annual maintenance and readiness hours, including up to 50 hours of specified nonemergency use. The 50 hours are part of the 100 hours, with stated maintenance exceptions and tightly conditioned dispatch provisions.","source_ids":["ga-atl057-issued-op28844-20230921"],"scope":"The separate 200 hour rolling total remains. This is not an additional 150 hour allowance or unrestricted peak shaving, grid sales or demand response. The full linked instrument controls exceptions and dispatch conditions.","locator":"Permit condition 2.4(a) through (c)(i)(E)"},"fuel":{"value":"Diesel fuel oil, with maximum sulfur of 15 ppm and either a minimum cetane index of 40 or maximum aromatic content of 35 volume percent for engines with less than 30 liters per cylinder.","source_ids":["ga-atl057-issued-op28844-20230921"],"scope":"Fuel purchase and use requirements, not measured fuel composition, actual fuel burned or emissions.","locator":"Permit conditions 2.5 and 2.6"},"seasonal_conditions":{"value":"Condition 2.8 includes an ozone season NOx standard where the emergency definition and listed data center conditions are not met. The listed conditions include less than 500 annual hours and routine testing from 10 p.m. to 4 a.m. during May through September, with other months allowing testing at any time of day.","source_ids":["ga-atl057-issued-op28844-20230921"],"scope":"The less than 500 hour criterion does not replace condition 2.3 limiting total operation to 200 hours during any twelve consecutive months. No actual exception, testing schedule or compliance outcome is found.","locator":"Permit conditions 2.3 and 2.8"},"monitoring_and_reporting":{"value":"Each generator requires a nonresettable hour meter recording emergency, nonemergency and total operation. Monthly operating and fuel records must be retained. Written startup notification is due within fifteen days of actual startup. Specified financial dispatch triggers an annual report due March 31 of the following year.","source_ids":["ga-atl057-issued-op28844-20230921"],"scope":"Monitoring and reporting duties do not establish actual startup, a submitted report, compliance, fuel use or a calendar deadline for this facility.","locator":"Permit conditions 5.3 and 7.1 through 7.6"},"future_emissions_review":{"value":"The narrative requires a renewed potential emissions demonstration for the later EG3 through EG6 phases and describes a RACT plan if potential NOx exceeds 25 tons per year.","source_ids":["ga-atl057-narrative-on28844-20230921"],"scope":"This is dated narrative review of proposed later phases, not a current major or minor source determination, actual annual emissions or issued RACT approval.","locator":"Narrative regulatory review page 3 and recommendations page 5"},"emissions_table_scope":{"value":"The narrative contains a table headed Actual Emissions alongside Potential Emissions, while its discussion describes vendor data, emission factors and planned construction.","source_ids":["ga-atl057-narrative-on28844-20230921"],"scope":"No measured emissions record, monitoring period or actual operations evidence is reviewed. No numerical value from that table is admitted as measured emissions.","locator":"Narrative emissions summary page 2 and background page 1"},"narrative_date_scope":{"value":"The narrative heading is May 4, 2023, and its text states that Public Advisory expired May 26, 2023.","source_ids":["ga-atl057-narrative-on28844-20230921","ga-atl057-issued-op28844-20230921"],"scope":"These labels remain separate. PDF metadata dated September 25 does not establish publication or revise the September 21 permit issuance date.","locator":"Narrative page 1 heading and purpose; page 5 recommendations; actual PDF metadata"},"permitted_generator_inventory":{"value":null,"source_ids":["ga-atl057-issued-op28844-20230921","ga-atl057-narrative-on28844-20230921"],"scope":"No numerical generator inventory is expressly stated in the signed permit. Narrative planned equipment is not substituted.","locator":"Dated permit and narrative review boundary","unknown_reason":"No numerical generator inventory is expressly stated in the signed permit. Narrative planned equipment is not substituted."},"current_permit_validity":{"value":null,"source_ids":["ga-atl057-issued-op28844-20230921","ga-atl057-narrative-on28844-20230921"],"scope":"Later amendments, stays or rescission and current unamended validity are not independently reviewed.","locator":"Dated permit and narrative review boundary","unknown_reason":"Later amendments, stays or rescission and current unamended validity are not independently reviewed."},"actual_installed_equipment":{"value":null,"source_ids":["ga-atl057-issued-op28844-20230921","ga-atl057-narrative-on28844-20230921"],"scope":"No actual installed generator inventory is verified.","locator":"Dated permit and narrative review boundary","unknown_reason":"No actual installed generator inventory is verified."},"actual_generation":{"value":null,"source_ids":["ga-atl057-issued-op28844-20230921","ga-atl057-narrative-on28844-20230921"],"scope":"No actual generation, served electric demand or operating hours are reviewed.","locator":"Dated permit and narrative review boundary","unknown_reason":"No actual generation, served electric demand or operating hours are reviewed."},"actual_started_on":{"value":null,"source_ids":["ga-atl057-issued-op28844-20230921","ga-atl057-narrative-on28844-20230921"],"scope":"No actual startup, energization or opening date is verified.","locator":"Dated permit and narrative review boundary","unknown_reason":"No actual startup, energization or opening date is verified."},"measured_emissions":{"value":null,"source_ids":["ga-atl057-issued-op28844-20230921","ga-atl057-narrative-on28844-20230921"],"scope":"No independent measured emissions, fuel use, compliance or health outcome is reviewed.","locator":"Dated permit and narrative review boundary","unknown_reason":"No independent measured emissions, fuel use, compliance or health outcome is reviewed."},"atlas_record_id":{"value":null,"source_ids":["ga-atl057-issued-op28844-20230921","ga-atl057-narrative-on28844-20230921"],"scope":"No independently verified Atlas facility, building or parcel identity join is made.","locator":"Dated permit and narrative review boundary","unknown_reason":"No independently verified Atlas facility, building or parcel identity join is made."}}},{"id":"air-ga-dcb-atlanta-east-20250226","kind":"generator_permit","subject":"DCB Atlanta East, Conyers, dated six generator permit","state_codes":["ga"],"scope":"Dated February 2025 six generator issued authorization with separate state and federal conditions, narrative calculation assumptions, future installation plan and explicit source differences. Permit is not operation.","fields":{"status":{"value":"permitted","source_ids":["ga-dcb-east-issued-op29442-20250226","ga-dcb-public-index-20261024"],"scope":"Dated issued permit with signed cover and current official search link. Not observed operation, installed inventory or proof that no later amendment exists.","locator":"Signed cover and exact East public search row"},"historical_permit_basis":{"value":"Historical issued permit","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"This February 2025 instrument is reviewed as a dated authorization, not a certified current unamended operating inventory.","locator":"Signed cover"},"issued_on":{"value":"2025-02-26","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"Actual printed issuance date, separate from application, narrative, installation plans and startup.","locator":"Cover issuance heading"},"application_on":{"value":"2024-09-26","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"Application 29442 date printed on the issued permit, not its approval date.","locator":"Cover application reference"},"permit_identifier":{"value":"7374-247-0076-B-01-0","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"Exact issued permit identifier; West is a different permit and facility.","locator":"Cover and all condition headings"},"facility_address":{"value":"1726 Farmer Road, Conyers, Georgia 30012, Rockdale County","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"Permit prints Farmer Rd. This facility address is separate from the Atlanta mailing address and supplies no reviewed parcel or Atlas identity join.","locator":"Cover facility and mailing address blocks"},"airs_identifier":{"value":"04-13-247-00076","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"Exact facility AIRS identifier in the issued permit.","locator":"Cover AIRS block"},"generator_count":{"value":6,"source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"Six emergency diesel generators expressly authorized by the issued cover. Not an installed count, actual operation, campus electric load or complete state census.","locator":"Cover authorization; conditions 2.1 through 2.10 source range EG01 through EG06","unit":"generators","measurement_role":"permitted_equipment"},"equipment_scope":{"value":"Six emergency generators, source identifiers EG01 through EG06.","source_ids":["ga-dcb-east-issued-op29442-20250226","ga-dcb-east-narrative-on29442-20261024"],"scope":"The final permit count is primary. Narrative 3 MW specifications and 2025 through 2028 phases remain proposed equipment descriptions, not aggregate grid capacity or verified installation.","locator":"Permit cover and source ranges; narrative PDF 1"},"fuel":{"value":"Diesel distillate with maximum 15 ppm sulfur, plus a minimum cetane index 40 or maximum aromatic content 35 volume percent.","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"Fuel requirement, not fuel actually purchased or burned. The general 2.5 percent clause is subsumed by the more restrictive federal fuel requirement and most stringent condition.","locator":"Conditions 1.5, 2.2, 2.3 and 2.5"},"hour_limits":{"value":"The state standby criteria require total annual operation below 500 hours for each generator, plus the specified reasons, seasonal testing window and records.","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"The federal emergency wording does not cancel separate state permit conditions. Condition 7.3 separately requires rolling twelve month calculation and notice at 500 hours or more. This is not actual runtime or a general allowance to operate 500 hours.","locator":"Conditions 1.5, 2.4 and 7.3"},"federal_nonemergency_limits":{"value":"Maintenance and readiness testing have a maximum 100 hours per calendar year, subject to specified petition or mandatory testing provisions. Up to 50 nonemergency hours are included within those 100 hours.","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"The 50 hours are not additional. All separate state conditions remain. No actual testing or dispatch is established.","locator":"Condition 2.8(b) and (c)"},"financial_dispatch_exception":{"value":"The narrow financial arrangement exception requires all five conditions for system operator dispatch, local reliability purpose, specified protocols, limited power service and records.","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"Ordinary peak shaving, nonemergency demand response and financial power supply are excluded outside the stated exception. The permit cross reference says 2.5.c.i even though the exception is printed under 2.8.c.i; this is preserved as a source cross reference issue, not silently repaired.","locator":"Condition 2.8(c) and (c)(i)(A)through(E), PDF 4 and 5"},"seasonal_testing":{"value":"Routine maintenance and testing from May through September must occur between 10 p.m. and 4 a.m.; other stated months allow any time of day.","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"State standby condition, not an observed schedule, noise finding or proof of compliance. Engines outside the standby definition have the separate ozone season NOx requirement.","locator":"Condition 2.4(a)through(d) andfollowing paragraph"},"monitoring_and_notice":{"value":"Each generator requires a nonresettable hour monitor, monthly operation and reason records, and monthly rolling totals. Startup notice is due within 15 days after startup.","source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"Duties, not completed records or actual startup. Rolling total notifications at 500 total or 100 nonemergency hours are separate from calendar year language. Five year record retention is not a claim that records were publicly obtained.","locator":"Conditions 1.4, 5.2, 7.1 through 7.5"},"narrative_model_basis":{"value":"The narrative models potential emissions using 200 hours per year and its Actual Emissions column using an expected ten hours per year.","source_ids":["ga-dcb-east-narrative-on29442-20261024"],"scope":"These are calculation assumptions, not a 200 hour operative permit ceiling, independently measured emissions or actual operation. No numerical modeled releases are promoted to measured values and no new totals are calculated.","locator":"Narrative PDF 2 through 4 and 8"},"modeled_potential_hours":{"value":200,"source_ids":["ga-dcb-east-narrative-on29442-20261024"],"scope":"Narrative calculation assumption for potential emissions, not a permit runtime ceiling or actual hours.","locator":"Narrative PDF 2 and 8","unit":"hours per year","measurement_role":"emissions_model_assumption"},"modeled_expected_hours":{"value":10,"source_ids":["ga-dcb-east-narrative-on29442-20261024"],"scope":"Narrative expected operating assumption underlying its Actual Emissions column, not measured operation.","locator":"Narrative PDF 2 through 4 and 8","unit":"hours per year","measurement_role":"emissions_model_assumption"},"narrative_plan":{"value":"The November 2024 narrative proposes three generators in 2025, one each in 2026, 2027 and 2028, with final installation and operation expected November 2028.","source_ids":["ga-dcb-east-narrative-on29442-20261024"],"scope":"Dated application plan, not completed installation, operation or a new forecast adopted as an outcome. No summedMW capacity is computed.","locator":"Narrative PDF 1 equipment table and background"},"source_differences":{"value":"The narrative summary says notice before startup while the issued permit requires notice within 15 days after startup. The narrative describes less than 100 hours while the final federal clause states a maximum 100 hours with specified extra testing provisions.","source_ids":["ga-dcb-east-issued-op29442-20250226","ga-dcb-east-narrative-on29442-20261024"],"scope":"Final issued conditions control this review. The final narrative addendum still contains unfilled review dates and alternative comments wording, not an actual later comment period or proof of no comments.","locator":"Permit 2.8 and 7.1; narrative PDF 7 and 10"},"current_permit_validity":{"value":null,"source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"Later amendments, stays, rescission and current unamended validity are not independently established.","locator":"Bounded dated permit and narrative review","unknown_reason":"Later amendments, stays, rescission and current unamended validity are not independently established."},"actual_installed_equipment":{"value":null,"source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"No installed generator inventory is independently verified.","locator":"Bounded dated permit and narrative review","unknown_reason":"No installed generator inventory is independently verified."},"actual_generation":{"value":null,"source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"No actual generated electricity, electric load or operating hours are reviewed.","locator":"Bounded dated permit and narrative review","unknown_reason":"No actual generated electricity, electric load or operating hours are reviewed."},"actual_started_on":{"value":null,"source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"No actual facility or generator startup date or completed startup notification is reviewed.","locator":"Bounded dated permit and narrative review","unknown_reason":"No actual facility or generator startup date or completed startup notification is reviewed."},"measured_emissions":{"value":null,"source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"The narrative calculated Actual Emissions column is not an independently measured release record.","locator":"Bounded dated permit and narrative review","unknown_reason":"The narrative calculated Actual Emissions column is not an independently measured release record."},"atlas_record_id":{"value":null,"source_ids":["ga-dcb-east-issued-op29442-20250226"],"scope":"No verified Atlas record, building or parcel identity join is made.","locator":"Bounded dated permit and narrative review","unknown_reason":"No verified Atlas record, building or parcel identity join is made."}}},{"id":"air-ga-dcb-atlanta-west-20260128","kind":"generator_permit","subject":"DCB Atlanta West, Douglasville, dated 76 generator and fuel limit permit","state_codes":["ga"],"scope":"Signed January 2026 authorization, facilitywide rolling diesel fuel ceiling, separate hour conditions and completed public comment addendum. Narrative calculation and chronology conflicts retained. Permit is not operation.","fields":{"status":{"value":"permitted","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"Dated final issued authorization establishes permitted equipment and enforceable conditions. It does not establish construction, installation, current unamended validity or operation.","locator":"Signed permit cover"},"historical_permit_basis":{"value":"Historical issued permit","source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"This exact January 2026 instrument is reviewed. Later amendment, rescission or actual equipment status is unknown.","locator":"Complete signed dated permit"},"issued_on":{"value":"2026-01-28","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"Printed final issuance day, distinct from application, original narrative and later narrative addendum dates.","locator":"Signed cover"},"application_on":{"value":"2025-05-28","source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"Application date printed on the final permit and narrative header. Narrative purpose paragraph instead prints May 23, retained as a source discrepancy.","locator":"Final cover; narrative PDF 1"},"narrative_heading_on":{"value":"2025-08-08","source_ids":["ga-dcb-west-narrative-on29723-20261024"],"scope":"Original narrative heading only. The retained document also contains later December 2025 and January 2026 addendum material, so its final publication day remains unknown.","locator":"Narrative PDF 1 and 16 through 24"},"permit_identifier":{"value":"7374-097-0102-S-01-0","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"Exact permit identifier for this dated West facility instrument. East facility permits are separate.","locator":"Signed cover and all condition headers"},"facility_address":{"value":"1701 North River Rd, Douglasville, Georgia 30122, Douglas County","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"Address printed on the issued permit, not a verified parcel, building geometry or exact Atlas location match.","locator":"Permit cover"},"airs_identifier":{"value":"04-13-097-00102","source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"Final cover facility AIRS identifier. Narrative abbreviated county facility identifier is separate from an Atlas record join.","locator":"Permit cover; narrative header"},"generator_count":{"value":76,"source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"Total emergency generators authorized for the two building facility. Not an installed inventory, actual operating count or count of permits.","locator":"Signed cover","unit":"generators","measurement_role":"permitted_equipment"},"equipment_scope":{"value":"The final cover authorizes two buildings with 76 emergency generators. The narrative proposes sixty 3.0 MW units and sixteen 2.5 MW units.","source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"Final total count and proposed equipment specifications have distinct sources. No aggregate MW, grid demand or installed capacity is computed. The emissions model instead represents all units as 3.0 MW.","locator":"Final cover; narrative PDF 1 through 4"},"permitted_diesel_fuel_limit":{"value":745286,"source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"Maximum collective diesel fuel consumption for all emergency generators in any twelve consecutive months. A rolling facilitywide permit ceiling, not actual use, a calendar year total, a per generator allowance or an emissions measurement.","locator":"Condition 2.1, PDF 2","unit":"gallons","measurement_role":"permitted_fuel_consumption_limit","measurement_period":"Any twelve consecutive months","measure_scope":"All facility emergency generators"},"fuel_monitoring_and_notice":{"value":"Fuel use is recorded monthly and summed over rolling twelve month periods. Written notification is due within 15 days if the rolling total equals or exceeds 745,286 gallons.","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"The notice threshold includes equality while the substantive cap prohibits exceeding the amount. These are different duties. No fuel meter values, supplier receipts or filed notification are reviewed.","locator":"Conditions 5.2(c), 7.4 and 7.5, PDF 6 and 9"},"fuel":{"value":"Diesel distillate with maximum sulfur 15 ppm and either minimum cetane index 40 or maximum aromatic content 35 volume percent.","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"Fuel specifications are not evidence of actual storage, purchase or combustion.","locator":"Conditions 2.5 and 2.10"},"hour_limits":{"value":"The state data center condition requires each generator to operate below 500 hours per year, for the specified emergency or testing purposes and with required records.","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"The federal emergency no time limit sentence does not cancel the separate most stringent state condition. Rolling hour notice duties are stated separately. No actual runtime is established.","locator":"Conditions 1.5 and 2.11"},"federal_nonemergency_limits":{"value":"Maintenance and readiness testing may use at most 100 hours per calendar year, subject to the stated additional testing provisions. Up to 50 nonemergency hours are included within those 100 hours.","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"The 50 hours are not additional to 100. The conditional financial dispatch exception and state data center limits remain separate.","locator":"Condition 2.7(a) through (c), PDF 3 and 4"},"financial_dispatch_exception":{"value":"The narrow exception requires all five conditions for system operator dispatch, local reliability purpose, specified protocols, limited power destination and dispatch records.","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"Ordinary peak shaving, nonemergency demand response and financial supply are excluded outside the specified exception. The exception is printed under 2.7(c)(i), despite a 2.5.c.i cross reference in the preceding paragraph.","locator":"Condition 2.7(c) and (c)(i)(A) through (E), PDF 4"},"seasonal_testing":{"value":"Routine testing and maintenance from May through September are limited to 10 p.m. through 4 a.m.; the other stated months permit any time of day.","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"State operating condition, not an observed operating or noise schedule. Engines that do not meet the stated data center definition retain the separate ozone season NOx condition.","locator":"Condition 2.11(c) and final paragraph, PDF 5"},"operating_records_and_notice":{"value":"Each generator requires a nonresettable hour meter and monthly hours and reasons. Rolling totals at or above 500 total hours or 100 nonemergency hours require written notice within 15 days. Startup notice is due within 15 days after startup.","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"Calendar year conditions, monthly rolling notifications and startup notice are distinct. These record duties and deadlines do not establish actual startup, hours, dispatch or compliance.","locator":"Conditions 5.2, 7.1, 7.6 through 7.9"},"conditional_annual_report":{"value":"Operation under the financial dispatch exception triggers an annual report due March 31 of the following calendar year, with electronic reporting or the stated written fallback.","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"Conditional reporting duty, not an actual filed report, routine annual reporting for every possible operation or proof of dispatch.","locator":"Condition 7.10, PDF 10"},"emissions_model_basis":{"value":"The narrative potential emissions table is calculated from the fuel limit and pollutant factors, conservatively representing all generators as 3.0 MW units at full load. Its benzene assessment uses screening model predictions.","source_ids":["ga-dcb-west-narrative-on29723-20261024"],"scope":"Potential releases and modeled ambient concentrations are not actual measured emissions, health outcomes or proof of facility operation. The narrative labels an SO2 example result as NOx; no new calculation or correction is substituted.","locator":"Narrative PDF 4, 5 and 13 through 15"},"narrative_plan":{"value":"The narrative schedules phased generator installation from November 2025 through 2027 and separately gives different final completion descriptions in its prose and equipment table.","source_ids":["ga-dcb-west-narrative-on29723-20261024"],"scope":"Dated proposed phases are not actual construction or startup. The opening says building construction begins May 2027, while the completed addendum says that year was revised to 2025. The disagreement is retained.","locator":"Narrative PDF 1 through 4 and 16"},"public_review_opened_on":{"value":"2025-12-15","source_ids":["ga-dcb-west-narrative-on29723-20261024"],"scope":"Start date reported by the completed narrative addendum, separate from the earlier July 2025 advisory. The addendum calls this a 30 day review; no independent duration calculation replaces its stated dates.","locator":"Narrative addendum PDF 16"},"public_review_closed_on":{"value":"2026-01-16","source_ids":["ga-dcb-west-narrative-on29723-20261024"],"scope":"End date in the completed addendum and date of received public comments, not permit issuance or actual startup.","locator":"Narrative PDF 16, 17 and appended letter date"},"public_comments":{"value":"The completed addendum records consultant comments on December 30, 2025 and public comments on January 16, 2026, with agency responses.","source_ids":["ga-dcb-west-narrative-on29723-20261024"],"scope":"Received comments are not adopted regulatory conditions or independently established claims about other facilities, regional generation or health. The appended external citations were not independently reviewed.","locator":"Narrative PDF 16 through 24"},"source_differences":{"value":"The narrative header and final cover say application May 28, 2025, but the purpose paragraph says May 23. The addendum says construction 2027 was corrected to 2025, while the retained opening still says 2027.","source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"Separate source discrepancies retained, not silently normalized or resolved into actual construction dates. Final permit conditions establish the authorized limits.","locator":"Permit cover; narrative PDF 1 and 16"},"permit_cross_references":{"value":"The financial exception points to 2.5.c.i while printed under 2.7.c.i. Condition 5.3 refers to 2.9 for fuel verification while 7.3 points to 2.5. Runtime conditions 7.8 and 7.9 refer to fuel records in 7.5.","source_ids":["ga-dcb-west-issued-op29723-20260128"],"scope":"These are printed internal references, not Atlas corrections or a claim the permit is invalid. The separately quoted substantive limits remain dated final permit conditions.","locator":"Conditions 2.7(c), 5.3, 7.3, 7.8 and 7.9"},"current_permit_validity":{"value":null,"source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"Later amendments, stays, rescission and present unamended validity are not independently established.","locator":"Complete dated permit and narrative review","unknown_reason":"Later amendments, stays, rescission and present unamended validity are not independently established."},"actual_installed_equipment":{"value":null,"source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"No installed generator inventory or verified equipment commissioning is reviewed.","locator":"Complete dated permit and narrative review","unknown_reason":"No installed generator inventory or verified equipment commissioning is reviewed."},"actual_generation":{"value":null,"source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"No actual electric generation, load, hours or dispatch is established by the permit or model.","locator":"Complete dated permit and narrative review","unknown_reason":"No actual electric generation, load, hours or dispatch is established by the permit or model."},"actual_started_on":{"value":null,"source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"No actual startup date or completed startup notice is reviewed.","locator":"Complete dated permit and narrative review","unknown_reason":"No actual startup date or completed startup notice is reviewed."},"actual_diesel_consumption":{"value":null,"source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"The permitted fuel ceiling and monthly record duties do not establish actual fuel use.","locator":"Complete dated permit and narrative review","unknown_reason":"The permitted fuel ceiling and monthly record duties do not establish actual fuel use."},"measured_emissions":{"value":null,"source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"No measured releases or actual ambient monitoring is reviewed. Potential emissions and screening predictions remain model results.","locator":"Complete dated permit and narrative review","unknown_reason":"No measured releases or actual ambient monitoring is reviewed. Potential emissions and screening predictions remain model results."},"actual_compliance":{"value":null,"source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"Permit conditions, expected construction and regulatory modeling are not an actual compliance finding.","locator":"Complete dated permit and narrative review","unknown_reason":"Permit conditions, expected construction and regulatory modeling are not an actual compliance finding."},"atlas_record_id":{"value":null,"source_ids":["ga-dcb-west-issued-op29723-20260128","ga-dcb-west-narrative-on29723-20261024"],"scope":"No exact Atlas site, parcel, building or operating record join is established.","locator":"Complete dated permit and narrative review","unknown_reason":"No exact Atlas site, parcel, building or operating record join is established."}}},{"id":"air-ga-qts-fayetteville-20241017","kind":"generator_permit","subject":"QTS Fayetteville dated 235 generator amendment and later proposed addition","state_codes":["ga"],"scope":"Historical generator source inventory and shared generator/fire pump fuel cap. Pump wording, application chronology and later 2026 proposal remain separate. Permitted is not installed or operating.","fields":{"status":{"value":"permitted","source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"Historical signed amendment, not current complete governing authority or operation.","locator":"Signed cover and amended conditions"},"historical_permit_basis":{"value":"Historical issued permit","source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"Issued amendment and aggregate source codes, distinct from the later proposed application.","locator":"Amendment cover and conditions 2.1 and 2.2"},"mixed_engine_cap_basis":{"value":"Combined generator and fire pump fuel cap with unresolved pump count wording","source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017"],"scope":"Separate equipment categories share one fuel allowance. Fire pumps are not added to the generator count.","locator":"Condition2.1; signed cover and narrative pages 1 and 2"},"issued_on":{"value":"2024-10-17","source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"Signed amendment issuance, not construction completion or current validity.","locator":"Amendment cover"},"permit_identifier":{"value":"7374 113 0073 S 01 2","source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017"],"scope":"Final amendment identifier. Narrative references containing133andS04are retained as source differences rather than substituted.","locator":"Amendment cover; narrative equipment note and emissions section"},"facility_address":{"value":"1435 Hwy 54 West, Fayetteville, Georgia 30214, Fayette County","source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"Facility address, separate from mailing address in Irving, Texas. No exact Atlas join made.","locator":"Signed cover"},"generator_count":{"value":235,"source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"Aggregate generators identified by amended conditions as EG001 through EG235. Not 235 new generators, installed equipment or generator plus fire pump count.","locator":"Amended conditions 2.1, 2.2 and 5.1","unit":"generators","measurement_role":"permitted_equipment"},"permitted_mixed_engine_fuel_limit":{"value":670000,"source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"One shared maximum over any twelve consecutive months for all listed generators and fire pumps combined, not an allowance per engine, consumption report or generator only fuel cap.","locator":"Amended condition 2.1","unit":"gallons","measurement_role":"permitted_fuel_consumption_limit","measurement_period":"Any twelve consecutive months","measure_scope":"All permitted emergency generators and fire pumps combined"},"fire_pump_source_difference":{"value":"The signed cover says two additional fire pumps, while the narrative purpose says one additional pump and its inventory lists FP001 and FP002.","source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017"],"scope":"No reconciled total pump inventory is assigned. The combined cap includes the two listed fire pump codes, but pumps are not counted as generators.","locator":"Permit cover and conditions 2.1 and 2.2; narrative pages 1 and 2"},"application_date_difference":{"value":"The narrative header gives June 17, 2024, while its purpose and the signed cover give July 17; the purpose states receipt July 22.","source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017"],"scope":"Conflicting application dates retained. No single reconciled application date inferred.","locator":"Narrative page 1 header and purpose; amendment cover"},"narrative_heading_on":{"value":"2024-08-12","source_ids":["ga-qts-fayetteville-on29366-20241017"],"scope":"Original heading, not publication of the completed file containing later review outcomes.","locator":"Narrative first page"},"completed_review_period":{"value":"The addendum records public review from September 11 to October 11, 2024 and says no comments were received.","source_ids":["ga-qts-fayetteville-on29366-20241017"],"scope":"Historical 2024 review, distinct from the separate 2026 proposal notice and not proof of current compliance.","locator":"Narrative page 8"},"equipment_code_difference":{"value":"The narrative renames former EG206 and EG207 to EG230 and EG231; the next row has source codes EG232 through EG235 but a description beginning EG230.","source_ids":["ga-qts-fayetteville-on29366-20241017","ga-qts-fayetteville-op29366-20241017"],"scope":"Renaming is not added equipment. The final amendment aggregate source code range remains the generator count basis. Narrative 2024 installation labels do not prove actual commissioning.","locator":"Narrative page 2 equipment table and note"},"fuel":{"value":"Diesel fuel with maximum 15 ppm sulfur and the stated cetane or aromatic alternatives.","source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"Amended fuel specifications for listed generators and fire pumps, not a measured fuel assay.","locator":"Amended condition 2.5"},"state_operating_conditions":{"value":"Generator operation is limited to routine testing and maintenance, utility power loss or internal system failures, with less than 500 annual hours per generator and recorded operating reasons.","source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"State emergency classification conditions, not actual hours or a complete restatement of unchanged federal and base permit requirements.","locator":"Amended condition 2.8"},"seasonal_testing":{"value":"Routine testing from May through September is limited to 10 p.m. through 4 a.m.; other months permit routine testing at any time of day.","source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"Testing condition, not a finding of when operation occurred.","locator":"Amended condition 2.8(c)"},"monitoring_and_records":{"value":"Separate emergency, nonemergency and cumulative hour metering is required; monthly fuel records for generators and pumps are retained for five years.","source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"Recordkeeping duties, not actual submitted hour logs, fuel reports or compliance findings.","locator":"Amended conditions 5.1, 7.4 and 7.5"},"emissions_model_scope":{"value":"The narrative models potential emissions under one shared fuel cap and a worst case engine type. Its Actual Emissions columns contain dashes.","source_ids":["ga-qts-fayetteville-on29366-20241017"],"scope":"Blank actual emissions are not zero. Modelled pollutant quantities and modeled benzene concentrations are not observed releases, exposure measurements or a health finding.","locator":"Narrative pages 3 and 7"},"amendment_scope":{"value":"Only modified and new conditions in the four page amendment were substantively reviewed as permit requirements.","source_ids":["ga-qts-fayetteville-op29366-20241017"],"scope":"The base permit and earlier amendment remain referenced. This review does not claim every unchanged federal provision or all current conditions were reviewed.","locator":"Amendment cover and all three condition pages"},"later_application":{"value":"Application 30027 is listed as a proposed permit for additional emergency generators.","source_ids":["ga-qts-september-public-advisory-20260921"],"scope":"A separate later request, not added to the 235 historical permitted inventory. No numerical proposed count admitted from this notice.","locator":"Official 2026 bulletin QTS Fayetteville major source SIP section"},"later_notice_sent_on":{"value":"2026-09-23","source_ids":["ga-qts-september-public-advisory-20260921"],"scope":"Explicit sent date; the title describes the week of September 21.","locator":"Public bulletin top heading and sent timestamp"},"later_comments_due_on":{"value":"2026-10-23","source_ids":["ga-qts-september-public-advisory-20260921"],"scope":"Printed comment deadline, not an approval, issue or effective date. The deadline passing does not establish a final outcome.","locator":"QTS proposed permit notice deadline"},"permitted_fire_pump_inventory":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"Cover and narrative wording do not establish a reconciled total fire pump inventory.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"Cover and narrative wording do not establish a reconciled total fire pump inventory."},"current_permit_validity":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"No complete current permit chain or later agency decision reviewed.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"No complete current permit chain or later agency decision reviewed."},"later_application_approval":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"No final outcome of application 30027 reviewed.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"No final outcome of application 30027 reviewed."},"later_added_generators":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"No numerical later approved or proposed equipment count established from the notice.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"No numerical later approved or proposed equipment count established from the notice."},"actual_installed_equipment":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"No installation or as built inventory verified.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"No installation or as built inventory verified."},"actual_generation":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"No actual generated electricity verified.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"No actual generated electricity verified."},"actual_started_on":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"No actual startup verified.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"No actual startup verified."},"actual_diesel_consumption":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"No measured or reported actual fuel use reviewed.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"No measured or reported actual fuel use reviewed."},"measured_emissions":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"No actual emissions measurement reviewed.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"No actual emissions measurement reviewed."},"actual_compliance":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"No actual compliance finding established.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"No actual compliance finding established."},"atlas_record_id":{"value":null,"source_ids":["ga-qts-fayetteville-op29366-20241017","ga-qts-fayetteville-on29366-20241017","ga-qts-september-public-advisory-20260921"],"scope":"No exact Atlas facility, parcel or operating building join established.","locator":"Bounded issued amendment, narrative and later proposed notice only","unknown_reason":"No exact Atlas facility, parcel or operating building join established."}}},{"id":"air-ga-ms-fty01-building3-20250415","kind":"generator_permit","subject":"Microsoft FTY01 dated 21 generator building 3 amendment","state_codes":["ga"],"scope":"Historical authorization for an additional building 3 group, with strict annual operating condition, separate calendar and rolling notification clocks, narrative source conflicts and unknown actual operation. The equipment count is not an aggregate campus inventory.","fields":{"status":{"value":"permitted","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Historical signed authorization, not installed equipment, observed operation or certification of every current condition.","locator":"Signed amendment cover"},"historical_permit_basis":{"value":"Historical issued permit","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Only the dated building 3 amendment and the referenced modified conditions are admitted as issued requirements.","locator":"Signed cover and all five condition pages"},"fty01_amendment_basis":{"value":"Building 3 addition only with unresolved narrative source codes","source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-ms-fty01-narrative-on29541-20261024"],"scope":"The numerical count belongs to the addition described on the signed cover, not an aggregate campus inventory calculated from the narrative table.","locator":"Signed cover addition clause; narrative equipment table, page 2"},"issued_on":{"value":"2025-04-15","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Signed issuance day, not startup, completion, checked date or narrative publication.","locator":"Signed cover issuance heading"},"application_on":{"value":"2024-12-19","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Application date, separate from agency receipt and later authorization.","locator":"Signed cover reason for amendment"},"application_received_on":{"value":"2024-12-26","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Agency receipt stated on the cover, not approval or operation.","locator":"Signed cover reason for amendment"},"narrative_heading_on":{"value":"2025-02-11","source_ids":["ga-ms-fty01-narrative-on29541-20261024"],"scope":"Original narrative heading. Completed addendum discusses later March comments, so this is not the publication day of all captured narrative bytes.","locator":"Narrative page 1 heading and pages 8 through 11 addendum"},"permit_identifier":{"value":"7376 097 0097 S 01 2","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Issued amendment identifier. The cover first references a base prefix 7373, then makes the amendment part of a base prefix 7376. That source difference is retained without silently repairing either identifier.","locator":"Signed cover heading and first and final paragraphs"},"facility_address":{"value":"1601 North River Road, Douglasville, Georgia 30122, Douglas County","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Facility address from the signed permit, distinct from the Redmond mailing address. No exact Atlas building or metropolitan water report join.","locator":"Signed cover facility and mailing address blocks"},"generator_count":{"value":21,"source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Twenty one additional generators in building 3 only: twenty rated 3,000 kW and one rated 500 kW. This is not a total campus inventory or count of installed or operating engines.","locator":"Signed cover amendment clause","unit":"generators","measurement_role":"permitted_equipment","measure_scope":"Building 3 additional generators only"},"equipment_code_difference":{"value":"The narrative table labels GN43 as a 500 kW engine and also includes GN43 within its 3,000 kW range GN43 through GN63.","source_ids":["ga-ms-fty01-narrative-on29541-20261024","ga-ms-fty01-issued-op29541-20250415"],"scope":"The signed cover explicitly describes twenty plus one additional generators. No sixty three engine aggregate or corrected replacement source code is computed from this conflicting table.","locator":"Narrative page 2 equipment table; signed cover addition clause"},"construction_year_difference":{"value":"The narrative equipment table lists 2026 for building 3 installation and construction, while its federal applicability discussion says planned construction in 2025.","source_ids":["ga-ms-fty01-narrative-on29541-20261024"],"scope":"These are inconsistent planning statements, not verified construction, installation or operation dates.","locator":"Narrative pages 2 and 4"},"state_operating_conditions":{"value":"Condition 2.5 requires less than 500 annual operating hours per generator, with operation limited to routine testing and maintenance, utility power loss or internal system failures and recorded reasons.","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Applies to GN1 through GN63. This strict annual condition is not relaxed by a notification duty at equality and does not establish actual hours.","locator":"Amendment condition 2.5, printed page 2"},"seasonal_testing":{"value":"Routine testing and maintenance from May through September is allowed only from 10 p.m. through 4 a.m.; other months allow it at any time of day.","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"A testing condition, not an observed operating schedule or general nighttime emergency restriction.","locator":"Amendment condition 2.5(c), printed page 2"},"federal_calendar_allowances":{"value":"Condition 2.3 describes up to 100 hours per calendar year for maintenance and readiness testing, with the stated petition or required testing provisions. The nonemergency allowance is up to 50 hours per calendar year counted within that 100 hours.","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"The fifty hours are not additional to the hundred. Financial arrangements and demand response are restricted subject to the stated conditional dispatch provisions. Separate state operating conditions still apply.","locator":"Amendment condition 2.3(b), (c) and (c)(i), printed pages 1 and 2"},"federal_emergency_clause":{"value":"Condition 2.3(a) states no time limit for emergency situations under that federal emergency engine clause.","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"This does not remove the separate state condition requiring less than 500 total annual hours per generator or establish actual emergency operation.","locator":"Amendment conditions 2.3(a) and 2.5(b)"},"fuel":{"value":"Diesel fuel with maximum sulfur content 15 ppm, plus a minimum cetane index of 40 or maximum aromatic content 35 volume percent.","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Fuel specification, not a laboratory test, fuel consumption report or authorization for every alternative fuel mentioned in the narrative.","locator":"Amendment condition 2.4, printed page 2"},"monitoring_and_records":{"value":"Monthly emergency and nonemergency operating records must use each engine hour meter and retain the operating reason and records for five years. Operating and monitoring equipment must be maintained under the stated monitoring provisions.","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Monitoring and retention duties, not actual logs or a finding of compliance.","locator":"Amendment conditions 5.2 and 7.2, printed page 3"},"hours_notification_triggers":{"value":"Conditions 7.3 and 7.4 require written notice within 15 days when a generator rolling twelve month total equals or exceeds 500 total hours or 100 nonemergency hours respectively.","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"The equality triggers are notification duties, not permission to operate 500 hours, calendar year allowances, actual exceedances or actual filed notices.","locator":"Amendment conditions 7.3 and 7.4, printed page 4"},"nox_notification_triggers":{"value":"Conditions 7.5 and 7.6 require notice within 15 days when calculated combined NOx equals or exceeds 8.25 tons in a calendar month or 99 tons over a rolling twelve month period.","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"These are the explicit amended notification thresholds. Referenced unchanged condition 2.2 is not reproduced in this amendment. No measured emissions, actual exceedance or complete base permit annual limit is independently assigned.","locator":"Amendment conditions 7.5 and 7.6, printed pages 4 and 5"},"emissions_calculation":{"value":"Monthly calculations use recorded hours and the source load specific emission rate table, with the next highest listed load for intermediate loads.","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"A prescribed calculation method and source factors, not an actual measured or reported pollutant quantity retained here.","locator":"Amendment condition 7.5 and load rate table, printed pages 4 and 5"},"source_cross_reference_difference":{"value":"Condition 2.3(c) refers to condition 2.4(c)(i), while its dispatch subparagraph appears under 2.3(c)(i). Fuel shipment condition 5.3 refers to condition 2.8, which is not reproduced here.","source_ids":["ga-ms-fty01-issued-op29541-20250415"],"scope":"Original references retained as unresolved source wording. No corrected legal cross reference or complete base requirement is substituted.","locator":"Amendment printed pages 1 and 3"},"emissions_model_scope":{"value":"The narrative calculates potential and constrained emissions using manufacturer information and other factors. Its toxic impact analysis uses a 200 hours per year assumption for long term benzene modeling.","source_ids":["ga-ms-fty01-narrative-on29541-20261024"],"scope":"The model assumption is not the operating cap. A column labeled Actual Emissions in this application analysis is not admitted as measured releases, exposure, current compliance or a health finding.","locator":"Narrative emissions summary pages 2 and 3; toxic impact assessment pages 5 through 7"},"corrected_comment_history":{"value":"The narrative initially says no comments were received by the February advisory deadline. Its addendum acknowledges a February 7 letter receipt problem and says that initial statement was erroneous; it also describes a March 28 letter.","source_ids":["ga-ms-fty01-narrative-on29541-20261024"],"scope":"The completed addendum corrects the initial receipt claim. Agency responses summarize comments; the full letters are not present in the captured appendix and were not read.","locator":"Narrative page 1 and addendum pages 8 and 10"},"public_period_source_difference":{"value":"The addendum opening says public review ended March 29, 2025, while its later receipt discussion refers to a March 28 ending.","source_ids":["ga-ms-fty01-narrative-on29541-20261024"],"scope":"Both source statements retained. No reconciled exact public review closing day is assigned. Neither day is the April permit issuance.","locator":"Narrative addendum pages 8 and 10"},"amendment_review_scope":{"value":"The complete six page issued amendment and twelve page narrative were read. The earlier base permit and June 2024 amendment were linked in the official index but not substantively reviewed.","source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-microsoft-public-index-20261024"],"scope":"The amendment carries forward unchanged base requirements. A filtered index and historical amendment do not certify the full current unamended permit chain.","locator":"Signed cover continuation clause; official FTY01 result rows"},"aggregate_campus_inventory":{"value":null,"source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-ms-fty01-narrative-on29541-20261024"],"scope":"The admitted count is the building 3 addition only. No reconciled aggregate is computed from the conflicting source code table.","locator":"Bounded final amendment and narrative review","unknown_reason":"The admitted count is the building 3 addition only. No reconciled aggregate is computed from the conflicting source code table."},"current_permit_validity":{"value":null,"source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-ms-fty01-narrative-on29541-20261024"],"scope":"The complete current permit chain and all unchanged base conditions have not been reviewed.","locator":"Bounded final amendment and narrative review","unknown_reason":"The complete current permit chain and all unchanged base conditions have not been reviewed."},"actual_installed_equipment":{"value":null,"source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-ms-fty01-narrative-on29541-20261024"],"scope":"No verified as built inventory or installation record reviewed.","locator":"Bounded final amendment and narrative review","unknown_reason":"No verified as built inventory or installation record reviewed."},"actual_generation":{"value":null,"source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-ms-fty01-narrative-on29541-20261024"],"scope":"No actual generated electricity reviewed.","locator":"Bounded final amendment and narrative review","unknown_reason":"No actual generated electricity reviewed."},"actual_started_on":{"value":null,"source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-ms-fty01-narrative-on29541-20261024"],"scope":"No actual commissioning or startup date verified.","locator":"Bounded final amendment and narrative review","unknown_reason":"No actual commissioning or startup date verified."},"actual_diesel_consumption":{"value":null,"source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-ms-fty01-narrative-on29541-20261024"],"scope":"No actual fuel consumption quantity reviewed.","locator":"Bounded final amendment and narrative review","unknown_reason":"No actual fuel consumption quantity reviewed."},"measured_emissions":{"value":null,"source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-ms-fty01-narrative-on29541-20261024"],"scope":"Narrative calculations and modeled concentrations are not measured emissions.","locator":"Bounded final amendment and narrative review","unknown_reason":"Narrative calculations and modeled concentrations are not measured emissions."},"actual_compliance":{"value":null,"source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-ms-fty01-narrative-on29541-20261024"],"scope":"No actual compliance finding, filed notification or measured exceedance reviewed.","locator":"Bounded final amendment and narrative review","unknown_reason":"No actual compliance finding, filed notification or measured exceedance reviewed."},"atlas_record_id":{"value":null,"source_ids":["ga-ms-fty01-issued-op29541-20250415","ga-ms-fty01-narrative-on29541-20261024"],"scope":"No exact Atlas building, parcel or operating record join established. The Microsoft Atlanta water disclosure is a separate metropolitan scope.","locator":"Bounded final amendment and narrative review","unknown_reason":"No exact Atlas building, parcel or operating record join established. The Microsoft Atlanta water disclosure is a separate metropolitan scope."}}},{"id":"air-ga-equinix-atlanta-20260630","kind":"generator_permit","subject":"Equinix Atlanta dated permit for 149 generators and separate fire pump","state_codes":["ga"],"scope":"Issued June 2026 air permit with conditional construction and operation, distinct engine table limits and retained source reference differences. Permission is not installed inventory, actual emissions, actual fuel or current operation.","fields":{"status":{"value":"permitted","source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-public-permit-search-20261024"],"scope":"Signed issued air permit for conditional construction and operation, not proof of actual construction, startup, installed generators or current operation.","locator":"Signed permit cover and matching public search issuance row"},"engine_table_limit_basis":{"value":"Issued permit with distinct general and engine table limits","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"The specific engine table, general criteria and federal provisions remain separate. No blanket five hundred hour operating allowance is inferred.","locator":"Permit conditions 1.5,2.2,2.5 and 2.11"},"permit_number":{"value":"7374-151-0068-E-01-0","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"Exact issued permit identifier, not a campus operating license or an approval of every other project permit.","locator":"Permit cover and all page headers"},"airs_number":{"value":"04-13-151-00068","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"Exact agency facility identifier in this document. No separate Atlas facility record is joined.","locator":"Permit cover"},"issued_on":{"value":"2026-06-30","source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-public-permit-search-20261024"],"scope":"Actual permit issuance day, not a generator startup or electricity service date.","locator":"Signed cover issuance date and official public index"},"application_on":{"value":"2025-10-03","source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"Application day referenced by both permit and narrative; differing application numbers are retained separately.","locator":"Permit cover application reference and narrative page 1"},"review_memo_dated_on":{"value":"2025-11-25","source_ids":["ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"Explicit narrative memo header date, not the final permit issuance or exact publication day.","locator":"Narrative page 1 date"},"public_advisory_opened_on":{"value":"2025-10-08","source_ids":["ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"Narrative reports a public advisory issued on this day. Underlying advisory and every comment were not independently reviewed.","locator":"Narrative page 2 advisory paragraph"},"public_advisory_closed_on":{"value":"2025-11-07","source_ids":["ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"Narrative reports that advisory expired on this day, distinct from final June 2026 issuance.","locator":"Narrative page 2 advisory paragraph"},"facility_address":{"value":"1100 Site Parkway, Hampton, Georgia 30228, Henry County","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"Address printed on this permit. Not a parcel geometry, exact site point or proof the facility is operating.","locator":"Permit cover"},"generator_count":{"value":149,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"Permitted diesel emergency standby generators. The separate fire pump is excluded from this count. Not installed equipment or actual operation.","locator":"Permit cover authorization","unit":"generators","measurement_role":"permitted_equipment"},"separate_fire_pump":{"value":"One diesel fired fire pump is authorized in addition to the 149 emergency generators.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"Cover distinguishes the pump from generators even though some permit conditions call all source codes emergency generators. No count of 150 generators is inferred.","locator":"Permit cover and Attachment A"},"rated_equipment_schedule":{"value":"Attachment A lists EG1 through EG144 at 3.62 MW, EG145 through EG148 at 1.0 MW, EG149 at 0.25 MW, and EG150 at 210 HP.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"Literal equipment schedule categories and units, not a summed IT load, utility contract capacity or a conversion of horsepower into MW.","locator":"Attachment A, PDF page 2"},"general_hour_criteria":{"value":"Condition 2.2 permits emergency, routine testing and maintenance or internal system failure uses under stated criteria, including less than 500 hours per year for each generator.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"General annual criteria do not override the stricter engine table in condition 2.11. The conditional alternate NOx standard in 2.2 is not an actual exceedance or an automatic exemption from other permit limits.","locator":"Conditions 2.2 a through 2.2 d, PDF pages 3 through 4"},"specific_rolling_hour_limits":{"value":"Condition 2.11 prohibits exceeding its engine table hours in any twelve consecutive months. The table prints 37 hours for the 3.5 MW engine class and 39 hours for the 1.0 MW, guard shack and fire pump entries.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"Specific rolling period limits, not annual expected use, model assumptions, calendar year totals or actual operation. Table capacity labels and equipment tags differ from Attachment A and are not silently remapped.","locator":"Condition 2.11 and Table 2.11.1, PDF page 7"},"strictest_condition":{"value":"Condition 1.5 says the most stringent permit condition prevails when permit conditions conflict for a source or operation.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"The federal emergency time statement does not erase the specific state permit engine table limits. This is a summary of this dated permit, not independent adjudication of a current facility compliance question.","locator":"Condition 1.5, PDF page 3"},"seasonal_test_window":{"value":"Routine testing and maintenance during May through September occurs only between 10 p.m. and 4 a.m. The other listed months allow those activities at any time of day.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"A permit time window for testing and maintenance, not a measured nighttime event, an emergency operation curfew or a finding about noise.","locator":"Condition 2.2 c, PDF page 4"},"federal_nonemergency_limits":{"value":"The permit prints a maximum of 100 hours per calendar year for ordinary maintenance and readiness testing, with specified petition or required testing exceptions. Up to 50 nonemergency hours are included within that 100 hour category.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"The 50 hours are not added to 100. The printed federal emergency provision has no time limit, but the other permit conditions and stricter engine table still apply. Current full federal rule text was not separately reviewed.","locator":"Conditions 2.5 a through 2.5 c, PDF pages 4 through 5"},"nonemergency_dispatch_conditions":{"value":"The permit prohibits ordinary peak shaving, nonemergency demand response and financial power arrangements, except a stated local reliability dispatch pathway requiring all listed conditions.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"The narrow exception requires authorized local dispatch, transmission or distribution limitation mitigation, specified reliability protocols, limited recipients and dispatch records. Not a blanket approved grid service or proof the pathway was used.","locator":"Condition 2.5 c.i A through E, PDF page 5"},"nox_limit_scope":{"value":"Condition 2.1 limits emissions from listed codes EG1 through EG150 to 249 tons per twelve consecutive months.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"A permitted emission cap including the listed pump code, not measured pollution, a per generator allowance, a calendar year reading or a metric ton conversion. The source calculation uses 2000 pounds per ton.","locator":"Condition 2.1, PDF page 3 andcondition 7.8 formula, PDF page 11"},"monitoring_requirements":{"value":"Each listed engine requires a nonresettable hour meter, operating reason and cumulative hour records, plus a nonresettable fuel consumption meter.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"Monitoring duties and record specifications, not evidence that a meter is installed, a public continuous emissions feed or actual fuel consumption.","locator":"Conditions 5.2 and 7.2, PDF pages 8 and 10"},"startup_notice":{"value":"Startup notification is required within fifteen days after startup.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"After startup deadline, not a notice due before startup or evidence a startup notice was filed.","locator":"Condition 7.1, PDF page 10"},"hour_notification_scope":{"value":"The permit requires monthly rolling hour calculations and written notice within fifteen days when specified emergency hours equal or exceed 500, nonemergency hours equal or exceed 100, or the engine table thresholds are reached.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"These are notification triggers, not additional operating allowances or actual violations. Condition 7.10 requests calculations using emergency plus nonemergency data but its notice clause refers to emergency service time; that wording difference is retained.","locator":"Conditions 7.3,7.4 and 7.10, PDF pages 10 and 12"},"emission_notification_scope":{"value":"Written notice within fifteen days is required if facility NOx exceeds 20.75 tons in a calendar month or 249 tons on a twelve month rolling basis.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"Different monthly notification and rolling cap periods, not two measured emissions values or independent compliance findings. No hours or pollution are inferred from the notification duty.","locator":"Conditions 7.8 and 7.9, PDF pages 11 through 12"},"application_reference_difference":{"value":"The signed permit cover references application 29889, while the public document links and narrative identify 29899.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-public-permit-search-20261024","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"Source identifier difference retained. No silent replacement or second facility application is invented.","locator":"Permit cover versus public OP29899/ON29899 links and narrative page 1"},"capacity_and_tag_differences":{"value":"Attachment A uses EG1 through EG150 and a 3.62 MW large engine row. The hour table uses E1 through E150 and a 3.5 MW column. The narrative equipment list uses different E code groups and explains different engine choices for modeled criteria pollutants and toxics.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"No exact mapping between conflicting tags or capacity descriptions is repaired. Narrative worst case modeling is not actual engine inventory, measured output or present operating load.","locator":"Attachment A; condition 2.11 table; narrative page 2"},"construction_date_boundary":{"value":"Attachment A prints 2025 or later for construction and installation categories.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630"],"scope":"A broad schedule entry, not an actual completed construction, installation or startup date.","locator":"Attachment A, PDF page 2"},"source_review_boundary":{"value":"All twelve issued permit pages and only the first five of nineteen narrative pages were read.","source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"Nine relevant originals actually viewed. Remaining narrative pages, the complete underlying application, later amendments, operating records and current full federal rules were not reviewed or certified as a complete governing stack.","locator":"Complete permit and bounded narrative pages 1 through 5"},"actual_started_on":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"No actual startup day or filed startup notice reviewed.","locator":"Bounded issued permit and narrative only","unknown_reason":"No actual startup day or filed startup notice reviewed."},"actual_installed_equipment":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"No actual installation inventory established from the permission.","locator":"Bounded issued permit and narrative only","unknown_reason":"No actual installation inventory established from the permission."},"actual_annual_hours":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"No actual engine operating hour records reviewed.","locator":"Bounded issued permit and narrative only","unknown_reason":"No actual engine operating hour records reviewed."},"measured_emissions":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"The emission cap and potential calculations are not measured pollution.","locator":"Bounded issued permit and narrative only","unknown_reason":"The emission cap and potential calculations are not measured pollution."},"measured_fuel_consumption":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"No actual fuel meter records reviewed.","locator":"Bounded issued permit and narrative only","unknown_reason":"No actual fuel meter records reviewed."},"actual_compliance":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"No independent current compliance finding established.","locator":"Bounded issued permit and narrative only","unknown_reason":"No independent current compliance finding established."},"actual_test_results":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"No actual performance test reports reviewed.","locator":"Bounded issued permit and narrative only","unknown_reason":"No actual performance test reports reviewed."},"total_capacity_mw":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"No aggregate generator or IT electrical capacity calculated.","locator":"Bounded issued permit and narrative only","unknown_reason":"No aggregate generator or IT electrical capacity calculated."},"resolved_source_tag_map":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"Equipment codes and capacity labels differ between attachment, table and narrative; no repaired mapping established.","locator":"Bounded issued permit and narrative only","unknown_reason":"Equipment codes and capacity labels differ between attachment, table and narrative; no repaired mapping established."},"current_governing_permit":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"Later amendments and complete current governing edition not certified by this bounded review.","locator":"Bounded issued permit and narrative only","unknown_reason":"Later amendments and complete current governing edition not certified by this bounded review."},"latest_federal_rule":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"Current full federal rule text not separately reviewed.","locator":"Bounded issued permit and narrative only","unknown_reason":"Current full federal rule text not separately reviewed."},"complete_application":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"The complete underlying application and all appendices were not reviewed.","locator":"Bounded issued permit and narrative only","unknown_reason":"The complete underlying application and all appendices were not reviewed."},"atlas_record_id":{"value":null,"source_ids":["ga-equinix-atlanta-issued-op29899-20260630","ga-equinix-atlanta-narrative-on29899-20261024"],"scope":"No exact Atlas facility or parcel joined.","locator":"Bounded issued permit and narrative only","unknown_reason":"No exact Atlas facility or parcel joined."}}},{"id":"air-ga-ms-cco06-20250604","kind":"generator_permit","subject":"Microsoft CCO06 dated 121 generator replacement permit","state_codes":["ga"],"scope":"Dated June 2025 air construction authorization, distinct calendar and rolling clocks, replacement permit and startup triggered application duty. Permitted is not operating.","fields":{"status":{"value":"permitted","source_ids":["ga-ms-cco06-issued-op29582-20250604","ga-ms-cco06-public-index-20261024"],"scope":"Issued dated conditional construction permit. Not installed generators, current operation, current full permit stack or proof all project approvals exist.","locator":"Signed cover and matching public index"},"cco06_permit_basis":{"value":"Issued replacement permit with separate calendar and rolling clocks","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"The complete dated permit controls this summary; narrative proposals and equipment years are kept separate from operating facts.","locator":"Cover and conditions 1.5, 2.2, 2.3, 2.5, 7.2 through 7.5 and 8.3 through 8.4"},"permit_number":{"value":"7376-121-0968-E-02-0","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Exact printed identifier. No independent operating status inferred.","locator":"Permit cover"},"airs_number":{"value":"04-13-121-00968","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Agency facility identifier in this permit, not a joined Atlas record.","locator":"Permit cover"},"issued_on":{"value":"2025-06-04","source_ids":["ga-ms-cco06-issued-op29582-20250604","ga-ms-cco06-public-index-20261024"],"scope":"Permit issuance day, not generator startup or service day.","locator":"Signed cover"},"application_on":{"value":"2025-01-31","source_ids":["ga-ms-cco06-issued-op29582-20250604","ga-ms-cco06-narrative-on29582-20261024"],"scope":"Referenced application day, not receipt, issuance or construction completion.","locator":"Permit cover and narrative page 1"},"application_received_on":{"value":"2025-02-03","source_ids":["ga-ms-cco06-narrative-on29582-20261024"],"scope":"Receipt day explicitly described in the dated narrative.","locator":"Narrative page 1"},"review_memo_dated_on":{"value":"2025-03-20","source_ids":["ga-ms-cco06-narrative-on29582-20261024"],"scope":"Narrative header day, not final permit issuance or exact online publication.","locator":"Narrative page 1"},"facility_address":{"value":"0 Williams Road, Palmetto, Georgia 30268, Fulton County","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Address printed in this permit. No parcel geometry, precise point or operating status inferred.","locator":"Permit cover"},"generator_count":{"value":121,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Permitted equipment count from the cover categories and GN1 through GN121 source range. Not an installed inventory or an additional 121 on top of older permits.","locator":"Cover and repeated GN1 through GN121 conditions","unit":"generators","measurement_role":"permitted_equipment"},"rated_generator_categories":{"value":"The cover authorizes 116 emergency generators rated 3000 kW each and five rated 500 kW each for Buildings 1 through 5.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Electrical ratings and categories, not a summed IT load, approved utility capacity or actual output.","locator":"Permit cover"},"new_vs_prior_scope":{"value":"The review describes a request to add eighty 3000 kW and three 500 kW generators for Buildings 3 through 5. Its equipment schedule extends through GN121 across all five buildings.","source_ids":["ga-ms-cco06-narrative-on29582-20261024"],"scope":"The requested addition is not added again to the replacement permit total. Table construction and installation years are not independently verified startup dates.","locator":"Narrative pages 1 and 2"},"prior_permits_replaced":{"value":"Condition 8.4 revokes all previously issued Georgia air permits for this facility, including the named S 01 0 permit and its amendments.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"A replacement authorization. Old and new permit counts are not summed as independent operating fleets. This review does not certify a later Title V issuance or current complete stack.","locator":"Condition 8.4, PDF page 9"},"nox_limit_scope":{"value":"The entire facility must remain below 249 tons of NOx during any twelve consecutive month period.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Condition 2.2 prohibits emissions equal to or greater than 249 tons. A rolling cap, not measured pollution, a per generator allowance or a calendar year inventory. The calculation uses 2000 pounds per ton; no metric conversion made.","locator":"Condition 2.2, PDF page 2 and formula PDF page 8"},"general_hour_criteria":{"value":"Condition 2.5 lists routine testing and maintenance, utility power unavailability or internal failures, with total operation for each generator less than 500 hours per year.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"The dated state criterion is distinct from federal calendar year maintenance and the later rolling notice tests. Conditional alternate ozone season NOx provisions do not establish an actual exceedance or erase other requirements.","locator":"Conditions 2.5 a through d, PDF page 4"},"federal_calendar_limits":{"value":"The permit prints 100 hours per calendar year for ordinary maintenance and readiness testing with specified petition or required testing exceptions. Its 50 nonemergency hours are included in that 100 hour category.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Fifty is not added to one hundred. The printed federal emergency time statement has no limit, but condition 1.5 retains the most stringent permit condition when provisions conflict. Current complete federal rules were not separately reviewed.","locator":"Conditions 1.5 and 2.3, PDF pages 2 through 4"},"dispatch_exception":{"value":"Ordinary peak shaving, nonemergency demand response and financial power arrangements are prohibited except a local reliability dispatch pathway requiring every listed condition.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Conditional dispatch authority, system limitation mitigation, protocols, recipients and records are required. Not proof of actual dispatch or blanket grid service eligibility. The text refers to condition 2.4.c.i while the printed exception is organized under 2.3.c.i; that cross reference is not silently repaired.","locator":"Conditions 2.3 c through E, PDF pages 3 through 4"},"seasonal_test_window":{"value":"Routine testing and maintenance during May through September occurs only between 10 p.m. and 4 a.m. The other listed months allow those activities at any time of day.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Permit scheduling requirement, not a measured event, noise finding or emergency curfew.","locator":"Condition 2.5 c, PDF page 4"},"rolling_hour_notices":{"value":"Monthly calculations of twelve month rolling hours trigger written notice within fifteen days at 500 hours of total operation or at 100 hours of nonemergency operation for any generator.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Rolling notice triggers differ from the printed calendar year federal maintenance limit. Notice thresholds are not added allowances or actual reported exceedances.","locator":"Conditions 7.2 and 7.3, PDF page 7"},"monthly_and_rolling_nox_notices":{"value":"NOx calculation and written notification within fifteen days use separate triggers of 20.75 tons during a calendar month and 249 tons during a twelve month rolling period.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"A monthly notice level is not the rolling emission cap. Neither number is actual emissions or an annual calendar inventory.","locator":"Conditions 7.4 and 7.5, PDF pages 7 through 8"},"fuel_requirements":{"value":"The issued permit specifies diesel fuel with maximum sulfur of 15 ppm and either minimum cetane index of 40 or maximum aromatic content of 35 volume percent, plus its listed distillate fuel specifications.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Fuel specifications are not gallons used, an actual renewable diesel share or an emissions reduction. The narrative discusses renewable hydrocarbon diesel separately; no separate current fuel eligibility adjudication made.","locator":"Conditions 2.4, 2.8, 5.3 and 7.8, PDF pages 4 through 6 and 9"},"monitoring_duties":{"value":"Each generator requires a nonresettable hour meter, operating reasons and cumulative hour records. Monthly emergency and nonemergency records are retained for five years.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"Requirements to monitor and preserve records, not evidence that meters or records exist or compliance was achieved.","locator":"Conditions 5.1, 5.2 and 7.1, PDF pages 5 through 7"},"title_v_application_clock":{"value":"Within twelve months after startup of new generators GN39 through GN121, a complete Part 70 application must be submitted.","source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"An application duty triggered by startup, not an issued Title V permit, a known startup day, a fixed calendar filing deadline or evidence that a filing was made.","locator":"Condition 8.3, PDF page 9"},"source_reference_differences":{"value":"The issued cover and narrative first page identify application 29582. Later narrative page headers print 29852. The narrative discusses prior 99 ton limits and requested expansion, while the issued permit gives its own rolling 249 ton condition.","source_ids":["ga-ms-cco06-issued-op29582-20250604","ga-ms-cco06-narrative-on29582-20261024"],"scope":"Source identifier and scope differences retained. Narrative equipment years and columns labeled Actual Emissions are not promoted into measured operations, startup or current compliance.","locator":"Permit cover; narrative pages 1 through 5"},"review_boundary":{"value":"The complete nine page issued permit and first five pages of the forty three page narrative were read, together with the substantive public index. Nine relevant original PDF pages were actually viewed.","source_ids":["ga-ms-cco06-issued-op29582-20250604","ga-ms-cco06-narrative-on29582-20261024","ga-ms-cco06-public-index-20261024"],"scope":"Remaining narrative pages, full application, underlying monitoring records, later permits and current federal legal stack were not reviewed as complete evidence. This dated document is not a current operating census.","locator":"Bounded source review"},"startup_on":{"value":null,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"No actual startup day established.","locator":"Dated permit and bounded narrative only","unknown_reason":"No actual startup day established."},"installed_generator_count":{"value":null,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"No physical installed generator inventory established.","locator":"Dated permit and bounded narrative only","unknown_reason":"No physical installed generator inventory established."},"actual_operating_hours":{"value":null,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"No actual operating hour records reviewed.","locator":"Dated permit and bounded narrative only","unknown_reason":"No actual operating hour records reviewed."},"actual_nox_emissions":{"value":null,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"No measured emissions inventory established.","locator":"Dated permit and bounded narrative only","unknown_reason":"No measured emissions inventory established."},"actual_fuel_used":{"value":null,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"No actual fuel deliveries or gallons used established.","locator":"Dated permit and bounded narrative only","unknown_reason":"No actual fuel deliveries or gallons used established."},"actual_compliance":{"value":null,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"No current compliance finding established.","locator":"Dated permit and bounded narrative only","unknown_reason":"No current compliance finding established."},"title_v_filed_on":{"value":null,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"No actual subsequent Part 70 application filing reviewed.","locator":"Dated permit and bounded narrative only","unknown_reason":"No actual subsequent Part 70 application filing reviewed."},"current_permit_stack":{"value":null,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"No complete current permit chain certified.","locator":"Dated permit and bounded narrative only","unknown_reason":"No complete current permit chain certified."},"total_it_capacity":{"value":null,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"No facility IT demand or actual generator output established.","locator":"Dated permit and bounded narrative only","unknown_reason":"No facility IT demand or actual generator output established."},"atlas_record_id":{"value":null,"source_ids":["ga-ms-cco06-issued-op29582-20250604"],"scope":"No exact Atlas facility, parcel or project record join made.","locator":"Dated permit and bounded narrative only","unknown_reason":"No exact Atlas facility, parcel or project record join made."}}},{"id":"air-egrid-state-2023-ga","subject":"Georgia historical2023 electricity-generation emissions","kind":"emissions_context","state_codes":["ga"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","fields":{"status":{"value":"historical","source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 Data Year column"},"egrid_report_year":{"value":"2023","source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 YEAR column"},"egrid_state_fips":{"value":"13","source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 FIPSST column"},"egrid_state_basis":{"value":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 labels,codes,units and review scope"},"egrid_annual_net_generation":{"value":129220273.258,"source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 GA row 13, STNGENAN (State annual net generation (MWh))","unit":"MWh","measurement_role":"reported_egrid_annual_net_generation","source_token":"129220273.258"},"egrid_annual_nox_emissions":{"value":18438.114,"source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 GA row 13, STNOXAN (State annual NOx emissions (tons))","unit":"tons","measurement_role":"reported_egrid_annual_nox_emissions","source_token":"18438.114000000001"},"egrid_annual_so2_emissions":{"value":12892.404,"source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 GA row 13, STSO2AN (State annual SO2 emissions (tons))","unit":"tons","measurement_role":"reported_egrid_annual_so2_emissions","source_token":"12892.404"},"egrid_annual_co2_emissions":{"value":46120743.102,"source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 GA row 13, STCO2AN (State annual CO2 emissions (tons))","unit":"tons","measurement_role":"reported_egrid_annual_co2_emissions","source_token":"46120743.101999998"},"egrid_nox_total_output_rate":{"value":0.285,"source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 GA row 13, STNOXRTA (State annual NOx total output emission rate (lb/MWh))","unit":"lb per MWh","measurement_role":"reported_egrid_nox_total_output_rate","source_token":"0.28499999999999998"},"egrid_so2_total_output_rate":{"value":0.2,"source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 GA row 13, STSO2RTA (State annual SO2 total output emission rate (lb/MWh))","unit":"lb per MWh","measurement_role":"reported_egrid_so2_total_output_rate","source_token":"0.2"},"egrid_co2_total_output_rate":{"value":713.831,"source_ids":["epa-egrid2023-states-rev2"],"scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.","locator":"ST23 GA row 13, STCO2RTA (State annual CO2 total output emission rate (lb/MWh))","unit":"lb per MWh","measurement_role":"reported_egrid_co2_total_output_rate","source_token":"713.83100000000002"},"egrid_annual_ch4_emissions_lb":{"value":7079195.597,"source_ids":["epa-egrid2023-states-rev2"],"scope":"Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.","locator":"ST23 GA row 13, STCH4AN (State annual CH4 emissions (lbs))","unit":"lbs","measurement_role":"reported_egrid_annual_ch4_emissions","source_token":"7079195.5970000001"},"egrid_annual_co2e_emissions":{"value":46354208.308,"source_ids":["epa-egrid2023-states-rev2"],"scope":"Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.","locator":"ST23 GA row 13, STCO2EQA (State annual CO2 equivalent emissions (tons))","unit":"tons","measurement_role":"reported_egrid_annual_co2e_emissions","source_token":"46354208.307999998"},"egrid_annual_n2o_emissions_lb":{"value":1014011.081,"source_ids":["epa-egrid2023-states-rev2"],"scope":"Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.","locator":"ST23 GA row 13, STN2OAN (State annual N2O emissions (lbs))","unit":"lbs","measurement_role":"reported_egrid_annual_n2o_emissions","source_token":"1014011.081"},"egrid_ozone_season_nox_total_output_rate":{"value":0.222,"source_ids":["epa-egrid2023-states-rev2"],"scope":"Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.","locator":"ST23 GA row 13, STNOXRTO (State ozone season NOx total output emission rate (lb/MWh))","unit":"lb per MWh","measurement_role":"reported_egrid_ozone_season_nox_total_output_rate","source_token":"0.222"},"egrid_extended_basis":{"value":"Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.","source_ids":["epa-egrid2023-states-rev2"],"scope":"Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.","locator":"ST23 field labels,report year and annual-versus-ozone-season units"},"egrid_ozone_season_nox_emissions":{"value":6754.113,"source_ids":["epa-egrid2023-states-rev2"],"scope":"Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.","locator":"ST23 GA row 13, STNOXOZ (State ozone season NOx emissions (tons))","unit":"tons","measurement_role":"reported_egrid_ozone_season_nox_emissions","source_token":"6754.1130000000003"},"egrid_co2e_total_output_rate":{"value":717.445,"source_ids":["epa-egrid2023-states-rev2"],"scope":"Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.","locator":"ST23 GA row 13, STC2ERTA (State annual CO2 equivalent total output emission rate (lb/MWh))","unit":"lb per MWh","measurement_role":"reported_egrid_co2e_total_output_rate","source_token":"717.44500000000005"},"egrid_ch4_total_output_rate":{"value":0.055,"source_ids":["epa-egrid2023-states-rev2"],"scope":"Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.","locator":"ST23 GA row 13, STCH4RTA (State annual CH4 total output emission rate (lb/MWh))","unit":"lb per MWh","measurement_role":"reported_egrid_ch4_total_output_rate","source_token":"5.5E-2"},"egrid_n2o_total_output_rate":{"value":0.008,"source_ids":["epa-egrid2023-states-rev2"],"scope":"Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.","locator":"ST23 GA row 13, STN2ORTA (State annual N2O total output emission rate (lb/MWh))","unit":"lb per MWh","measurement_role":"reported_egrid_n2o_total_output_rate","source_token":"8.0000000000000002E-3"}}},{"id":"air-eia-state-emissions-2025-ga","kind":"emissions_context","subject":"Georgia historical power and useful thermal emissions2025 and2024","state_codes":["ga"],"scope":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.","fields":{"status":{"value":"historical","source_ids":["eia-epa2025-state-emissions"],"scope":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.","locator":"Table9.5 years2025 and2024"},"eia_emissions_basis":{"value":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.","source_ids":["eia-epa2025-state-emissions"],"scope":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.","locator":"Table9.5 header and methodological notes"},"eia_emissions_co2_2025":{"value":43991.0,"source_ids":["eia-epa2025-state-emissions"],"scope":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.","locator":"Table9.5 Georgia row;co2;Year 2025","source_token":"43,991","unit":"thousand metric tons","measurement_role":"agency_estimated_generation_and_useful_thermal_emissions"},"eia_emissions_co2_2024":{"value":42718.0,"source_ids":["eia-epa2025-state-emissions"],"scope":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.","locator":"Table9.5 Georgia row;co2;Year 2024","source_token":"42,718","unit":"thousand metric tons","measurement_role":"agency_estimated_generation_and_useful_thermal_emissions"},"eia_emissions_so2_2025":{"value":40.0,"source_ids":["eia-epa2025-state-emissions"],"scope":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.","locator":"Table9.5 Georgia row;so2;Year 2025","source_token":"40","unit":"thousand metric tons","measurement_role":"agency_estimated_generation_and_useful_thermal_emissions"},"eia_emissions_so2_2024":{"value":40.0,"source_ids":["eia-epa2025-state-emissions"],"scope":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.","locator":"Table9.5 Georgia row;so2;Year 2024","source_token":"40","unit":"thousand metric tons","measurement_role":"agency_estimated_generation_and_useful_thermal_emissions"},"eia_emissions_nox_2025":{"value":34.0,"source_ids":["eia-epa2025-state-emissions"],"scope":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.","locator":"Table9.5 Georgia row;nox;Year 2025","source_token":"34","unit":"thousand metric tons","measurement_role":"agency_estimated_generation_and_useful_thermal_emissions"},"eia_emissions_nox_2024":{"value":35.0,"source_ids":["eia-epa2025-state-emissions"],"scope":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.","locator":"Table9.5 Georgia row;nox;Year 2024","source_token":"35","unit":"thousand metric tons","measurement_role":"agency_estimated_generation_and_useful_thermal_emissions"}}}],"sources":{"ga-final-op29644":{"url":"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644","title":"Georgia air quality permit7374-097-0101-S-01-0, Amazon ATL068 and ATL078","publisher":"Georgia Environmental Protection Division","published_on":"2025-08-18","date_note":null,"checked_at":"2026-10-23T14:32:00.064744+00:00","sha256":"0e9591b3fbeb73ad07735af7fbe12877fb00bbca4bad5822e2e65e417ea7544e","scope":"Dated issued permit for two colocated campuses, cover and operative printed pages3 and4 actually viewed. Conditional operating categories and exceptions remain distinct. Later amendments, actual equipment installation and operation are not established.","tier":"A","establishes_status":["permitted"]},"ga-atl089-final-op29883-20260629":{"url":"https://air.gaepd.org/Permits/View/OP-29883","title":"Georgia issued ATL089 air quality permit 7374 217 0078 E 01 0","publisher":"Georgia Environmental Protection Division","published_on":"2026-06-29","date_note":"","checked_at":"2026-10-24T00:01:50.626623+00:00","sha256":"5af7809c51c930bf63b589aa407dd2fe7ecb21f9be50bd9ca6db55cfd9b36519","scope":"Actual signed twelve page instrument fully read. Original PDF 1, 4, 5 and 12 viewed. This dated authorization establishes permitted inventory and terms, not installed equipment, current unamended authorization or actual operation.","tier":"A","establishes_status":["permitted"]},"ga-atl089-final-narrative-on29883":{"url":"https://air.gaepd.org/Permits/View/ON-29883","title":"Georgia application 29883 narrative and comment response","publisher":"Georgia Environmental Protection Division","published_on":null,"date_note":"Heading dated November 3, 2025; final addendum describes March and April 2026 review. A separate issuance or posting date of the full combined version is not stated.","checked_at":"2026-10-24T00:01:50.981798+00:00","sha256":"e362d1232290bd2f50f36eb748c7bd0023ec313e55dcf51ff7df18f509b054ba","scope":"Complete eleven page narrative read, originals 1, 2, 3 and 11 viewed. Main heading names ATL089 but gives AIRS 149 00013, and repeated headers name ATL086. Actual signed permit and current search establish the dated permit identity; these inconsistent labels are retained and not silently corrected. Referenced Appendix A is not present in this capture and is not reviewed. Potential emissions, proposed installation and modeling are not actuals.","tier":"A","establishes_status":[]},"ga-atl089-modern-public-search-20261023":{"url":"https://air.gaepd.org/Permits/Search?Name=Amazon&Permit=7374-217-0078","title":"Georgia public permit search result for ATL089","publisher":"Georgia Environmental Protection Division","published_on":null,"date_note":"Dynamic public search has no stated publication date. Checked date is the actual capture time.","checked_at":"2026-10-24T00:01:45.352550+00:00","sha256":"a98ef9f25793ffcc7d93958500f8f84c3d8492c64a80b67c8afd48524cf7fd1a","scope":"Observed public GET form from the actual redirected air.gaepd.org origin returns one ATL089 result for permit 7374 217 0078 E 01 0 dated June 29, 2026 and links the separately retained permit and narrative. Old domain search and JavaScript paths redirected to a search home page; those home HTML captures are not final permit documents or search results.","tier":"A","establishes_status":[]},"ga-atl057-issued-op28844-20230921":{"url":"https://air.gaepd.org/Permits/View/OP-28844","title":"Georgia issued ATL057 air quality permit dated September 21, 2023","publisher":"Georgia Environmental Protection Division","published_on":"2023-09-21","date_note":"Actual permit issuance date, not construction, startup or current unamended validity.","checked_at":"2026-10-24T01:26:23.995272+00:00","sha256":"388299b3e5724411a9654f434d8466119802a6f1f2c3c3817ec0253ee8f6c905","scope":"Complete signed eight page permit read. Original PDF pages 1, 3, 4 and 8 actually viewed. The cover authorizes construction and operation of a data center but gives no numerical generator inventory. Dated operating conditions do not establish actual installation, emissions or current unamended validity.","tier":"A","establishes_status":["permitted"]},"ga-atl057-narrative-on28844-20230921":{"url":"https://air.gaepd.org/Permits/View/ON-28844","title":"Georgia ATL057 application 28844 narrative and equipment plan","publisher":"Georgia Environmental Protection Division","published_on":null,"date_note":"Header dated May 4, 2023, while text describes Public Advisory expired May 26. PDF metadata September 25 is not proof of publication. Exact publication day of this combined document remains unknown.","checked_at":"2026-10-24T01:26:24.440618+00:00","sha256":"75db9250c91ad518ad2acdae1923d11af5b6cc03e097ff0272ffa09098430579","scope":"Complete five page narrative read, originals 1, 2 and 5 actually viewed. Seven units are a planned application inventory with phases in 2023, 2028 and 2037. The table headed Actual Emissions is not independently verified measured emissions; surrounding text describes vendor data, emission factors and a planned project. Future source status review and a recommendation to issue are separate from actual startup and the signed issued permit.","tier":"A","establishes_status":[]},"ga-dcb-east-issued-op29442-20250226":{"url":"https://air.gaepd.org/Permits/View/OP-29442","title":"Georgia DCB Atlanta East issued air permit 7374-247-0076-B-01-0","publisher":"Georgia Environmental Protection Division","published_on":"2025-02-26","date_note":"Printed issuance date, not an independently established online publication date or actual startup.","checked_at":"2026-10-24T02:23:55.224863+00:00","sha256":"f8615a338534c51495eb2f9aef47bd5bc0a4b4174bad507890ec391824487f76","scope":"Complete eight page issued permit fully read, including signed cover, all seven condition pages and exact six unit authorization. Original cover and PDF pages 3, 4, 6, 7 actually viewed. Only this dated instrument is established, not absence of later amendment or operation. The public search exact final link resolves the earlier old host 404 without replacing or erasing that failure.","tier":"A","establishes_status":["permitted"]},"ga-dcb-east-narrative-on29442-20261024":{"url":"https://air.gaepd.org/Permits/View/ON-29442","title":"Georgia DCB Atlanta East application 29442 narrative","publisher":"Georgia Environmental Protection Division","published_on":"2024-11-19","date_note":"Printed narrative heading date. Later online posting date is not established. The final addendum remains an unfilled template.","checked_at":"2026-10-24T02:23:55.148087+00:00","sha256":"de16e742dfdbb85ea7fc4acd73a2f30345040b964c904324e95a3d660be9b3a0","scope":"Complete ten page narrative fully read. Original pages 1, 2, 7, 10 actually viewed. Six proposed 3 MW units and expected 2025 through 2028 installation remain plans. The table labeled Actual Emissions is calculated from an assumed ten hour year, not measured emissions;200 hours is a modeling assumption. Final narrative addendum contains literal unfilled review dates and comments alternatives. Summary explanation conflicts with the final permit on startup notice timing and the 100 hour wording; final issued conditions are separately cited.","tier":"A","establishes_status":[]},"ga-dcb-public-index-20261024":{"url":"https://air.gaepd.org/Permits/Search?Name=DCB&Permit=","title":"Georgia public DCB permit search exact East and West results","publisher":"Georgia Environmental Protection Division","published_on":null,"date_note":"Exact webpage publication date is not supplied. Current checked date does not make the dated permits new approvals.","checked_at":"2026-10-24T02:23:32.080275+00:00","sha256":"9c77aa5f573f0d4b3432c40cedd034756c3a16932f8942ace51b42a8d47f2a00","scope":"Both exact DCB result rows and their final permit and narrative links read. East permit 29442 is dated February 26, 2025, distinct from West 29723 dated January 28, 2026. Only the East full permit and narrative are substantively reviewed here. West bodies are captured research leads and not admitted by this row.","tier":"A","establishes_status":[]},"ga-dcb-west-issued-op29723-20260128":{"url":"https://air.gaepd.org/Permits/View/OP-29723","title":"Georgia DCB Atlanta West issued synthetic minor air permit 7374-097-0102-S-01-0","publisher":"Georgia Environmental Protection Division","published_on":"2026-01-28","date_note":"Printed issuance date on the signed cover. Exact online publication day and actual startup are not established.","checked_at":"2026-10-24T02:23:55.111208+00:00","sha256":"0cb6d37711279bc1af275514c765c621d00bf3a4bb465398458b2eae9491f49e","scope":"Complete eleven page final issued permit fully read, signed cover and original PDF 2, 5 and 9 actually viewed. Total 76 emergency generators across two buildings and facilitywide fuel limit are authorized conditions, not installed equipment, fuel actually burned or actual emissions. Separate state and federal hour conditions, rolling fuel and hour notices and source cross reference issues retained.","tier":"A","establishes_status":["permitted"]},"ga-dcb-west-narrative-on29723-20261024":{"url":"https://air.gaepd.org/Permits/View/ON-29723","title":"Georgia DCB Atlanta West application 29723 complete narrative and public review addendum","publisher":"Georgia Environmental Protection Division","published_on":null,"date_note":"The original heading is dated August 8, 2025, while the same retained file contains December 2025 and January 2026 review responses and a January 16 comment appendix. That early heading is not a publication date for this later complete file. Exact final file publication day is unknown.","checked_at":"2026-10-24T02:23:55.340564+00:00","sha256":"1bd839ad32c71159f008e34af12511ca68cde9d1a87546e34f8cd4e0a051f271","scope":"All 24 pages fully read, including equipment tables, potential emissions calculations, regulatory assessment, toxic impact modeling, completed public review addendum and appended public comment letter. Original PDF 1, 5, 16 and 17 actually viewed. Plans, model results and received comments are separate from operation, measured releases and adopted requirements. Addendum says construction 2027 was changed to 2025 but the retained opening still prints 2027. The comment appendix secondary counts, health claims, grid forecasts and cited outside materials are not independently admitted.","tier":"A","establishes_status":[]},"ga-qts-fayetteville-op29366-20241017":{"url":"https://air.gaepd.org/Permits/View/OP-29366","title":"Georgia signed QTS Fayetteville October 17, 2024 amendment","publisher":"Georgia Environmental Protection Division","published_on":"2024-10-17","date_note":"Signed amendment issuance day.","checked_at":"2026-10-24T04:42:46.679498+00:00","sha256":"51c5ac209a77da6aa038b7dce13c574fca7892a3caa37cabf911ced946afdd35","scope":"Complete four page signed amendment read, all four original pages viewed. Aggregate generator codes EG001 through EG235 and combined generator/fire pump fuel cap are dated authorization only. Unchanged underlying permit conditions are not all restated here.","tier":"A","establishes_status":["permitted"]},"ga-qts-fayetteville-on29366-20241017":{"url":"https://air.gaepd.org/Permits/View/ON-29366","title":"Georgia QTS Fayetteville amendment narrative with completed October 2024 addendum","publisher":"Georgia Environmental Protection Division","published_on":null,"date_note":"Narrative heading August12,2024is not the publication day of the completed file with October review addendum.","checked_at":"2026-10-24T04:42:46.679499+00:00","sha256":"918e800f6fe1ee50d0b2c0623acf44d76ff1c0ba3978acaaf101cc328f24a178","scope":"Complete eight pages read, originals one, two, three and eight viewed. Heading August 12 precedes completed September 11 to October 11 review addendum. Potential emissions model is not measured emissions. Application dates, pump count and source code wording conflicts retained.","tier":"A","establishes_status":[]},"ga-qts-september-public-advisory-20260921":{"url":"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554","title":"Georgia official September 23, 2026 bulletin containing QTS proposed additional generator notice","publisher":"Georgia Environmental Protection Division","published_on":"2026-09-23","date_note":"Explicit public bulletin sent date, separate from title week.","checked_at":"2026-10-24T04:32:33.579363+00:00","sha256":"f89277ff19ad8ceec605585bceb66bf6e961d3cb35b340c68dd76022d78e4599","scope":"Only complete QTS major source proposed permit section and its governing notice introduction/deadline language admitted. Bulletin was sent September 23 although title week is September 21. Application 30027 and October 23 comment deadline establish no later approval or numerical equipment inventory.","tier":"A","establishes_status":["proposed"]},"ga-ms-fty01-issued-op29541-20250415":{"url":"https://air.gaepd.org/Permits/View/OP-29541","title":"Georgia signed Microsoft FTY01 April 15, 2025 building 3 generator amendment","publisher":"Georgia Environmental Protection Division","published_on":"2025-04-15","date_note":"Signed amendment issuance day, distinct from application, narrative and checked dates.","checked_at":"2026-10-24T06:21:24.400688+00:00","sha256":"22dd5ea87643793d052aa1c44d815bbf6fa5d65035a38ae998aafcdf3fac4f60","scope":"All six pages fully read; original PDF pages 1, 2, 3, 5 and 6 actually viewed. Signed cover authorizes twenty one additional building 3 emergency generators. Modified operating, monitoring and notification conditions apply to GN1 through GN63 but do not independently establish installed inventory, actual use or current unamended validity. Unchanged condition 2.2 and the full base permit were not substantively reviewed.","tier":"A","establishes_status":["permitted"]},"ga-ms-fty01-narrative-on29541-20261024":{"url":"https://air.gaepd.org/Permits/View/ON-29541","title":"Georgia Microsoft FTY01 application 29541 completed narrative with public comments addendum","publisher":"Georgia Environmental Protection Division","published_on":null,"date_note":"The February 11, 2025 narrative heading does not date the completed PDF containing later March public review outcomes. Exact completed file publication day unknown.","checked_at":"2026-10-24T06:21:24.840132+00:00","sha256":"c0457c0465fefb7b1d698a3d31727265ea54c7022318fdc8bd822dbb693a2fc0","scope":"All twelve pages fully read; original pages 1, 2, 6 and 10 actually viewed. February 11 heading precedes completed March comment addendum. Duplicate GN43 equipment codes, construction year differences, corrected comment receipt claim and conflicting public period end wording retained. Model assumptions and columns labeled Actual Emissions are not actual measured emissions. Appendix A is only a written comments cover; the full letters and separate application appendices were not read.","tier":"A","establishes_status":[]},"ga-microsoft-public-index-20261024":{"url":"https://air.gaepd.org/Permits/Search?Name=Microsoft&Permit=","title":"Georgia public Microsoft issued permit search index","publisher":"Georgia Environmental Protection Division","published_on":null,"date_note":"Exact index publication day not supplied. Dated permit rows are separate document dates.","checked_at":"2026-10-24T06:20:53.275996+00:00","sha256":"5bd464a0e8fad412cb5aae6d8b2f9032642e711564fcb6873b6ec0cb47de3d9d","scope":"All eight Microsoft result rows and their exact permit and narrative links read. The FTY01 row supplies the April 15, 2025 issued amendment link. A filtered search is not proof that no other later decisions or current conditions exist.","tier":"A","establishes_status":["permitted"]},"ga-equinix-public-permit-search-20261024":{"url":"https://air.gaepd.org/Permits/Search?Name=Equinix","title":"Georgia EPD public Equinix permit search","publisher":"Georgia Environmental Protection Division","tier":"A","published_on":null,"date_note":"No exact search result publication day stated. The listed June 30, 2026 permit issuance is separately confirmed on the signed permit.","checked_at":"2026-10-24T09:03:55.588712+00:00","sha256":"1a8881c318c11d164332602754d1ad1516256ea0d915e4d24f086d5ccc5f75da","scope":"Complete two result public name search reviewed. The 2026 HenryCounty EquinixAtlantaData Center row links exactOP29899 and ON29899. The distinct 2010 Fultonfacilityrow is not joined or admitted as this campus.","establishes_status":["permitted"]},"ga-equinix-atlanta-issued-op29899-20260630":{"url":"https://air.gaepd.org/Permits/View/OP-29899","title":"Georgia EPD Equinix Atlanta signed June 30, 2026 air permit","publisher":"Georgia Environmental Protection Division","tier":"A","published_on":"2026-06-30","date_note":"Explicit issuance date on signed cover and public index, not a construction or startup day. Exact online posting day is not established separately.","checked_at":"2026-10-24T09:04:35.780817+00:00","sha256":"a67f83e9ef6e478b829e2a40227e4ecf7e14df0268320fec9c64a31f5ccd7847","scope":"All 12 PDF pages completely read. Seven relevant originals actually viewed.149 generators and one separate fire pump, conditional state/federal/tablehour limits, NOxcap, records and reporting. Source application/tag/capacity differences are retained without claiming operation, installation, current complete governing edition oractualemissions.","establishes_status":["permitted"]},"ga-equinix-atlanta-narrative-on29899-20261024":{"url":"https://air.gaepd.org/Permits/View/ON-29899","title":"Georgia EPD Equinix Atlanta dated application review narrative","publisher":"Georgia Environmental Protection Division","tier":"A","published_on":null,"date_note":"Memo header is dated November 25, 2025; exact publication day is not stated. It references an October 3, 2025 application and earlier public advisory period, not the final June 2026 issuance day.","checked_at":"2026-10-24T09:04:35.742408+00:00","sha256":"789f9dfe76c49379b70a888be9d10fae28bc7a42037d2cdd8395b13805e9b404","scope":"Only complete first 5 pages of 19 read and admitted, with first 2 originals actually viewed. Application chronology, proposed equipment and modeling basis, not an issued authorization or actual measurements. Remaining 14 pages and full underlying application/appendices not reviewed or admitted.","establishes_status":[]},"ga-ms-cco06-issued-op29582-20250604":{"url":"https://air.gaepd.org/Permits/View/OP-29582","title":"Microsoft CCO06 issued June 2025 air permit","publisher":"Georgia Environmental Protection Division","published_on":"2025-06-04","date_note":"Printed issuance day and matching official index, not PDF creation metadata or a startup day.","checked_at":"2026-10-24T10:07:21.408722+00:00","sha256":"fc6460e34b820db673f657cec9a1ee4c3f54fd922e6fbf76ab5050bef0f3065c","scope":"Complete signed cover and all eight numbered conditions pages read. Seven relevant permit originals actually viewed. Dated conditional authorization and requirements, not installed inventory or measured operation.","tier":"A","establishes_status":["permitted"]},"ga-ms-cco06-narrative-on29582-20261024":{"url":"https://air.gaepd.org/Permits/View/ON-29582","title":"Microsoft CCO06 March 2025 review narrative with equipment schedule","publisher":"Georgia Environmental Protection Division","published_on":null,"date_note":"Memo header dated March 20, 2025 is separate from final June 4 issuance. Exact online publication day is not stated. PDF creation metadata is not substituted.","checked_at":"2026-10-24T10:07:22.896335+00:00","sha256":"530961969daba638594110513f997d423baff515ea93d4e78200a5ff15c6b86b","scope":"Only complete first five pages of 43 read, including background, requested addition, equipment list and applicability. Originals pages 1 and 2 actually viewed. Remaining narrative, application appendices, response and emissions evidence not completely reviewed.","tier":"A","establishes_status":[]},"ga-ms-cco06-public-index-20261024":{"url":"https://air.gaepd.org/Permits/Search?Name=Microsoft","title":"Georgia public Microsoft permit index checked October 24","publisher":"Georgia Environmental Protection Division","published_on":null,"date_note":"No exact page publication day stated; individual issuance dates remain separate from webpage publication.","checked_at":"2026-10-24T10:07:21.015591+00:00","sha256":"92baa0972c12a18ebc1d6f512a36012482d67036a24356b124d27df0730fe816","scope":"Complete substantive Microsoft result table read. It separately lists CCO06 prior permits and June 4, 2025 issued permit link. Public search coverage does not certify no later permit exists or actual operation.","tier":"A","establishes_status":["permitted"]},"epa-egrid2023-states-rev2":{"url":"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx","title":"EPA eGRID2023 revision2 original workbook ST23 state emissions,generation and total output rates","publisher":"U.S. Environmental Protection Agency","published_on":null,"date_note":"Exact workbook publication day not established;2025-06 path is a storage folder,not an exact publication date.2023 is report year,not retrieval year.","checked_at":"2026-10-27T21:05:24.064631+00:00","sha256":"895cd81dd8662406189ad8adf5a2578dcb362cdb5cff7cca81b10ee6bd2447c6","raw_path":"/Users/shaunwilson/Documents/Data Centers Atlas/build/cache/layers-20261023/epa-egrid2023-data-rev2.bin","tier":"A","scope":"EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Download index identifies eGRID2023 revision2;only workbook metadata/shared strings/ST23 entries read,no whole-archive extraction.","establishes_status":["historical"]},"eia-epa2025-state-emissions":{"url":"https://www.eia.gov/electricity/annual/table.php?t=epa_09_05.html","publisher":"U.S. Energy Information Administration","title":"Electric Power Annual Table9.5 state power and CHP emissions2025 and2024","published_on":"2026-10-21","checked_at":"2026-10-28T02:40:42.051795+00:00","sha256":"36e6dbf2164041a56f6985a5fcac8357791d95eb82545bfc542aea095c38d5dd","raw_path":"/Users/shaunwilson/Documents/Data Centers Atlas/build/cache/layers-20261023/eia-epa2025-state-emissions-20261028.html","tier":"A","establishes_status":["historical"],"scope":"EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins."}},"details":[{"id":"air-ga-amazon-atl068-atl078-20250818","html":"<article><h3>Amazon ATL068 and ATL078, Lithia Springs</h3><p class=\"layer-scope\">One dated permit jointly covers two colocated campuses. 188 is a combined permitted generator inventory, not observed operation or a per building count.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>permitted<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Issued permit dated August 18, 2025, not observed operation or a finding that this is the latest unamended authorization. Locator: Cover issuance heading and signed disposition.</p></dd><dt>Issued on</dt><dd>August 18, 2025<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Permit issuance, not installation, energization or opening. Locator: Cover issuance date.</p></dd><dt>Permit identifier</dt><dd>7374-097-0101-S-01-0<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Exact identifier of this dated permit. Locator: Cover and page headings.</p></dd><dt>Facility address</dt><dd>1456 Trae Lane, Lithia Springs, Georgia 30122, Douglas County<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Facility address from permit cover. The separate Virginia mailing address is not the generator location. Locator: Cover facility address.</p></dd><dt>Generator count</dt><dd>188 generators<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Combined permitted inventory across two campuses, not 188 at each campus, an installed count or complete Georgia census. Locator: Cover authorization paragraph.</p></dd><dt>Equipment scope</dt><dd>Two colocated campuses, ATL068 and ATL078: 180 critical generators and eight house, boost pump station and security generators.<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Cover total 188; critical source range 1 through 180, six house units and one each boost pump station and security. No individual building quantity or grid load assigned. Locator: Cover and conditions2.10 and2.11.</p></dd><dt>Fuel</dt><dd>Diesel, including biodiesel; maximum 15 ppm sulfur, with the specified cetane or aromatic content conditions.<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Permitted fuel, not fuel actually purchased or burned. Locator: Condition2.6, printed page2.</p></dd><dt>Federal operating limits</dt><dd>Maintenance checks and readiness testing have a 100 hour annual allowance with stated petition or required testing provisions. Nonemergency operation is limited to 50 hours annually, included within that 100 hours.<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Per generator. Included in 100 hours, not an additional 50. Separate state conditions and the most stringent condition still apply. No actual annual hours admitted. Locator: Conditions1.5 and2.7.b,c.</p></dd><dt>Financial dispatch exception</dt><dd>Peak shaving and nonemergency demand response are generally excluded. A narrow financial arrangement exception requires balancing authority or system operator dispatch, local reliability purpose, specified protocols, limited service scope and records.<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">All condition2.7.c.i requirements must be met together. Not a general right to sell power or provide demand response. Locator: Condition2.7.c.i, printed page3.</p></dd><dt>State operating categories</dt><dd>House, pump and security standby criteria include less than 200 hours yearly. Critical standby criteria include less than 500 hours yearly and May through September testing only between 10 p.m. and 4 a.m. Engines that cannot meet the standby definitions face separate ozone season NOx requirements.<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Conditional Georgia categories per generator, not an unconditional 500 hour cap for every unit. The alternate NOx standard is 80 ppm at 15 percent oxygen, dry basis, during May 1 through September 30. Federal permit conditions also apply. Locator: Conditions2.10 and2.11, printed pages4 and5.</p></dd><dt>Emission ceiling</dt><dd>Across the permitted generator inventory, NOx and CO each have a 99.9 ton ceiling per 12 consecutive months; VOC has a 24.9 ton ceiling over the same rolling period.<span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Permit ceilings for the listed generators, not measured emissions or an air quality impact estimate. Locator: Conditions2.1,2.2 and2.3.</p></dd><dt>Actual started on</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">No observed generator startup or facility opening date established by this permit. Locator: Review limit.</p></dd><dt>Measured emissions</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">No measured emissions, fuel use, compliance finding or actual operating hours admitted. Locator: Review limit.</p></dd><dt>Atlas record id</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Two campus permit scope has not been independently joined to an exact Atlas building or parcel. Locator: Identity review hold.</p></dd><dt>Later amendments</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://permitsearch.gaepd.org/permit.aspx?id=PDF-OP-29644\">Georgia Environmental Protection Division</a>. Source: August 18, 2025. Checked: October 23, 2026.</span> <p class=\"layer-scope\">Later permits, amendments, stays and current compliance outcomes require separate review. Locator: Dated source scope.</p></dd></dl></article>"},{"id":"air-ga-amazon-atl089-20260629","html":"<article><h3>Amazon ATL089 campus, Covington, issued June 2026 generator permit</h3><p class=\"layer-scope\">One actual dated permit authorizes 321 emergency generators. Inventory, conditional operating and reporting requirements, narrative conflicts and actual outcomes remain separate. No observed operation or statewide count completeness implied.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>permitted<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Actual issued permit, not observed operation or a finding that no later amendment exists. Locator: Signed cover and issue heading.</p></dd><dt>Historical permit basis</dt><dd>Historical issued permit<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">This is a dated June 2026 issued instrument. A current source inventory or operating observation requires separate review. Locator: Signed cover.</p></dd><dt>Issued on</dt><dd>June 29, 2026<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permit issuance, separate from application, narrative date, proposed installation and actual startup. Locator: Cover issue heading.</p></dd><dt>Application on</dt><dd>September 19, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Date of application 29883 as cited by the final permit, not its approval date. Locator: Cover application reference.</p></dd><dt>Permit identifier</dt><dd>7374-217-0078-E-01-0<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Exact dated permit identity. Locator: Cover and page headings.</p></dd><dt>Facility address</dt><dd>11145 Alcovy Road, Covington, Georgia 30054, Newton County<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permit facility address. The Virginia mailing address is separate and no Atlas building or parcel identity join is made. Locator: Cover facility address.</p></dd><dt>Airs identifier</dt><dd>04-13-217-00078<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Actual signed permit AIRS identity. The narrative carries a different number, disclosed separately. Locator: Cover AIRS heading.</p></dd><dt>Generator count</dt><dd>321 generators<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Total expressly authorized in the permit, not installed units, an operational count, grid MW or a statewide census. Locator: Cover authorization and printed page 9 equation explanation.</p></dd><dt>Equipment scope</dt><dd>316 critical emergency generators plus five ancillary building emergency generators, in groups of two, two and one.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29883\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Narrative identifies the source groups corresponding to the final permit source ranges. Proposed 2026 installation is not proof of installation. Storage tanks are not added to the generator count. Locator: Permit conditions 2.10 and 2.11; narrative PDF 1 and 2.</p></dd><dt>Narrative identity conflict</dt><dd>The narrative heading names ATL089 and application 29883 but gives AIRS 149 00013; repeated page headers name ATL086.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29883\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/Search?Name=Amazon&amp;Permit=7374-217-0078\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The signed permit and current public search name ATL089, AIRS 217 00078 and this exact permit. The conflicting narrative labels are disclosed, not silently corrected, treated as a second facility or used to make an Atlas identity join. Locator: Permit cover; public search single result; narrative PDF 1 and repeated headings.</p></dd><dt>Narrative chronology</dt><dd>Narrative heading dated November 3, 2025; its final addendum describes public review from March 4 to April 6, 2026 and comments received on April 6.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29883\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No invented separate addendum posting date. Narrative recommendation is separate from actual June 29 issuance. Appendix A is referenced but not included in the captured eleven pages and is not reviewed. Locator: Narrative PDF 1, 10 and 11.</p></dd><dt>Fuel</dt><dd>Diesel including biodiesel, maximum sulfur 15 ppm and either minimum cetane index 40 or maximum aromatic content 35 volume percent.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permitted fuel specification, not fuel actually purchased, stored or burned. Locator: Conditions 2.6 and 2.12.</p></dd><dt>Hour limits</dt><dd>Condition 2.3 bars more than 500 hours per year for any listed engine. The critical engine standby category requires less than 500 hours per year, while the ancillary standby category requires less than 200 hours per year.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Condition 7.5 requires a monthly calculation of the rolling twelve month hours. Federal emergency use wording does not cancel these separate permit conditions; the most stringent condition controls. Engines outside the state standby definitions face the separate ozone season NOx requirement. No actual hours or entitlement to 500 hours for every unit is established. Locator: Conditions 1.5, 2.3, 2.7(a), 2.10, 2.11 and 7.5.</p></dd><dt>Federal nonemergency limits</dt><dd>Maintenance and readiness testing have a 100 hour calendar year allowance with specified petition or required testing provisions. Nonemergency operation has a 50 hour calendar year limit included within the 100 hours.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The 50 hours are not an additional allowance. Federal allowances remain subject to the separate state permit conditions and most stringent condition. No actual testing, dispatch or annual hours verified. Locator: Condition 2.7(b) and (c).</p></dd><dt>Financial dispatch exception</dt><dd>A narrow financial arrangement exception requires all five conditions for system operator dispatch, local reliability purpose, specified protocols, limited service scope and dispatch records.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Peak shaving and nonemergency demand response are generally excluded. This is not a general permission to sell power or an observed dispatch. Locator: Condition 2.7(c)(i)(A) through (E).</p></dd><dt>Seasonal testing</dt><dd>Critical engine routine testing and maintenance from May through September must occur between 10 p.m. and 4 a.m.; other months allow any time of day.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Conditional permit operating schedule, not an actual testing record or proof of compliance. Locator: Condition 2.11(c).</p></dd><dt>Emission ceiling</dt><dd>NOx and CO each have a 249.9 ton ceiling per twelve consecutive months across the listed generator inventory.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29883\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permit limits, not measured releases, ambient concentrations, avoided pollution or actual customer load. Narrative potential emissions table has no actual values and its dashes are not converted to zero. Locator: Conditions 2.1, 2.2 and 7.3; narrative PDF 3.</p></dd><dt>Control requirements</dt><dd>Critical engines have SCR and catalyzed diesel particulate filter requirements when exhaust temperature reaches 572 degrees Fahrenheit, with startup, shutdown and malfunction exceptions.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29883\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The narrative distinguishes controlled and uncontrolled operation. Control requirements are not proof of controls installed or operating continuously. No emission reduction or health outcome calculated. Locator: Conditions 4.2 through 4.4 and 5.2; narrative PDF 3.</p></dd><dt>Startup and title v</dt><dd>Startup notice is due within fifteen days after startup. A complete Title V permit application is required within twelve months after any emergency generator starts.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">These are duties triggered by an actual startup date. No startup, completed notice, application, issued Title V permit or calendar deadline is inferred from the construction permit. Locator: Conditions 7.1 and 8.3.</p></dd><dt>Current permit validity</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Later amendments, stays or rescission and current unamended validity are not independently reviewed. Locator: Dated permit review boundary.</p></dd><dt>Actual installed equipment</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual installed generator inventory is verified. Locator: Dated permit review boundary.</p></dd><dt>Actual generation</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual generation, served electric demand or generator operating hours are reviewed. Locator: Dated permit review boundary.</p></dd><dt>Actual started on</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual startup, energization or opening date is verified. Locator: Dated permit review boundary.</p></dd><dt>Measured emissions</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No emissions measurement, fuel use, compliance or health outcome is reviewed. Locator: Dated permit review boundary.</p></dd><dt>Atlas record id</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29883\">Georgia Environmental Protection Division</a>. Source: June 29, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No independently verified Atlas facility, building or parcel identity join is made. Locator: Dated permit review boundary.</p></dd></dl></article>"},{"id":"air-ga-amazon-atl057-20230921-context","html":"<article><h3>Amazon ATL057 dated permit and separate equipment plan</h3><p class=\"layer-scope\">Issued September 2023 permit terms and a separate seven unit narrative plan. The signed instrument gives no numerical inventory. Planned equipment, future phases, rolling operating limits and unknown actual outcomes remain distinct.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>permitted<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Actual dated permit issuance only. No observed construction, generator installation, energization or operating status is inferred. Locator: Signed cover and issue heading.</p></dd><dt>Planned inventory basis</dt><dd>Issued permit with separate narrative equipment plan<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The signed instrument states no numerical generator inventory. The narrative plan is retained separately and excluded from the table of numerical permitted inventories. Locator: Permit cover and full conditions; narrative purpose and equipment list.</p></dd><dt>Issued on</dt><dd>September 21, 2023<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Actual issuance date, separate from application, narrative heading, public advisory and proposed installation dates. Locator: Signed cover.</p></dd><dt>Application on</dt><dd>April 6, 2023<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Application date cited by the signed permit. The narrative separately says received the same date. Locator: Permit cover; narrative page 1.</p></dd><dt>Facility address</dt><dd>New Boyd Road, Duluth, Georgia 30024, Forsyth County<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Dated permit facility address. The Herndon mailing address is separate. No parcel, building or Atlas record identity is joined. Locator: Permit cover.</p></dd><dt>Permit identifier</dt><dd>7374 117 0093 B 01 0<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permit identifier components shown with spaces for readability. The original linked instrument retains its punctuation. Locator: Permit cover.</p></dd><dt>Airs identifier</dt><dd>04 13 117 00093<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">AIRS identity components in the signed cover, separate from equipment count or an Atlas identity join. Locator: Permit cover.</p></dd><dt>Planned generator count</dt><dd>7 generators<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Narrative application requests seven diesel emergency generators. This is a proposed equipment inventory, not a numerical inventory expressly stated by the signed permit or installed equipment. Locator: Narrative page 1 purpose of application and equipment list on pages 1 and 2.</p></dd><dt>Equipment plan</dt><dd>One 0.6 MW house generator and six 2.5 MW generators. The plan places the house generator and two larger units in August 2023, two more in August 2028 and two in August 2037.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Original plan ratings and months are retained without summing grid capacity or treating any date as actual installation. No current completion, revised phase or operating observation is verified. Locator: Narrative background and equipment list, pages 1 and 2.</p></dd><dt>Hour limits</dt><dd>Condition 2.3 limits total operation to no more than 200 hours per generator during any twelve consecutive months.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">This rolling total is not 200 maintenance hours plus unrestricted emergency hours. Condition 1.5 says the most stringent conflicting condition prevails. No actual operating hours are reviewed. Locator: Permit conditions 1.5 and 2.3.</p></dd><dt>Federal operation conditions</dt><dd>Condition 2.4 describes emergency use without a federal emergency time limit and generally allows 100 annual maintenance and readiness hours, including up to 50 hours of specified nonemergency use. The 50 hours are part of the 100 hours, with stated maintenance exceptions and tightly conditioned dispatch provisions.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The separate 200 hour rolling total remains. This is not an additional 150 hour allowance or unrestricted peak shaving, grid sales or demand response. The full linked instrument controls exceptions and dispatch conditions. Locator: Permit condition 2.4(a) through (c)(i)(E).</p></dd><dt>Fuel</dt><dd>Diesel fuel oil, with maximum sulfur of 15 ppm and either a minimum cetane index of 40 or maximum aromatic content of 35 volume percent for engines with less than 30 liters per cylinder.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Fuel purchase and use requirements, not measured fuel composition, actual fuel burned or emissions. Locator: Permit conditions 2.5 and 2.6.</p></dd><dt>Seasonal conditions</dt><dd>Condition 2.8 includes an ozone season NOx standard where the emergency definition and listed data center conditions are not met. The listed conditions include less than 500 annual hours and routine testing from 10 p.m. to 4 a.m. during May through September, with other months allowing testing at any time of day.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The less than 500 hour criterion does not replace condition 2.3 limiting total operation to 200 hours during any twelve consecutive months. No actual exception, testing schedule or compliance outcome is found. Locator: Permit conditions 2.3 and 2.8.</p></dd><dt>Monitoring and reporting</dt><dd>Each generator requires a nonresettable hour meter recording emergency, nonemergency and total operation. Monthly operating and fuel records must be retained. Written startup notification is due within fifteen days of actual startup. Specified financial dispatch triggers an annual report due March 31 of the following year.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Monitoring and reporting duties do not establish actual startup, a submitted report, compliance, fuel use or a calendar deadline for this facility. Locator: Permit conditions 5.3 and 7.1 through 7.6.</p></dd><dt>Future emissions review</dt><dd>The narrative requires a renewed potential emissions demonstration for the later EG3 through EG6 phases and describes a RACT plan if potential NOx exceeds 25 tons per year.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">This is dated narrative review of proposed later phases, not a current major or minor source determination, actual annual emissions or issued RACT approval. Locator: Narrative regulatory review page 3 and recommendations page 5.</p></dd><dt>Emissions table scope</dt><dd>The narrative contains a table headed Actual Emissions alongside Potential Emissions, while its discussion describes vendor data, emission factors and planned construction.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No measured emissions record, monitoring period or actual operations evidence is reviewed. No numerical value from that table is admitted as measured emissions. Locator: Narrative emissions summary page 2 and background page 1.</p></dd><dt>Narrative date scope</dt><dd>The narrative heading is May 4, 2023, and its text states that Public Advisory expired May 26, 2023.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <p class=\"layer-scope\">These labels remain separate. PDF metadata dated September 25 does not establish publication or revise the September 21 permit issuance date. Locator: Narrative page 1 heading and purpose; page 5 recommendations; actual PDF metadata.</p></dd><dt>Permitted generator inventory</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No numerical generator inventory is expressly stated in the signed permit. Narrative planned equipment is not substituted. Locator: Dated permit and narrative review boundary.</p></dd><dt>Current permit validity</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Later amendments, stays or rescission and current unamended validity are not independently reviewed. Locator: Dated permit and narrative review boundary.</p></dd><dt>Actual installed equipment</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual installed generator inventory is verified. Locator: Dated permit and narrative review boundary.</p></dd><dt>Actual generation</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual generation, served electric demand or operating hours are reviewed. Locator: Dated permit and narrative review boundary.</p></dd><dt>Actual started on</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual startup, energization or opening date is verified. Locator: Dated permit and narrative review boundary.</p></dd><dt>Measured emissions</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No independent measured emissions, fuel use, compliance or health outcome is reviewed. Locator: Dated permit and narrative review boundary.</p></dd><dt>Atlas record id</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-28844\">Georgia Environmental Protection Division</a>. Source: September 21, 2023. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-28844\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No independently verified Atlas facility, building or parcel identity join is made. Locator: Dated permit and narrative review boundary.</p></dd></dl></article>"},{"id":"air-ga-dcb-atlanta-east-20250226","html":"<article><h3>DCB Atlanta East, Conyers, dated six generator permit</h3><p class=\"layer-scope\">Dated February 2025 six generator issued authorization with separate state and federal conditions, narrative calculation assumptions, future installation plan and explicit source differences. Permit is not operation.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>permitted<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/Search?Name=DCB&amp;Permit=\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Dated issued permit with signed cover and current official search link. Not observed operation, installed inventory or proof that no later amendment exists. Locator: Signed cover and exact East public search row.</p></dd><dt>Historical permit basis</dt><dd>Historical issued permit<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">This February 2025 instrument is reviewed as a dated authorization, not a certified current unamended operating inventory. Locator: Signed cover.</p></dd><dt>Issued on</dt><dd>February 26, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Actual printed issuance date, separate from application, narrative, installation plans and startup. Locator: Cover issuance heading.</p></dd><dt>Application on</dt><dd>September 26, 2024<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Application 29442 date printed on the issued permit, not its approval date. Locator: Cover application reference.</p></dd><dt>Permit identifier</dt><dd>7374-247-0076-B-01-0<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Exact issued permit identifier; West is a different permit and facility. Locator: Cover and all condition headings.</p></dd><dt>Facility address</dt><dd>1726 Farmer Road, Conyers, Georgia 30012, Rockdale County<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permit prints Farmer Rd. This facility address is separate from the Atlanta mailing address and supplies no reviewed parcel or Atlas identity join. Locator: Cover facility and mailing address blocks.</p></dd><dt>Airs identifier</dt><dd>04-13-247-00076<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Exact facility AIRS identifier in the issued permit. Locator: Cover AIRS block.</p></dd><dt>Generator count</dt><dd>6 generators<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Six emergency diesel generators expressly authorized by the issued cover. Not an installed count, actual operation, campus electric load or complete state census. Locator: Cover authorization; conditions 2.1 through 2.10 source range EG01 through EG06.</p></dd><dt>Equipment scope</dt><dd>Six emergency generators, source identifiers EG01 through EG06.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29442\">Georgia Environmental Protection Division</a>. Source: November 19, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The final permit count is primary. Narrative 3 MW specifications and 2025 through 2028 phases remain proposed equipment descriptions, not aggregate grid capacity or verified installation. Locator: Permit cover and source ranges; narrative PDF 1.</p></dd><dt>Fuel</dt><dd>Diesel distillate with maximum 15 ppm sulfur, plus a minimum cetane index 40 or maximum aromatic content 35 volume percent.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Fuel requirement, not fuel actually purchased or burned. The general 2.5 percent clause is subsumed by the more restrictive federal fuel requirement and most stringent condition. Locator: Conditions 1.5, 2.2, 2.3 and 2.5.</p></dd><dt>Hour limits</dt><dd>The state standby criteria require total annual operation below 500 hours for each generator, plus the specified reasons, seasonal testing window and records.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The federal emergency wording does not cancel separate state permit conditions. Condition 7.3 separately requires rolling twelve month calculation and notice at 500 hours or more. This is not actual runtime or a general allowance to operate 500 hours. Locator: Conditions 1.5, 2.4 and 7.3.</p></dd><dt>Federal nonemergency limits</dt><dd>Maintenance and readiness testing have a maximum 100 hours per calendar year, subject to specified petition or mandatory testing provisions. Up to 50 nonemergency hours are included within those 100 hours.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The 50 hours are not additional. All separate state conditions remain. No actual testing or dispatch is established. Locator: Condition 2.8(b) and (c).</p></dd><dt>Financial dispatch exception</dt><dd>The narrow financial arrangement exception requires all five conditions for system operator dispatch, local reliability purpose, specified protocols, limited power service and records.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Ordinary peak shaving, nonemergency demand response and financial power supply are excluded outside the stated exception. The permit cross reference says 2.5.c.i even though the exception is printed under 2.8.c.i; this is preserved as a source cross reference issue, not silently repaired. Locator: Condition 2.8(c) and (c)(i)(A)through(E), PDF 4 and 5.</p></dd><dt>Seasonal testing</dt><dd>Routine maintenance and testing from May through September must occur between 10 p.m. and 4 a.m.; other stated months allow any time of day.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">State standby condition, not an observed schedule, noise finding or proof of compliance. Engines outside the standby definition have the separate ozone season NOx requirement. Locator: Condition 2.4(a)through(d) andfollowing paragraph.</p></dd><dt>Monitoring and notice</dt><dd>Each generator requires a nonresettable hour monitor, monthly operation and reason records, and monthly rolling totals. Startup notice is due within 15 days after startup.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Duties, not completed records or actual startup. Rolling total notifications at 500 total or 100 nonemergency hours are separate from calendar year language. Five year record retention is not a claim that records were publicly obtained. Locator: Conditions 1.4, 5.2, 7.1 through 7.5.</p></dd><dt>Narrative model basis</dt><dd>The narrative models potential emissions using 200 hours per year and its Actual Emissions column using an expected ten hours per year.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29442\">Georgia Environmental Protection Division</a>. Source: November 19, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">These are calculation assumptions, not a 200 hour operative permit ceiling, independently measured emissions or actual operation. No numerical modeled releases are promoted to measured values and no new totals are calculated. Locator: Narrative PDF 2 through 4 and 8.</p></dd><dt>Modeled potential hours</dt><dd>200 hours per year<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29442\">Georgia Environmental Protection Division</a>. Source: November 19, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Narrative calculation assumption for potential emissions, not a permit runtime ceiling or actual hours. Locator: Narrative PDF 2 and 8.</p></dd><dt>Modeled expected hours</dt><dd>10 hours per year<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29442\">Georgia Environmental Protection Division</a>. Source: November 19, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Narrative expected operating assumption underlying its Actual Emissions column, not measured operation. Locator: Narrative PDF 2 through 4 and 8.</p></dd><dt>Narrative plan</dt><dd>The November 2024 narrative proposes three generators in 2025, one each in 2026, 2027 and 2028, with final installation and operation expected November 2028.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29442\">Georgia Environmental Protection Division</a>. Source: November 19, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Dated application plan, not completed installation, operation or a new forecast adopted as an outcome. No summedMW capacity is computed. Locator: Narrative PDF 1 equipment table and background.</p></dd><dt>Source differences</dt><dd>The narrative summary says notice before startup while the issued permit requires notice within 15 days after startup. The narrative describes less than 100 hours while the final federal clause states a maximum 100 hours with specified extra testing provisions.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29442\">Georgia Environmental Protection Division</a>. Source: November 19, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Final issued conditions control this review. The final narrative addendum still contains unfilled review dates and alternative comments wording, not an actual later comment period or proof of no comments. Locator: Permit 2.8 and 7.1; narrative PDF 7 and 10.</p></dd><dt>Current permit validity</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Later amendments, stays, rescission and current unamended validity are not independently established. Locator: Bounded dated permit and narrative review.</p></dd><dt>Actual installed equipment</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No installed generator inventory is independently verified. Locator: Bounded dated permit and narrative review.</p></dd><dt>Actual generation</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual generated electricity, electric load or operating hours are reviewed. Locator: Bounded dated permit and narrative review.</p></dd><dt>Actual started on</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual facility or generator startup date or completed startup notification is reviewed. Locator: Bounded dated permit and narrative review.</p></dd><dt>Measured emissions</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The narrative calculated Actual Emissions column is not an independently measured release record. Locator: Bounded dated permit and narrative review.</p></dd><dt>Atlas record id</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29442\">Georgia Environmental Protection Division</a>. Source: February 26, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No verified Atlas record, building or parcel identity join is made. Locator: Bounded dated permit and narrative review.</p></dd></dl></article>"},{"id":"air-ga-dcb-atlanta-west-20260128","html":"<article><h3>DCB Atlanta West, Douglasville, dated 76 generator and fuel limit permit</h3><p class=\"layer-scope\">Signed January 2026 authorization, facilitywide rolling diesel fuel ceiling, separate hour conditions and completed public comment addendum. Narrative calculation and chronology conflicts retained. Permit is not operation.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>permitted<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Dated final issued authorization establishes permitted equipment and enforceable conditions. It does not establish construction, installation, current unamended validity or operation. Locator: Signed permit cover.</p></dd><dt>Historical permit basis</dt><dd>Historical issued permit<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">This exact January 2026 instrument is reviewed. Later amendment, rescission or actual equipment status is unknown. Locator: Complete signed dated permit.</p></dd><dt>Issued on</dt><dd>January 28, 2026<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Printed final issuance day, distinct from application, original narrative and later narrative addendum dates. Locator: Signed cover.</p></dd><dt>Application on</dt><dd>May 28, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Application date printed on the final permit and narrative header. Narrative purpose paragraph instead prints May 23, retained as a source discrepancy. Locator: Final cover; narrative PDF 1.</p></dd><dt>Narrative heading on</dt><dd>August 8, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Original narrative heading only. The retained document also contains later December 2025 and January 2026 addendum material, so its final publication day remains unknown. Locator: Narrative PDF 1 and 16 through 24.</p></dd><dt>Permit identifier</dt><dd>7374-097-0102-S-01-0<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Exact permit identifier for this dated West facility instrument. East facility permits are separate. Locator: Signed cover and all condition headers.</p></dd><dt>Facility address</dt><dd>1701 North River Rd, Douglasville, Georgia 30122, Douglas County<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Address printed on the issued permit, not a verified parcel, building geometry or exact Atlas location match. Locator: Permit cover.</p></dd><dt>Airs identifier</dt><dd>04-13-097-00102<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Final cover facility AIRS identifier. Narrative abbreviated county facility identifier is separate from an Atlas record join. Locator: Permit cover; narrative header.</p></dd><dt>Generator count</dt><dd>76 generators<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Total emergency generators authorized for the two building facility. Not an installed inventory, actual operating count or count of permits. Locator: Signed cover.</p></dd><dt>Equipment scope</dt><dd>The final cover authorizes two buildings with 76 emergency generators. The narrative proposes sixty 3.0 MW units and sixteen 2.5 MW units.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Final total count and proposed equipment specifications have distinct sources. No aggregate MW, grid demand or installed capacity is computed. The emissions model instead represents all units as 3.0 MW. Locator: Final cover; narrative PDF 1 through 4.</p></dd><dt>Permitted diesel fuel limit</dt><dd>745,286 gallons<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Maximum collective diesel fuel consumption for all emergency generators in any twelve consecutive months. A rolling facilitywide permit ceiling, not actual use, a calendar year total, a per generator allowance or an emissions measurement. Locator: Condition 2.1, PDF 2.</p></dd><dt>Fuel monitoring and notice</dt><dd>Fuel use is recorded monthly and summed over rolling twelve month periods. Written notification is due within 15 days if the rolling total equals or exceeds 745,286 gallons.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The notice threshold includes equality while the substantive cap prohibits exceeding the amount. These are different duties. No fuel meter values, supplier receipts or filed notification are reviewed. Locator: Conditions 5.2(c), 7.4 and 7.5, PDF 6 and 9.</p></dd><dt>Fuel</dt><dd>Diesel distillate with maximum sulfur 15 ppm and either minimum cetane index 40 or maximum aromatic content 35 volume percent.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Fuel specifications are not evidence of actual storage, purchase or combustion. Locator: Conditions 2.5 and 2.10.</p></dd><dt>Hour limits</dt><dd>The state data center condition requires each generator to operate below 500 hours per year, for the specified emergency or testing purposes and with required records.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The federal emergency no time limit sentence does not cancel the separate most stringent state condition. Rolling hour notice duties are stated separately. No actual runtime is established. Locator: Conditions 1.5 and 2.11.</p></dd><dt>Federal nonemergency limits</dt><dd>Maintenance and readiness testing may use at most 100 hours per calendar year, subject to the stated additional testing provisions. Up to 50 nonemergency hours are included within those 100 hours.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The 50 hours are not additional to 100. The conditional financial dispatch exception and state data center limits remain separate. Locator: Condition 2.7(a) through (c), PDF 3 and 4.</p></dd><dt>Financial dispatch exception</dt><dd>The narrow exception requires all five conditions for system operator dispatch, local reliability purpose, specified protocols, limited power destination and dispatch records.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Ordinary peak shaving, nonemergency demand response and financial supply are excluded outside the specified exception. The exception is printed under 2.7(c)(i), despite a 2.5.c.i cross reference in the preceding paragraph. Locator: Condition 2.7(c) and (c)(i)(A) through (E), PDF 4.</p></dd><dt>Seasonal testing</dt><dd>Routine testing and maintenance from May through September are limited to 10 p.m. through 4 a.m.; the other stated months permit any time of day.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">State operating condition, not an observed operating or noise schedule. Engines that do not meet the stated data center definition retain the separate ozone season NOx condition. Locator: Condition 2.11(c) and final paragraph, PDF 5.</p></dd><dt>Operating records and notice</dt><dd>Each generator requires a nonresettable hour meter and monthly hours and reasons. Rolling totals at or above 500 total hours or 100 nonemergency hours require written notice within 15 days. Startup notice is due within 15 days after startup.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Calendar year conditions, monthly rolling notifications and startup notice are distinct. These record duties and deadlines do not establish actual startup, hours, dispatch or compliance. Locator: Conditions 5.2, 7.1, 7.6 through 7.9.</p></dd><dt>Conditional annual report</dt><dd>Operation under the financial dispatch exception triggers an annual report due March 31 of the following calendar year, with electronic reporting or the stated written fallback.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Conditional reporting duty, not an actual filed report, routine annual reporting for every possible operation or proof of dispatch. Locator: Condition 7.10, PDF 10.</p></dd><dt>Emissions model basis</dt><dd>The narrative potential emissions table is calculated from the fuel limit and pollutant factors, conservatively representing all generators as 3.0 MW units at full load. Its benzene assessment uses screening model predictions.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Potential releases and modeled ambient concentrations are not actual measured emissions, health outcomes or proof of facility operation. The narrative labels an SO2 example result as NOx; no new calculation or correction is substituted. Locator: Narrative PDF 4, 5 and 13 through 15.</p></dd><dt>Narrative plan</dt><dd>The narrative schedules phased generator installation from November 2025 through 2027 and separately gives different final completion descriptions in its prose and equipment table.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Dated proposed phases are not actual construction or startup. The opening says building construction begins May 2027, while the completed addendum says that year was revised to 2025. The disagreement is retained. Locator: Narrative PDF 1 through 4 and 16.</p></dd><dt>Public review opened on</dt><dd>December 15, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Start date reported by the completed narrative addendum, separate from the earlier July 2025 advisory. The addendum calls this a 30 day review; no independent duration calculation replaces its stated dates. Locator: Narrative addendum PDF 16.</p></dd><dt>Public review closed on</dt><dd>January 16, 2026<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">End date in the completed addendum and date of received public comments, not permit issuance or actual startup. Locator: Narrative PDF 16, 17 and appended letter date.</p></dd><dt>Public comments</dt><dd>The completed addendum records consultant comments on December 30, 2025 and public comments on January 16, 2026, with agency responses.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Received comments are not adopted regulatory conditions or independently established claims about other facilities, regional generation or health. The appended external citations were not independently reviewed. Locator: Narrative PDF 16 through 24.</p></dd><dt>Source differences</dt><dd>The narrative header and final cover say application May 28, 2025, but the purpose paragraph says May 23. The addendum says construction 2027 was corrected to 2025, while the retained opening still says 2027.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Separate source discrepancies retained, not silently normalized or resolved into actual construction dates. Final permit conditions establish the authorized limits. Locator: Permit cover; narrative PDF 1 and 16.</p></dd><dt>Permit cross references</dt><dd>The financial exception points to 2.5.c.i while printed under 2.7.c.i. Condition 5.3 refers to 2.9 for fuel verification while 7.3 points to 2.5. Runtime conditions 7.8 and 7.9 refer to fuel records in 7.5.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">These are printed internal references, not Atlas corrections or a claim the permit is invalid. The separately quoted substantive limits remain dated final permit conditions. Locator: Conditions 2.7(c), 5.3, 7.3, 7.8 and 7.9.</p></dd><dt>Current permit validity</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Later amendments, stays, rescission and present unamended validity are not independently established. Locator: Complete dated permit and narrative review.</p></dd><dt>Actual installed equipment</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No installed generator inventory or verified equipment commissioning is reviewed. Locator: Complete dated permit and narrative review.</p></dd><dt>Actual generation</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual electric generation, load, hours or dispatch is established by the permit or model. Locator: Complete dated permit and narrative review.</p></dd><dt>Actual started on</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual startup date or completed startup notice is reviewed. Locator: Complete dated permit and narrative review.</p></dd><dt>Actual diesel consumption</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The permitted fuel ceiling and monthly record duties do not establish actual fuel use. Locator: Complete dated permit and narrative review.</p></dd><dt>Measured emissions</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No measured releases or actual ambient monitoring is reviewed. Potential emissions and screening predictions remain model results. Locator: Complete dated permit and narrative review.</p></dd><dt>Actual compliance</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permit conditions, expected construction and regulatory modeling are not an actual compliance finding. Locator: Complete dated permit and narrative review.</p></dd><dt>Atlas record id</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29723\">Georgia Environmental Protection Division</a>. Source: January 28, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29723\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No exact Atlas site, parcel, building or operating record join is established. Locator: Complete dated permit and narrative review.</p></dd></dl></article>"},{"id":"air-ga-qts-fayetteville-20241017","html":"<article><h3>QTS Fayetteville dated 235 generator amendment and later proposed addition</h3><p class=\"layer-scope\">Historical generator source inventory and shared generator/fire pump fuel cap. Pump wording, application chronology and later 2026 proposal remain separate. Permitted is not installed or operating.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>permitted<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Historical signed amendment, not current complete governing authority or operation. Locator: Signed cover and amended conditions.</p></dd><dt>Historical permit basis</dt><dd>Historical issued permit<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Issued amendment and aggregate source codes, distinct from the later proposed application. Locator: Amendment cover and conditions 2.1 and 2.2.</p></dd><dt>Mixed engine cap basis</dt><dd>Combined generator and fire pump fuel cap with unresolved pump count wording<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Separate equipment categories share one fuel allowance. Fire pumps are not added to the generator count. Locator: Condition2.1; signed cover and narrative pages 1 and 2.</p></dd><dt>Issued on</dt><dd>October 17, 2024<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Signed amendment issuance, not construction completion or current validity. Locator: Amendment cover.</p></dd><dt>Permit identifier</dt><dd>7374 113 0073 S 01 2<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Final amendment identifier. Narrative references containing133andS04are retained as source differences rather than substituted. Locator: Amendment cover; narrative equipment note and emissions section.</p></dd><dt>Facility address</dt><dd>1435 Hwy 54 West, Fayetteville, Georgia 30214, Fayette County<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Facility address, separate from mailing address in Irving, Texas. No exact Atlas join made. Locator: Signed cover.</p></dd><dt>Generator count</dt><dd>235 generators<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Aggregate generators identified by amended conditions as EG001 through EG235. Not 235 new generators, installed equipment or generator plus fire pump count. Locator: Amended conditions 2.1, 2.2 and 5.1.</p></dd><dt>Permitted mixed engine fuel limit</dt><dd>670,000 gallons<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">One shared maximum over any twelve consecutive months for all listed generators and fire pumps combined, not an allowance per engine, consumption report or generator only fuel cap. Locator: Amended condition 2.1.</p></dd><dt>Fire pump source difference</dt><dd>The signed cover says two additional fire pumps, while the narrative purpose says one additional pump and its inventory lists FP001 and FP002.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No reconciled total pump inventory is assigned. The combined cap includes the two listed fire pump codes, but pumps are not counted as generators. Locator: Permit cover and conditions 2.1 and 2.2; narrative pages 1 and 2.</p></dd><dt>Application date difference</dt><dd>The narrative header gives June 17, 2024, while its purpose and the signed cover give July 17; the purpose states receipt July 22.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Conflicting application dates retained. No single reconciled application date inferred. Locator: Narrative page 1 header and purpose; amendment cover.</p></dd><dt>Narrative heading on</dt><dd>August 12, 2024<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Original heading, not publication of the completed file containing later review outcomes. Locator: Narrative first page.</p></dd><dt>Completed review period</dt><dd>The addendum records public review from September 11 to October 11, 2024 and says no comments were received.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Historical 2024 review, distinct from the separate 2026 proposal notice and not proof of current compliance. Locator: Narrative page 8.</p></dd><dt>Equipment code difference</dt><dd>The narrative renames former EG206 and EG207 to EG230 and EG231; the next row has source codes EG232 through EG235 but a description beginning EG230.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Renaming is not added equipment. The final amendment aggregate source code range remains the generator count basis. Narrative 2024 installation labels do not prove actual commissioning. Locator: Narrative page 2 equipment table and note.</p></dd><dt>Fuel</dt><dd>Diesel fuel with maximum 15 ppm sulfur and the stated cetane or aromatic alternatives.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Amended fuel specifications for listed generators and fire pumps, not a measured fuel assay. Locator: Amended condition 2.5.</p></dd><dt>State operating conditions</dt><dd>Generator operation is limited to routine testing and maintenance, utility power loss or internal system failures, with less than 500 annual hours per generator and recorded operating reasons.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">State emergency classification conditions, not actual hours or a complete restatement of unchanged federal and base permit requirements. Locator: Amended condition 2.8.</p></dd><dt>Seasonal testing</dt><dd>Routine testing from May through September is limited to 10 p.m. through 4 a.m.; other months permit routine testing at any time of day.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Testing condition, not a finding of when operation occurred. Locator: Amended condition 2.8(c).</p></dd><dt>Monitoring and records</dt><dd>Separate emergency, nonemergency and cumulative hour metering is required; monthly fuel records for generators and pumps are retained for five years.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Recordkeeping duties, not actual submitted hour logs, fuel reports or compliance findings. Locator: Amended conditions 5.1, 7.4 and 7.5.</p></dd><dt>Emissions model scope</dt><dd>The narrative models potential emissions under one shared fuel cap and a worst case engine type. Its Actual Emissions columns contain dashes.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Blank actual emissions are not zero. Modelled pollutant quantities and modeled benzene concentrations are not observed releases, exposure measurements or a health finding. Locator: Narrative pages 3 and 7.</p></dd><dt>Amendment scope</dt><dd>Only modified and new conditions in the four page amendment were substantively reviewed as permit requirements.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The base permit and earlier amendment remain referenced. This review does not claim every unchanged federal provision or all current conditions were reviewed. Locator: Amendment cover and all three condition pages.</p></dd><dt>Later application</dt><dd>Application 30027 is listed as a proposed permit for additional emergency generators.<span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">A separate later request, not added to the 235 historical permitted inventory. No numerical proposed count admitted from this notice. Locator: Official 2026 bulletin QTS Fayetteville major source SIP section.</p></dd><dt>Later notice sent on</dt><dd>September 23, 2026<span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Explicit sent date; the title describes the week of September 21. Locator: Public bulletin top heading and sent timestamp.</p></dd><dt>Later comments due on</dt><dd>October 23, 2026<span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Printed comment deadline, not an approval, issue or effective date. The deadline passing does not establish a final outcome. Locator: QTS proposed permit notice deadline.</p></dd><dt>Permitted fire pump inventory</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Cover and narrative wording do not establish a reconciled total fire pump inventory. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd><dt>Current permit validity</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No complete current permit chain or later agency decision reviewed. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd><dt>Later application approval</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No final outcome of application 30027 reviewed. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd><dt>Later added generators</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No numerical later approved or proposed equipment count established from the notice. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd><dt>Actual installed equipment</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No installation or as built inventory verified. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd><dt>Actual generation</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual generated electricity verified. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd><dt>Actual started on</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual startup verified. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd><dt>Actual diesel consumption</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No measured or reported actual fuel use reviewed. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd><dt>Measured emissions</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual emissions measurement reviewed. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd><dt>Actual compliance</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual compliance finding established. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd><dt>Atlas record id</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29366\">Georgia Environmental Protection Division</a>. Source: October 17, 2024. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29366\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://content.govdelivery.com/accounts/GAEPD/bulletins/42c3554\">Georgia Environmental Protection Division</a>. Source: September 23, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No exact Atlas facility, parcel or operating building join established. Locator: Bounded issued amendment, narrative and later proposed notice only.</p></dd></dl></article>"},{"id":"air-ga-ms-fty01-building3-20250415","html":"<article><h3>Microsoft FTY01 dated 21 generator building 3 amendment</h3><p class=\"layer-scope\">Historical authorization for an additional building 3 group, with strict annual operating condition, separate calendar and rolling notification clocks, narrative source conflicts and unknown actual operation. The equipment count is not an aggregate campus inventory.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>permitted<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Historical signed authorization, not installed equipment, observed operation or certification of every current condition. Locator: Signed amendment cover.</p></dd><dt>Historical permit basis</dt><dd>Historical issued permit<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Only the dated building 3 amendment and the referenced modified conditions are admitted as issued requirements. Locator: Signed cover and all five condition pages.</p></dd><dt>Fty01 amendment basis</dt><dd>Building 3 addition only with unresolved narrative source codes<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The numerical count belongs to the addition described on the signed cover, not an aggregate campus inventory calculated from the narrative table. Locator: Signed cover addition clause; narrative equipment table, page 2.</p></dd><dt>Issued on</dt><dd>April 15, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Signed issuance day, not startup, completion, checked date or narrative publication. Locator: Signed cover issuance heading.</p></dd><dt>Application on</dt><dd>December 19, 2024<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Application date, separate from agency receipt and later authorization. Locator: Signed cover reason for amendment.</p></dd><dt>Application received on</dt><dd>December 26, 2024<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Agency receipt stated on the cover, not approval or operation. Locator: Signed cover reason for amendment.</p></dd><dt>Narrative heading on</dt><dd>February 11, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Original narrative heading. Completed addendum discusses later March comments, so this is not the publication day of all captured narrative bytes. Locator: Narrative page 1 heading and pages 8 through 11 addendum.</p></dd><dt>Permit identifier</dt><dd>7376 097 0097 S 01 2<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Issued amendment identifier. The cover first references a base prefix 7373, then makes the amendment part of a base prefix 7376. That source difference is retained without silently repairing either identifier. Locator: Signed cover heading and first and final paragraphs.</p></dd><dt>Facility address</dt><dd>1601 North River Road, Douglasville, Georgia 30122, Douglas County<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Facility address from the signed permit, distinct from the Redmond mailing address. No exact Atlas building or metropolitan water report join. Locator: Signed cover facility and mailing address blocks.</p></dd><dt>Generator count</dt><dd>21 generators<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Twenty one additional generators in building 3 only: twenty rated 3,000 kW and one rated 500 kW. This is not a total campus inventory or count of installed or operating engines. Locator: Signed cover amendment clause.</p></dd><dt>Equipment code difference</dt><dd>The narrative table labels GN43 as a 500 kW engine and also includes GN43 within its 3,000 kW range GN43 through GN63.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The signed cover explicitly describes twenty plus one additional generators. No sixty three engine aggregate or corrected replacement source code is computed from this conflicting table. Locator: Narrative page 2 equipment table; signed cover addition clause.</p></dd><dt>Construction year difference</dt><dd>The narrative equipment table lists 2026 for building 3 installation and construction, while its federal applicability discussion says planned construction in 2025.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">These are inconsistent planning statements, not verified construction, installation or operation dates. Locator: Narrative pages 2 and 4.</p></dd><dt>State operating conditions</dt><dd>Condition 2.5 requires less than 500 annual operating hours per generator, with operation limited to routine testing and maintenance, utility power loss or internal system failures and recorded reasons.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Applies to GN1 through GN63. This strict annual condition is not relaxed by a notification duty at equality and does not establish actual hours. Locator: Amendment condition 2.5, printed page 2.</p></dd><dt>Seasonal testing</dt><dd>Routine testing and maintenance from May through September is allowed only from 10 p.m. through 4 a.m.; other months allow it at any time of day.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">A testing condition, not an observed operating schedule or general nighttime emergency restriction. Locator: Amendment condition 2.5(c), printed page 2.</p></dd><dt>Federal calendar allowances</dt><dd>Condition 2.3 describes up to 100 hours per calendar year for maintenance and readiness testing, with the stated petition or required testing provisions. The nonemergency allowance is up to 50 hours per calendar year counted within that 100 hours.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The fifty hours are not additional to the hundred. Financial arrangements and demand response are restricted subject to the stated conditional dispatch provisions. Separate state operating conditions still apply. Locator: Amendment condition 2.3(b), (c) and (c)(i), printed pages 1 and 2.</p></dd><dt>Federal emergency clause</dt><dd>Condition 2.3(a) states no time limit for emergency situations under that federal emergency engine clause.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">This does not remove the separate state condition requiring less than 500 total annual hours per generator or establish actual emergency operation. Locator: Amendment conditions 2.3(a) and 2.5(b).</p></dd><dt>Fuel</dt><dd>Diesel fuel with maximum sulfur content 15 ppm, plus a minimum cetane index of 40 or maximum aromatic content 35 volume percent.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Fuel specification, not a laboratory test, fuel consumption report or authorization for every alternative fuel mentioned in the narrative. Locator: Amendment condition 2.4, printed page 2.</p></dd><dt>Monitoring and records</dt><dd>Monthly emergency and nonemergency operating records must use each engine hour meter and retain the operating reason and records for five years. Operating and monitoring equipment must be maintained under the stated monitoring provisions.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Monitoring and retention duties, not actual logs or a finding of compliance. Locator: Amendment conditions 5.2 and 7.2, printed page 3.</p></dd><dt>Hours notification triggers</dt><dd>Conditions 7.3 and 7.4 require written notice within 15 days when a generator rolling twelve month total equals or exceeds 500 total hours or 100 nonemergency hours respectively.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The equality triggers are notification duties, not permission to operate 500 hours, calendar year allowances, actual exceedances or actual filed notices. Locator: Amendment conditions 7.3 and 7.4, printed page 4.</p></dd><dt>Nox notification triggers</dt><dd>Conditions 7.5 and 7.6 require notice within 15 days when calculated combined NOx equals or exceeds 8.25 tons in a calendar month or 99 tons over a rolling twelve month period.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">These are the explicit amended notification thresholds. Referenced unchanged condition 2.2 is not reproduced in this amendment. No measured emissions, actual exceedance or complete base permit annual limit is independently assigned. Locator: Amendment conditions 7.5 and 7.6, printed pages 4 and 5.</p></dd><dt>Emissions calculation</dt><dd>Monthly calculations use recorded hours and the source load specific emission rate table, with the next highest listed load for intermediate loads.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">A prescribed calculation method and source factors, not an actual measured or reported pollutant quantity retained here. Locator: Amendment condition 7.5 and load rate table, printed pages 4 and 5.</p></dd><dt>Source cross reference difference</dt><dd>Condition 2.3(c) refers to condition 2.4(c)(i), while its dispatch subparagraph appears under 2.3(c)(i). Fuel shipment condition 5.3 refers to condition 2.8, which is not reproduced here.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Original references retained as unresolved source wording. No corrected legal cross reference or complete base requirement is substituted. Locator: Amendment printed pages 1 and 3.</p></dd><dt>Emissions model scope</dt><dd>The narrative calculates potential and constrained emissions using manufacturer information and other factors. Its toxic impact analysis uses a 200 hours per year assumption for long term benzene modeling.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The model assumption is not the operating cap. A column labeled Actual Emissions in this application analysis is not admitted as measured releases, exposure, current compliance or a health finding. Locator: Narrative emissions summary pages 2 and 3; toxic impact assessment pages 5 through 7.</p></dd><dt>Corrected comment history</dt><dd>The narrative initially says no comments were received by the February advisory deadline. Its addendum acknowledges a February 7 letter receipt problem and says that initial statement was erroneous; it also describes a March 28 letter.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The completed addendum corrects the initial receipt claim. Agency responses summarize comments; the full letters are not present in the captured appendix and were not read. Locator: Narrative page 1 and addendum pages 8 and 10.</p></dd><dt>Public period source difference</dt><dd>The addendum opening says public review ended March 29, 2025, while its later receipt discussion refers to a March 28 ending.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Both source statements retained. No reconciled exact public review closing day is assigned. Neither day is the April permit issuance. Locator: Narrative addendum pages 8 and 10.</p></dd><dt>Amendment review scope</dt><dd>The complete six page issued amendment and twelve page narrative were read. The earlier base permit and June 2024 amendment were linked in the official index but not substantively reviewed.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/Search?Name=Microsoft&amp;Permit=\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The amendment carries forward unchanged base requirements. A filtered index and historical amendment do not certify the full current unamended permit chain. Locator: Signed cover continuation clause; official FTY01 result rows.</p></dd><dt>Aggregate campus inventory</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The admitted count is the building 3 addition only. No reconciled aggregate is computed from the conflicting source code table. Locator: Bounded final amendment and narrative review.</p></dd><dt>Current permit validity</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The complete current permit chain and all unchanged base conditions have not been reviewed. Locator: Bounded final amendment and narrative review.</p></dd><dt>Actual installed equipment</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No verified as built inventory or installation record reviewed. Locator: Bounded final amendment and narrative review.</p></dd><dt>Actual generation</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual generated electricity reviewed. Locator: Bounded final amendment and narrative review.</p></dd><dt>Actual started on</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual commissioning or startup date verified. Locator: Bounded final amendment and narrative review.</p></dd><dt>Actual diesel consumption</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual fuel consumption quantity reviewed. Locator: Bounded final amendment and narrative review.</p></dd><dt>Measured emissions</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Narrative calculations and modeled concentrations are not measured emissions. Locator: Bounded final amendment and narrative review.</p></dd><dt>Actual compliance</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual compliance finding, filed notification or measured exceedance reviewed. Locator: Bounded final amendment and narrative review.</p></dd><dt>Atlas record id</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29541\">Georgia Environmental Protection Division</a>. Source: April 15, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29541\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No exact Atlas building, parcel or operating record join established. The Microsoft Atlanta water disclosure is a separate metropolitan scope. Locator: Bounded final amendment and narrative review.</p></dd></dl></article>"},{"id":"air-ga-equinix-atlanta-20260630","html":"<article><h3>Equinix Atlanta dated permit for 149 generators and separate fire pump</h3><p class=\"layer-scope\">Issued June 2026 air permit with conditional construction and operation, distinct engine table limits and retained source reference differences. Permission is not installed inventory, actual emissions, actual fuel or current operation.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>permitted<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/Search?Name=Equinix\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Signed issued air permit for conditional construction and operation, not proof of actual construction, startup, installed generators or current operation. Locator: Signed permit cover and matching public search issuance row.</p></dd><dt>Engine table limit basis</dt><dd>Issued permit with distinct general and engine table limits<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The specific engine table, general criteria and federal provisions remain separate. No blanket five hundred hour operating allowance is inferred. Locator: Permit conditions 1.5,2.2,2.5 and 2.11.</p></dd><dt>Permit number</dt><dd>7374-151-0068-E-01-0<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Exact issued permit identifier, not a campus operating license or an approval of every other project permit. Locator: Permit cover and all page headers.</p></dd><dt>Airs number</dt><dd>04-13-151-00068<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Exact agency facility identifier in this document. No separate Atlas facility record is joined. Locator: Permit cover.</p></dd><dt>Issued on</dt><dd>June 30, 2026<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/Search?Name=Equinix\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Actual permit issuance day, not a generator startup or electricity service date. Locator: Signed cover issuance date and official public index.</p></dd><dt>Application on</dt><dd>October 3, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Application day referenced by both permit and narrative; differing application numbers are retained separately. Locator: Permit cover application reference and narrative page 1.</p></dd><dt>Review memo dated on</dt><dd>November 25, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Explicit narrative memo header date, not the final permit issuance or exact publication day. Locator: Narrative page 1 date.</p></dd><dt>Public advisory opened on</dt><dd>October 8, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Narrative reports a public advisory issued on this day. Underlying advisory and every comment were not independently reviewed. Locator: Narrative page 2 advisory paragraph.</p></dd><dt>Public advisory closed on</dt><dd>November 7, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Narrative reports that advisory expired on this day, distinct from final June 2026 issuance. Locator: Narrative page 2 advisory paragraph.</p></dd><dt>Facility address</dt><dd>1100 Site Parkway, Hampton, Georgia 30228, Henry County<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Address printed on this permit. Not a parcel geometry, exact site point or proof the facility is operating. Locator: Permit cover.</p></dd><dt>Generator count</dt><dd>149 generators<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permitted diesel emergency standby generators. The separate fire pump is excluded from this count. Not installed equipment or actual operation. Locator: Permit cover authorization.</p></dd><dt>Separate fire pump</dt><dd>One diesel fired fire pump is authorized in addition to the 149 emergency generators.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Cover distinguishes the pump from generators even though some permit conditions call all source codes emergency generators. No count of 150 generators is inferred. Locator: Permit cover and Attachment A.</p></dd><dt>Rated equipment schedule</dt><dd>Attachment A lists EG1 through EG144 at 3.62 MW, EG145 through EG148 at 1.0 MW, EG149 at 0.25 MW, and EG150 at 210 HP.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Literal equipment schedule categories and units, not a summed IT load, utility contract capacity or a conversion of horsepower into MW. Locator: Attachment A, PDF page 2.</p></dd><dt>General hour criteria</dt><dd>Condition 2.2 permits emergency, routine testing and maintenance or internal system failure uses under stated criteria, including less than 500 hours per year for each generator.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">General annual criteria do not override the stricter engine table in condition 2.11. The conditional alternate NOx standard in 2.2 is not an actual exceedance or an automatic exemption from other permit limits. Locator: Conditions 2.2 a through 2.2 d, PDF pages 3 through 4.</p></dd><dt>Specific rolling hour limits</dt><dd>Condition 2.11 prohibits exceeding its engine table hours in any twelve consecutive months. The table prints 37 hours for the 3.5 MW engine class and 39 hours for the 1.0 MW, guard shack and fire pump entries.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Specific rolling period limits, not annual expected use, model assumptions, calendar year totals or actual operation. Table capacity labels and equipment tags differ from Attachment A and are not silently remapped. Locator: Condition 2.11 and Table 2.11.1, PDF page 7.</p></dd><dt>Strictest condition</dt><dd>Condition 1.5 says the most stringent permit condition prevails when permit conditions conflict for a source or operation.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The federal emergency time statement does not erase the specific state permit engine table limits. This is a summary of this dated permit, not independent adjudication of a current facility compliance question. Locator: Condition 1.5, PDF page 3.</p></dd><dt>Seasonal test window</dt><dd>Routine testing and maintenance during May through September occurs only between 10 p.m. and 4 a.m. The other listed months allow those activities at any time of day.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">A permit time window for testing and maintenance, not a measured nighttime event, an emergency operation curfew or a finding about noise. Locator: Condition 2.2 c, PDF page 4.</p></dd><dt>Federal nonemergency limits</dt><dd>The permit prints a maximum of 100 hours per calendar year for ordinary maintenance and readiness testing, with specified petition or required testing exceptions. Up to 50 nonemergency hours are included within that 100 hour category.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The 50 hours are not added to 100. The printed federal emergency provision has no time limit, but the other permit conditions and stricter engine table still apply. Current full federal rule text was not separately reviewed. Locator: Conditions 2.5 a through 2.5 c, PDF pages 4 through 5.</p></dd><dt>Nonemergency dispatch conditions</dt><dd>The permit prohibits ordinary peak shaving, nonemergency demand response and financial power arrangements, except a stated local reliability dispatch pathway requiring all listed conditions.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The narrow exception requires authorized local dispatch, transmission or distribution limitation mitigation, specified reliability protocols, limited recipients and dispatch records. Not a blanket approved grid service or proof the pathway was used. Locator: Condition 2.5 c.i A through E, PDF page 5.</p></dd><dt>Nox limit scope</dt><dd>Condition 2.1 limits emissions from listed codes EG1 through EG150 to 249 tons per twelve consecutive months.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">A permitted emission cap including the listed pump code, not measured pollution, a per generator allowance, a calendar year reading or a metric ton conversion. The source calculation uses 2000 pounds per ton. Locator: Condition 2.1, PDF page 3 andcondition 7.8 formula, PDF page 11.</p></dd><dt>Monitoring requirements</dt><dd>Each listed engine requires a nonresettable hour meter, operating reason and cumulative hour records, plus a nonresettable fuel consumption meter.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Monitoring duties and record specifications, not evidence that a meter is installed, a public continuous emissions feed or actual fuel consumption. Locator: Conditions 5.2 and 7.2, PDF pages 8 and 10.</p></dd><dt>Startup notice</dt><dd>Startup notification is required within fifteen days after startup.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">After startup deadline, not a notice due before startup or evidence a startup notice was filed. Locator: Condition 7.1, PDF page 10.</p></dd><dt>Hour notification scope</dt><dd>The permit requires monthly rolling hour calculations and written notice within fifteen days when specified emergency hours equal or exceed 500, nonemergency hours equal or exceed 100, or the engine table thresholds are reached.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">These are notification triggers, not additional operating allowances or actual violations. Condition 7.10 requests calculations using emergency plus nonemergency data but its notice clause refers to emergency service time; that wording difference is retained. Locator: Conditions 7.3,7.4 and 7.10, PDF pages 10 and 12.</p></dd><dt>Emission notification scope</dt><dd>Written notice within fifteen days is required if facility NOx exceeds 20.75 tons in a calendar month or 249 tons on a twelve month rolling basis.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Different monthly notification and rolling cap periods, not two measured emissions values or independent compliance findings. No hours or pollution are inferred from the notification duty. Locator: Conditions 7.8 and 7.9, PDF pages 11 through 12.</p></dd><dt>Application reference difference</dt><dd>The signed permit cover references application 29889, while the public document links and narrative identify 29899.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/Search?Name=Equinix\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Source identifier difference retained. No silent replacement or second facility application is invented. Locator: Permit cover versus public OP29899/ON29899 links and narrative page 1.</p></dd><dt>Capacity and tag differences</dt><dd>Attachment A uses EG1 through EG150 and a 3.62 MW large engine row. The hour table uses E1 through E150 and a 3.5 MW column. The narrative equipment list uses different E code groups and explains different engine choices for modeled criteria pollutants and toxics.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No exact mapping between conflicting tags or capacity descriptions is repaired. Narrative worst case modeling is not actual engine inventory, measured output or present operating load. Locator: Attachment A; condition 2.11 table; narrative page 2.</p></dd><dt>Construction date boundary</dt><dd>Attachment A prints 2025 or later for construction and installation categories.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <p class=\"layer-scope\">A broad schedule entry, not an actual completed construction, installation or startup date. Locator: Attachment A, PDF page 2.</p></dd><dt>Source review boundary</dt><dd>All twelve issued permit pages and only the first five of nineteen narrative pages were read.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Nine relevant originals actually viewed. Remaining narrative pages, the complete underlying application, later amendments, operating records and current full federal rules were not reviewed or certified as a complete governing stack. Locator: Complete permit and bounded narrative pages 1 through 5.</p></dd><dt>Actual started on</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual startup day or filed startup notice reviewed. Locator: Bounded issued permit and narrative only.</p></dd><dt>Actual installed equipment</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual installation inventory established from the permission. Locator: Bounded issued permit and narrative only.</p></dd><dt>Actual annual hours</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual engine operating hour records reviewed. Locator: Bounded issued permit and narrative only.</p></dd><dt>Measured emissions</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The emission cap and potential calculations are not measured pollution. Locator: Bounded issued permit and narrative only.</p></dd><dt>Measured fuel consumption</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual fuel meter records reviewed. Locator: Bounded issued permit and narrative only.</p></dd><dt>Actual compliance</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No independent current compliance finding established. Locator: Bounded issued permit and narrative only.</p></dd><dt>Actual test results</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual performance test reports reviewed. Locator: Bounded issued permit and narrative only.</p></dd><dt>Total capacity mw</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No aggregate generator or IT electrical capacity calculated. Locator: Bounded issued permit and narrative only.</p></dd><dt>Resolved source tag map</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Equipment codes and capacity labels differ between attachment, table and narrative; no repaired mapping established. Locator: Bounded issued permit and narrative only.</p></dd><dt>Current governing permit</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Later amendments and complete current governing edition not certified by this bounded review. Locator: Bounded issued permit and narrative only.</p></dd><dt>Latest federal rule</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Current full federal rule text not separately reviewed. Locator: Bounded issued permit and narrative only.</p></dd><dt>Complete application</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The complete underlying application and all appendices were not reviewed. Locator: Bounded issued permit and narrative only.</p></dd><dt>Atlas record id</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29899\">Georgia Environmental Protection Division</a>. Source: June 30, 2026. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29899\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No exact Atlas facility or parcel joined. Locator: Bounded issued permit and narrative only.</p></dd></dl></article>"},{"id":"air-ga-ms-cco06-20250604","html":"<article><h3>Microsoft CCO06 dated 121 generator replacement permit</h3><p class=\"layer-scope\">Dated June 2025 air construction authorization, distinct calendar and rolling clocks, replacement permit and startup triggered application duty. Permitted is not operating.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>permitted<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/Search?Name=Microsoft\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Issued dated conditional construction permit. Not installed generators, current operation, current full permit stack or proof all project approvals exist. Locator: Signed cover and matching public index.</p></dd><dt>Cco06 permit basis</dt><dd>Issued replacement permit with separate calendar and rolling clocks<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The complete dated permit controls this summary; narrative proposals and equipment years are kept separate from operating facts. Locator: Cover and conditions 1.5, 2.2, 2.3, 2.5, 7.2 through 7.5 and 8.3 through 8.4.</p></dd><dt>Permit number</dt><dd>7376-121-0968-E-02-0<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Exact printed identifier. No independent operating status inferred. Locator: Permit cover.</p></dd><dt>Airs number</dt><dd>04-13-121-00968<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Agency facility identifier in this permit, not a joined Atlas record. Locator: Permit cover.</p></dd><dt>Issued on</dt><dd>June 4, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/Search?Name=Microsoft\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permit issuance day, not generator startup or service day. Locator: Signed cover.</p></dd><dt>Application on</dt><dd>January 31, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29582\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Referenced application day, not receipt, issuance or construction completion. Locator: Permit cover and narrative page 1.</p></dd><dt>Application received on</dt><dd>February 3, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29582\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Receipt day explicitly described in the dated narrative. Locator: Narrative page 1.</p></dd><dt>Review memo dated on</dt><dd>March 20, 2025<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29582\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Narrative header day, not final permit issuance or exact online publication. Locator: Narrative page 1.</p></dd><dt>Facility address</dt><dd>0 Williams Road, Palmetto, Georgia 30268, Fulton County<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Address printed in this permit. No parcel geometry, precise point or operating status inferred. Locator: Permit cover.</p></dd><dt>Generator count</dt><dd>121 generators<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permitted equipment count from the cover categories and GN1 through GN121 source range. Not an installed inventory or an additional 121 on top of older permits. Locator: Cover and repeated GN1 through GN121 conditions.</p></dd><dt>Rated generator categories</dt><dd>The cover authorizes 116 emergency generators rated 3000 kW each and five rated 500 kW each for Buildings 1 through 5.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Electrical ratings and categories, not a summed IT load, approved utility capacity or actual output. Locator: Permit cover.</p></dd><dt>New vs prior scope</dt><dd>The review describes a request to add eighty 3000 kW and three 500 kW generators for Buildings 3 through 5. Its equipment schedule extends through GN121 across all five buildings.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29582\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The requested addition is not added again to the replacement permit total. Table construction and installation years are not independently verified startup dates. Locator: Narrative pages 1 and 2.</p></dd><dt>Prior permits replaced</dt><dd>Condition 8.4 revokes all previously issued Georgia air permits for this facility, including the named S 01 0 permit and its amendments.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">A replacement authorization. Old and new permit counts are not summed as independent operating fleets. This review does not certify a later Title V issuance or current complete stack. Locator: Condition 8.4, PDF page 9.</p></dd><dt>Nox limit scope</dt><dd>The entire facility must remain below 249 tons of NOx during any twelve consecutive month period.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Condition 2.2 prohibits emissions equal to or greater than 249 tons. A rolling cap, not measured pollution, a per generator allowance or a calendar year inventory. The calculation uses 2000 pounds per ton; no metric conversion made. Locator: Condition 2.2, PDF page 2 and formula PDF page 8.</p></dd><dt>General hour criteria</dt><dd>Condition 2.5 lists routine testing and maintenance, utility power unavailability or internal failures, with total operation for each generator less than 500 hours per year.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">The dated state criterion is distinct from federal calendar year maintenance and the later rolling notice tests. Conditional alternate ozone season NOx provisions do not establish an actual exceedance or erase other requirements. Locator: Conditions 2.5 a through d, PDF page 4.</p></dd><dt>Federal calendar limits</dt><dd>The permit prints 100 hours per calendar year for ordinary maintenance and readiness testing with specified petition or required testing exceptions. Its 50 nonemergency hours are included in that 100 hour category.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Fifty is not added to one hundred. The printed federal emergency time statement has no limit, but condition 1.5 retains the most stringent permit condition when provisions conflict. Current complete federal rules were not separately reviewed. Locator: Conditions 1.5 and 2.3, PDF pages 2 through 4.</p></dd><dt>Dispatch exception</dt><dd>Ordinary peak shaving, nonemergency demand response and financial power arrangements are prohibited except a local reliability dispatch pathway requiring every listed condition.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Conditional dispatch authority, system limitation mitigation, protocols, recipients and records are required. Not proof of actual dispatch or blanket grid service eligibility. The text refers to condition 2.4.c.i while the printed exception is organized under 2.3.c.i; that cross reference is not silently repaired. Locator: Conditions 2.3 c through E, PDF pages 3 through 4.</p></dd><dt>Seasonal test window</dt><dd>Routine testing and maintenance during May through September occurs only between 10 p.m. and 4 a.m. The other listed months allow those activities at any time of day.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Permit scheduling requirement, not a measured event, noise finding or emergency curfew. Locator: Condition 2.5 c, PDF page 4.</p></dd><dt>Rolling hour notices</dt><dd>Monthly calculations of twelve month rolling hours trigger written notice within fifteen days at 500 hours of total operation or at 100 hours of nonemergency operation for any generator.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Rolling notice triggers differ from the printed calendar year federal maintenance limit. Notice thresholds are not added allowances or actual reported exceedances. Locator: Conditions 7.2 and 7.3, PDF page 7.</p></dd><dt>Monthly and rolling nox notices</dt><dd>NOx calculation and written notification within fifteen days use separate triggers of 20.75 tons during a calendar month and 249 tons during a twelve month rolling period.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">A monthly notice level is not the rolling emission cap. Neither number is actual emissions or an annual calendar inventory. Locator: Conditions 7.4 and 7.5, PDF pages 7 through 8.</p></dd><dt>Fuel requirements</dt><dd>The issued permit specifies diesel fuel with maximum sulfur of 15 ppm and either minimum cetane index of 40 or maximum aromatic content of 35 volume percent, plus its listed distillate fuel specifications.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Fuel specifications are not gallons used, an actual renewable diesel share or an emissions reduction. The narrative discusses renewable hydrocarbon diesel separately; no separate current fuel eligibility adjudication made. Locator: Conditions 2.4, 2.8, 5.3 and 7.8, PDF pages 4 through 6 and 9.</p></dd><dt>Monitoring duties</dt><dd>Each generator requires a nonresettable hour meter, operating reasons and cumulative hour records. Monthly emergency and nonemergency records are retained for five years.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Requirements to monitor and preserve records, not evidence that meters or records exist or compliance was achieved. Locator: Conditions 5.1, 5.2 and 7.1, PDF pages 5 through 7.</p></dd><dt>Title v application clock</dt><dd>Within twelve months after startup of new generators GN39 through GN121, a complete Part 70 application must be submitted.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">An application duty triggered by startup, not an issued Title V permit, a known startup day, a fixed calendar filing deadline or evidence that a filing was made. Locator: Condition 8.3, PDF page 9.</p></dd><dt>Source reference differences</dt><dd>The issued cover and narrative first page identify application 29582. Later narrative page headers print 29852. The narrative discusses prior 99 ton limits and requested expansion, while the issued permit gives its own rolling 249 ton condition.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29582\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Source identifier and scope differences retained. Narrative equipment years and columns labeled Actual Emissions are not promoted into measured operations, startup or current compliance. Locator: Permit cover; narrative pages 1 through 5.</p></dd><dt>Review boundary</dt><dd>The complete nine page issued permit and first five pages of the forty three page narrative were read, together with the substantive public index. Nine relevant original PDF pages were actually viewed.<span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/ON-29582\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/Search?Name=Microsoft\">Georgia Environmental Protection Division</a>. Source: Publication date not stated. Checked: October 24, 2026.</span> <p class=\"layer-scope\">Remaining narrative pages, full application, underlying monitoring records, later permits and current federal legal stack were not reviewed as complete evidence. This dated document is not a current operating census. Locator: Bounded source review.</p></dd><dt>Startup on</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual startup day established. Locator: Dated permit and bounded narrative only.</p></dd><dt>Installed generator count</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No physical installed generator inventory established. Locator: Dated permit and bounded narrative only.</p></dd><dt>Actual operating hours</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual operating hour records reviewed. Locator: Dated permit and bounded narrative only.</p></dd><dt>Actual nox emissions</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No measured emissions inventory established. Locator: Dated permit and bounded narrative only.</p></dd><dt>Actual fuel used</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual fuel deliveries or gallons used established. Locator: Dated permit and bounded narrative only.</p></dd><dt>Actual compliance</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No current compliance finding established. Locator: Dated permit and bounded narrative only.</p></dd><dt>Title v filed on</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No actual subsequent Part 70 application filing reviewed. Locator: Dated permit and bounded narrative only.</p></dd><dt>Current permit stack</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No complete current permit chain certified. Locator: Dated permit and bounded narrative only.</p></dd><dt>Total it capacity</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No facility IT demand or actual generator output established. Locator: Dated permit and bounded narrative only.</p></dd><dt>Atlas record id</dt><dd><span class=\"layer-empty\">Not established</span><span class=\"layer-source\"><a href=\"https://air.gaepd.org/Permits/View/OP-29582\">Georgia Environmental Protection Division</a>. Source: June 4, 2025. Checked: October 24, 2026.</span> <p class=\"layer-scope\">No exact Atlas facility, parcel or project record join made. Locator: Dated permit and bounded narrative only.</p></dd></dl></article>"},{"id":"air-egrid-state-2023-ga","html":"<article><h3>Georgia historical2023 electricity-generation emissions</h3><p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>historical<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 Data Year column.</p></dd><dt>Egrid report year</dt><dd>2023<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 YEAR column.</p></dd><dt>Egrid state fips</dt><dd>13<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 FIPSST column.</p></dd><dt>Egrid state basis</dt><dd>EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence.<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 labels,codes,units and review scope.</p></dd><dt>Egrid annual net generation</dt><dd>129220273.26 MWh<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 GA row 13, STNGENAN (State annual net generation (MWh)).</p></dd><dt>Egrid annual nox emissions</dt><dd>18438.11 tons<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 GA row 13, STNOXAN (State annual NOx emissions (tons)).</p></dd><dt>Egrid annual so2 emissions</dt><dd>12892.40 tons<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 GA row 13, STSO2AN (State annual SO2 emissions (tons)).</p></dd><dt>Egrid annual co2 emissions</dt><dd>46120743.10 tons<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 GA row 13, STCO2AN (State annual CO2 emissions (tons)).</p></dd><dt>Egrid nox total output rate</dt><dd>0.28 lb per MWh<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 GA row 13, STNOXRTA (State annual NOx total output emission rate (lb/MWh)).</p></dd><dt>Egrid so2 total output rate</dt><dd>0.20 lb per MWh<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 GA row 13, STSO2RTA (State annual SO2 total output emission rate (lb/MWh)).</p></dd><dt>Egrid co2 total output rate</dt><dd>713.83 lb per MWh<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">EPA eGRID2023 revision2 state electricity-generation emissions context,ST23 worksheet. Historical2023,not current2026 conditions or data center facility emissions. Annual NOx,SO2 andCO2 totals in source tons are distinct from source-reported total output rates in lb/MWh;CO2 is not CO2 equivalent. Annual net generation is MWh,not installed capacity or customer use. Rates are not marginal emissions,ambient concentrations,health effects or emissions factors allocated to a data center. No tons-to-tonnes conversion,rate recomputation,facility join or causal data center inference. State generation context does not establish the mix delivered to consumers. Puerto Rico source row is outside this51state/DC review,not absence. Locator: ST23 GA row 13, STCO2RTA (State annual CO2 total output emission rate (lb/MWh)).</p></dd><dt>Egrid annual ch4 emissions lb</dt><dd>7079195.60 lbs<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference. Locator: ST23 GA row 13, STCH4AN (State annual CH4 emissions (lbs)).</p></dd><dt>Egrid annual co2e emissions</dt><dd>46354208.31 tons<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference. Locator: ST23 GA row 13, STCO2EQA (State annual CO2 equivalent emissions (tons)).</p></dd><dt>Egrid annual n2o emissions lb</dt><dd>1014011.08 lbs<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference. Locator: ST23 GA row 13, STN2OAN (State annual N2O emissions (lbs)).</p></dd><dt>Egrid ozone season nox total output rate</dt><dd>0.22 lb per MWh<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference. Locator: ST23 GA row 13, STNOXRTO (State ozone season NOx total output emission rate (lb/MWh)).</p></dd><dt>Egrid extended basis</dt><dd>Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference.<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference. Locator: ST23 field labels,report year and annual-versus-ozone-season units.</p></dd><dt>Egrid ozone season nox emissions</dt><dd>6754.11 tons<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference. Locator: ST23 GA row 13, STNOXOZ (State ozone season NOx emissions (tons)).</p></dd><dt>Egrid co2e total output rate</dt><dd>717.45 lb per MWh<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference. Locator: ST23 GA row 13, STC2ERTA (State annual CO2 equivalent total output emission rate (lb/MWh)).</p></dd><dt>Egrid ch4 total output rate</dt><dd>0.06 lb per MWh<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference. Locator: ST23 GA row 13, STCH4RTA (State annual CH4 total output emission rate (lb/MWh)).</p></dd><dt>Egrid n2o total output rate</dt><dd>0.01 lb per MWh<span class=\"layer-source\"><a href=\"https://www.epa.gov/system/files/documents/2025-06/egrid2023_data_rev2.xlsx\">U.S. Environmental Protection Agency</a>. Source: Publication date not stated. Checked: October 27, 2026.</span> <p class=\"layer-scope\">Historical2023 EPA eGRID ST23 source-reported CH4,N2O,CO2 equivalent and ozone-season NOx context. Annual CH4/N2O totals are source lbs;CO2 equivalent total is source tons;total output rates are lb/MWh. CO2 equivalent differs from raw CO2; no global-warming-potential factor assumed or recomputed,no pounds/tons/metric-tonne conversion. Source-defined ozone-season NOx is not full-year NOx or an ambient ozone concentration. Annual and seasonal rates and totals remain separate,not summed across scopes. No marginal,facility,health-risk or attributable data center emissions inference. Locator: ST23 GA row 13, STN2ORTA (State annual N2O total output emission rate (lb/MWh)).</p></dd></dl></article>"},{"id":"air-eia-state-emissions-2025-ga","html":"<article><h3>Georgia historical power and useful thermal emissions2025 and2024</h3><p class=\"layer-scope\">EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.</p><dl class=\"layer-fields\"><dt>Status</dt><dd>historical<span class=\"layer-source\"><a href=\"https://www.eia.gov/electricity/annual/table.php?t=epa_09_05.html\">U.S. Energy Information Administration</a>. Source: October 21, 2026. Checked: October 28, 2026.</span> <p class=\"layer-scope\">EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins. Locator: Table9.5 years2025 and2024.</p></dd><dt>Eia emissions basis</dt><dd>EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins.<span class=\"layer-source\"><a href=\"https://www.eia.gov/electricity/annual/table.php?t=epa_09_05.html\">U.S. Energy Information Administration</a>. Source: October 21, 2026. Checked: October 28, 2026.</span> <p class=\"layer-scope\">EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins. Locator: Table9.5 header and methodological notes.</p></dd><dt>Eia emissions co2 2025</dt><dd>43991.00 thousand metric tons<span class=\"layer-source\"><a href=\"https://www.eia.gov/electricity/annual/table.php?t=epa_09_05.html\">U.S. Energy Information Administration</a>. Source: October 21, 2026. Checked: October 28, 2026.</span> <p class=\"layer-scope\">EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins. Locator: Table9.5 Georgia row;co2;Year 2025.</p></dd><dt>Eia emissions co2 2024</dt><dd>42718.00 thousand metric tons<span class=\"layer-source\"><a href=\"https://www.eia.gov/electricity/annual/table.php?t=epa_09_05.html\">U.S. Energy Information Administration</a>. Source: October 21, 2026. Checked: October 28, 2026.</span> <p class=\"layer-scope\">EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins. Locator: Table9.5 Georgia row;co2;Year 2024.</p></dd><dt>Eia emissions so2 2025</dt><dd>40.00 thousand metric tons<span class=\"layer-source\"><a href=\"https://www.eia.gov/electricity/annual/table.php?t=epa_09_05.html\">U.S. Energy Information Administration</a>. Source: October 21, 2026. Checked: October 28, 2026.</span> <p class=\"layer-scope\">EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins. Locator: Table9.5 Georgia row;so2;Year 2025.</p></dd><dt>Eia emissions so2 2024</dt><dd>40.00 thousand metric tons<span class=\"layer-source\"><a href=\"https://www.eia.gov/electricity/annual/table.php?t=epa_09_05.html\">U.S. Energy Information Administration</a>. Source: October 21, 2026. Checked: October 28, 2026.</span> <p class=\"layer-scope\">EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins. Locator: Table9.5 Georgia row;so2;Year 2024.</p></dd><dt>Eia emissions nox 2025</dt><dd>34.00 thousand metric tons<span class=\"layer-source\"><a href=\"https://www.eia.gov/electricity/annual/table.php?t=epa_09_05.html\">U.S. Energy Information Administration</a>. Source: October 21, 2026. Checked: October 28, 2026.</span> <p class=\"layer-scope\">EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins. Locator: Table9.5 Georgia row;nox;Year 2025.</p></dd><dt>Eia emissions nox 2024</dt><dd>35.00 thousand metric tons<span class=\"layer-source\"><a href=\"https://www.eia.gov/electricity/annual/table.php?t=epa_09_05.html\">U.S. Energy Information Administration</a>. Source: October 21, 2026. Checked: October 28, 2026.</span> <p class=\"layer-scope\">EIA Table9.5 historical state2025 and2024 emissions estimates from energy consumption at conventional power and combined-heat-and-power plants. Includes electricity generation AND production of useful thermal output,not electricity-only emissions. Source unit is thousand metric tons,not eGRID source tons,pounds,CO2equivalent or emission intensity. Source CO2,SO2 and NOx are distinct pollutants,not summed as one climate measure. Displayed zero values may represent small values rounded to zero;no absence or zero-emissions certification. Retain displayed HTML precision;source says Excel cells provide additional precision,not adopted here. No direct eGRID trend or data center allocation,marginal emissions,ambient concentration,health risk,permit compliance,current2026 activity or Native facility joins. Locator: Table9.5 Georgia row;nox;Year 2024.</p></dd></dl></article>"}]}