  "schema_version": 1,
  "source_compilation_context": {
    "ga": {
      "attribution": {
        "inventory": {
          "name": "Compute Atlas",
          "creator": "Edward Kubiak",
          "url": "https://www.compute-atlas.com/api",
          "license": "CC BY 4.0",
          "license_url": "https://creativecommons.org/licenses/by/4.0/",
          "snapshot_url": "https://www.compute-atlas.com/api/facilities",
          "retrieved": "2026-10-14",
          "sha256": "79ad432dab7c128e428234c9d0dd40933114b415a4a5d697db00095637d50f37",
          "changes": "Added provenance, publication-date distinctions, display-safe wording, quarantine flags and state partitioning. Original source records retained locally."
        },
        "counties": "U.S. Census Bureau county boundaries (public domain)",
        "research": "Field-specific source context. See the linked source and limits on each record."
      },
      "source_data_url": "https://datacentersatlas.com/data/ga.json",
      "updated": "2026-10-24"
    }
  },
  "scope": "Exact retained city label subset. This is not a municipal boundary or complete city inventory. Research records retain their sources, dates and location limits. Counts are not a census of operating buildings. Company name links alone do not establish ownership or operation.",
  "collection": {
    "kind": "cities",
    "key": "ga/palmetto",
    "label": "Palmetto, Georgia"
  },
  "records": [
    {
      "id": "cyrusone-project-peach-palmetto-ga",
      "state": "ga",
      "kind": "facility",
      "name": "Project Peach (CyrusOne Palmetto Data Center Campus)",
      "group": "unknown",
      "status": "Status unclear",
      "raw_status": "",
      "status_field": "",
      "crypto": false,
      "type": "Data center (inventory classification)",
      "counties": [
        "Coweta"
      ],
      "city": "Palmetto",
      "address": "",
      "who": "",
      "end_user": "",
      "mw": null,
      "power": "",
      "power_note": "",
      "investment": "",
      "jobs": "",
      "acres": null,
      "utility": "",
      "water": "",
      "incentives": "",
      "note": "Manual source context is available for this inherited inventory record. The inventory label and approximate geography are retained for discovery. This is not certification of current operation, ownership, a separate physical building, technical capacity or a precise parcel. Missing fields remain unknown. Named content personally reviewed; no whole-record certification. Dates and forecasts remain source-specific.. Peach described as April2025 while May2026 roundup prints April2026: approval year held for original resolution. Allegations/communications not court findings. Sail economics not Peach figures. Subsequent original decisions and current operator disclosures take precedence. Fields can apply to shared campus, regional or historical context; consult source review before assigning to a building.",
      "date": "",
      "events": [
        [
          "2026-10-20",
          "Coweta County October 21, 2026 recap records October 20 Board approval of reversion of the former Project Peach REZONE 24 14 property from Light Industrial to Rural Conservation. This is a zoning action, not a data center opening, physical shutdown or an exact finding about construction activity."
        ]
      ],
      "timeline": [],
      "opened": "",
      "tier": "",
      "sources": [
        {
          "url": "https://www.desmog.com/2026/04/07/how-data-center-developers-staked-their-claim-in-rural-georgia/",
          "host": "desmog.com",
          "date": "2026-04-07",
          "published": "2026-04-07",
          "checked": "2026-10-14",
          "date_kind": "publication",
          "label": "Reviewed source"
        },
        {
          "url": "https://www.coweta.ga.us/m/newsflash/Home/Detail/53",
          "host": "www.coweta.ga.us",
          "published": "2026-10-21",
          "date": "2026-10-21",
          "checked": "2026-10-23",
          "label": "Reviewed government record"
        }
      ],
      "loc": {
        "lat": 33.36438,
        "lng": -84.77561,
        "precision": "county",
        "basis": "Shown at county level only. The dot is placed inside the county for the map and is not the site, its address or a parcel."
      },
      "reviewed_evidence": [
        {
          "overlay": "regional-development-review-round24-2026-10-14.json",
          "scope": "Named content personally reviewed; no whole-record certification. Dates and forecasts remain source-specific.",
          "fields": {
            "reported_context": "DeSmog distinguishes Project Peach CyrusOne rezoning from Project Sail Atlas/Prologis approval campaign.",
            "independently_verified_current_operating_status": null
          },
          "notes": [
            "Peach described as April2025 while May2026 roundup prints April2026: approval year held for original resolution. Allegations/communications not court findings. Sail economics not Peach figures.",
            "Subsequent original decisions and current operator disclosures take precedence.",
            "Fields can apply to shared campus, regional or historical context; consult source review before assigning to a building."
          ],
          "sources": [
            {
              "url": "https://www.desmog.com/2026/04/07/how-data-center-developers-staked-their-claim-in-rural-georgia/",
              "host": "desmog.com",
              "date": "2026-04-07",
              "published": "2026-04-07",
              "checked": "2026-10-14",
              "date_kind": "publication",
              "label": "Reviewed source"
            }
          ],
          "whole_record_certified": false
        },
        {
          "overlay": "Codex 3 research cohort 19",
          "scope": "Coweta October 21, 2026 recap says the Board approved reversion of the former Project Peach REZONE 24 14 property from Light Industrial to Rural Conservation on October 20. This is an affirmative zoning action, not the older industrial approval or a mere scheduled hearing. The recap does not establish an operating facility shutdown, a physical construction phase, the final resolution of concerns or a new operator role. Current physical stage remains unclear; zoning reversion is retained as its own dated event.",
          "fields": {
            "current_stage_evidence": {
              "outcome": "recent_zoning_reversion_not_physical_shutdown",
              "scope": "Coweta October 21, 2026 recap says the Board approved reversion of the former Project Peach REZONE 24 14 property from Light Industrial to Rural Conservation on October 20. This is an affirmative zoning action, not the older industrial approval or a mere scheduled hearing. The recap does not establish an operating facility shutdown, a physical construction phase, the final resolution of concerns or a new operator role. Current physical stage remains unclear; zoning reversion is retained as its own dated event."
            },
            "government_record_scope": {
              "board_action_on": "2026-10-20",
              "county_recap_published_on": "2026-10-21",
              "zoning_reversion_not_operating_closure": true,
              "prior_industrial_approval_not_current_zone": true
            }
          },
          "notes": [
            "Coweta October 21, 2026 recap says the Board approved reversion of the former Project Peach REZONE 24 14 property from Light Industrial to Rural Conservation on October 20. This is an affirmative zoning action, not the older industrial approval or a mere scheduled hearing. The recap does not establish an operating facility shutdown, a physical construction phase, the final resolution of concerns or a new operator role. Current physical stage remains unclear; zoning reversion is retained as its own dated event.",
            "The review preserves existing physical identity, locations, roles, quantities and opening fields. Source issue dates, review checks and physical milestones remain distinct."
          ],
          "sources": [
            {
              "url": "https://www.coweta.ga.us/m/newsflash/Home/Detail/53",
              "host": "www.coweta.ga.us",
              "published": "2026-10-21",
              "date": "2026-10-21",
              "checked": "2026-10-23",
              "label": "Reviewed government record"
            }
          ],
          "checked": "2026-10-23",
          "whole_record_certified": false
        }
      ],
      "manual_source_reviewed": true,
      "whole_record_certified": false,
      "field_evidence_present": true,
      "inventory_label_retained": true,
      "precision_label": "Exact site not published; shown at county level",
      "summary": "Palmetto · Coweta · Source context reviewed",
      "event_evidence": [
        {
          "date": "2026-10-20",
          "text": "Coweta County October 21, 2026 recap records October 20 Board approval of reversion of the former Project Peach REZONE 24 14 property from Light Industrial to Rural Conservation. This is a zoning action, not a data center opening, physical shutdown or an exact finding about construction activity.",
          "kind": "approved",
          "sources": [
            {
              "url": "https://www.coweta.ga.us/m/newsflash/Home/Detail/53",
              "host": "www.coweta.ga.us",
              "published": "2026-10-21",
              "date": "2026-10-21",
              "checked": "2026-10-23",
              "label": "Reviewed government record"
            }
          ]
        }
      ],
      "location_display": {
        "policy": "reviewed-map-references-2026-10-23",
        "decision": "withheld_unreviewed_point",
        "scope": "The available point evidence does not establish a supported site location. No site pin, nearby distance or aerial destination is published. The original coordinate and its provenance remain in research history.",
        "county_display": "13077"
      }
    },
    {
      "id": "microsoft-palmetto-fulton-ga",
      "state": "ga",
      "kind": "facility",
      "name": "Microsoft Palmetto Data Center",
      "group": "building",
      "status": "Operator-reported construction",
      "raw_status": "under construction",
      "status_field": "current_status",
      "crypto": false,
      "type": "Data center (inventory classification)",
      "counties": [
        "Fulton"
      ],
      "city": "Palmetto",
      "address": "",
      "who": "Microsoft",
      "end_user": "",
      "mw": null,
      "power": "",
      "power_note": "",
      "investment": "",
      "jobs": "",
      "acres": null,
      "utility": "",
      "water": "",
      "incentives": "",
      "note": "Manual source context is available for this inherited inventory record. The inventory label and approximate geography are retained for discovery. This is not certification of current operation, ownership, a separate physical building, technical capacity or a precise parcel. Missing fields remain unknown. Microsoft Palmetto construction chronology. October2025constructiontargetnotobservedcompletionorcustomerenergization. Schoolinformation-sessionvenueandJohnsonRdviewnotverifiedfacilitystreetaddress. No MW or current construction completion in reviewed undated update. Fields can apply to shared campus, regional or historical context; consult source review before assigning to a building.",
      "date": "",
      "events": [],
      "timeline": [],
      "opened": "",
      "tier": "",
      "sources": [
        {
          "url": "https://local.microsoft.com/blog/palmetto-datacenter-construction-update/",
          "host": "local.microsoft.com",
          "date": "",
          "published": "",
          "checked": "2026-10-14",
          "date_kind": "publication date not established",
          "label": "Reviewed source"
        },
        {
          "url": "https://local.microsoft.com/communities/americas/greater-atlanta/",
          "host": "local.microsoft.com",
          "published": "",
          "date": "",
          "checked": "2026-10-22",
          "label": "Reviewed operator source"
        }
      ],
      "loc": {
        "lat": 33.78294,
        "lng": -84.50774,
        "precision": "county",
        "basis": "Shown at county level only. The dot is placed inside the county for the map and is not the site, its address or a parcel."
      },
      "reviewed_evidence": [
        {
          "overlay": "primary-source-review-round9-2026-10-14.json",
          "scope": "Microsoft Palmetto construction chronology",
          "fields": {
            "operator_site_name": "Palmetto datacenter",
            "locality": "Palmetto, Georgia",
            "construction_start": "2024-04",
            "construction_start_precision": "month",
            "historical_construction_completion_estimate": "beginning of2025-10",
            "operator_community_information_session_date": "2024-07-23",
            "general_contractor": "Turner Construction Company"
          },
          "notes": [
            "October2025constructiontargetnotobservedcompletionorcustomerenergization. Schoolinformation-sessionvenueandJohnsonRdviewnotverifiedfacilitystreetaddress. No MW or current construction completion in reviewed undated update.",
            "Fields can apply to shared campus, regional or historical context; consult source review before assigning to a building."
          ],
          "sources": [
            {
              "url": "https://local.microsoft.com/blog/palmetto-datacenter-construction-update/",
              "host": "local.microsoft.com",
              "date": "",
              "published": "",
              "checked": "2026-10-14",
              "date_kind": "publication date not established",
              "label": "Reviewed source"
            }
          ],
          "whole_record_certified": false
        },
        {
          "overlay": "Codex 3 research cohort 12",
          "scope": "The current Microsoft Georgia location page names Palmetto as a data center construction location. The separate Palmetto update records a start month of April 2024 and an estimated completion by the beginning of October 2025. Operator reported construction is the current listing claim. The expired estimate is not verified completion or operation, and the start month is not converted into an exact day.",
          "fields": {
            "current_stage_evidence": {
              "outcome": "operator_reported_construction",
              "scope": "The current Microsoft Georgia location page names Palmetto as a data center construction location. The separate Palmetto update records a start month of April 2024 and an estimated completion by the beginning of October 2025. Operator reported construction is the current listing claim. The expired estimate is not verified completion or operation, and the start month is not converted into an exact day."
            },
            "date_scope": {
              "reported_construction_start_month": "2024-04",
              "exact_start_day_established": false,
              "older_completion_forecast": "beginning of October 2025",
              "forecast_occurrence_verified": false
            }
          },
          "notes": [
            "The current Microsoft Georgia location page names Palmetto as a data center construction location. The separate Palmetto update records a start month of April 2024 and an estimated completion by the beginning of October 2025. Operator reported construction is the current listing claim. The expired estimate is not verified completion or operation, and the start month is not converted into an exact day.",
            "The review preserves existing physical identity, locations, roles, quantities and opening fields. Document and source check dates remain separate from physical milestones."
          ],
          "sources": [
            {
              "url": "https://local.microsoft.com/communities/americas/greater-atlanta/",
              "host": "local.microsoft.com",
              "published": "",
              "date": "",
              "checked": "2026-10-22",
              "label": "Reviewed operator source"
            },
            {
              "url": "https://local.microsoft.com/blog/palmetto-datacenter-construction-update/",
              "host": "local.microsoft.com",
              "published": "",
              "date": "",
              "checked": "2026-10-22",
              "label": "Reviewed operator source"
            }
          ],
          "checked": "2026-10-22",
          "whole_record_certified": false
        },
        {
          "overlay": "Company role source check59, October24,2026",
          "scope": "Microsoft identifies its own Palmetto data center project in the main body of the official community update. Developer per source identifies the Microsoft provider brand for this retained project only. The previously empty company field is filled from that explicit source, without assigning a legal subsidiary, landowner, contractor or current operator. Existing status, location, address, county, quantities, dates and component identity remain exact. Any separately retained street is identity context only and does not newly admit a location, parcel or roof. Proposed designs, forecast schedules, contractor descriptions and community measures do not certify current physical completion, operation, permits, impacts or site ownership. Declared publication and modification dates are separate from construction milestones. No personal contact or resident names are retained in the review. Microsoft reports construction from April 2024 and names Turner Construction Company as general contractor. The elapsed October 2025 completion estimate is not a verified completion or opening; Palmetto Elementary School was a meeting venue, not the site.",
          "fields": {
            "company_association": {
              "name": "Microsoft",
              "role": "developer",
              "identity_scope": "provider_brand_only",
              "scope": "Microsoft identifies its own Palmetto data center project in the main body of the official community update. Developer per source identifies the Microsoft provider brand for this retained project only. The previously empty company field is filled from that explicit source, without assigning a legal subsidiary, landowner, contractor or current operator. Existing status, location, address, county, quantities, dates and component identity remain exact. Any separately retained street is identity context only and does not newly admit a location, parcel or roof. Proposed designs, forecast schedules, contractor descriptions and community measures do not certify current physical completion, operation, permits, impacts or site ownership. Declared publication and modification dates are separate from construction milestones. No personal contact or resident names are retained in the review. Microsoft reports construction from April 2024 and names Turner Construction Company as general contractor. The elapsed October 2025 completion estimate is not a verified completion or opening; Palmetto Elementary School was a meeting venue, not the site."
            },
            "provider_role": "developer"
          },
          "notes": [
            "Microsoft identifies its own Palmetto data center project in the main body of the official community update. Developer per source identifies the Microsoft provider brand for this retained project only. The previously empty company field is filled from that explicit source, without assigning a legal subsidiary, landowner, contractor or current operator. Existing status, location, address, county, quantities, dates and component identity remain exact. Any separately retained street is identity context only and does not newly admit a location, parcel or roof. Proposed designs, forecast schedules, contractor descriptions and community measures do not certify current physical completion, operation, permits, impacts or site ownership. Declared publication and modification dates are separate from construction milestones. No personal contact or resident names are retained in the review. Microsoft reports construction from April 2024 and names Turner Construction Company as general contractor. The elapsed October 2025 completion estimate is not a verified completion or opening; Palmetto Elementary School was a meeting venue, not the site."
          ],
          "sources": [
            {
              "url": "https://local.microsoft.com/blog/palmetto-datacenter-construction-update/",
              "host": "local.microsoft.com",
              "published": "2024-07-03",
              "date": "2024-07-03",
              "checked": "2026-10-24",
              "label": "Reviewed operator source"
            }
          ],
          "checked": "2026-10-24",
          "whole_record_certified": false
        }
      ],
      "manual_source_reviewed": true,
      "whole_record_certified": false,
      "field_evidence_present": true,
      "inventory_label_retained": true,
      "precision_label": "Exact site not published; shown at county level",
      "summary": "Palmetto · Fulton · Source context reviewed",
      "status_scope": "The current Microsoft Georgia location page names Palmetto as a data center construction location. The separate Palmetto update records a start month of April 2024 and an estimated completion by the beginning of October 2025. Operator reported construction is the current listing claim. The expired estimate is not verified completion or operation, and the start month is not converted into an exact day.",
      "location_display": {
        "policy": "reviewed-map-references-2026-10-23",
        "decision": "withheld_unreviewed_point",
        "scope": "The available point evidence does not establish a supported site location. No site pin, nearby distance or aerial destination is published. The original coordinate and its provenance remain in research history.",
        "county_display": "13121"
      }
    },
    {
      "id": "t5-atlanta-iv-palmetto-ga",
      "state": "ga",
      "kind": "facility",
      "name": "T5 @ Atlanta IV",
      "group": "unknown",
      "status": "Status unclear",
      "raw_status": "",
      "status_field": "",
      "crypto": false,
      "type": "Data center (inventory classification)",
      "counties": [
        "Fulton"
      ],
      "city": "Palmetto",
      "address": "",
      "who": "",
      "end_user": "",
      "mw": null,
      "power": "",
      "power_note": "",
      "investment": "",
      "jobs": "",
      "acres": null,
      "utility": "",
      "water": "",
      "incentives": "",
      "note": "Manual source context is available for this inherited inventory record. The inventory label and approximate geography are retained for discovery. This is not certification of current operation, ownership, a separate physical building, technical capacity or a precise parcel. Missing fields remain unknown. Named-site context, with limited previews/corridor crosswalks explicitly identified.. Jarred Schenke, Bisnow June 12, 2024 original Fairburn planning-director interview: early T5 proposal near I-85/Gullatt, 495,000 square feet/two buildings, land not yet owned and use permit still needed. Limited corridor crosswalk to inherited Atlanta IV/Palmetto row; exact parcel/city-boundary discrepancy and later 200/300 MW claims not resolved here. Existing Lithia Springs and Coweta proposal are separate campuses. DRI filing/review is not construction approval or current operation. Not all fields, current operation, precise parcel or critical IT independently certified.",
      "date": "",
      "events": [],
      "timeline": [],
      "opened": "",
      "tier": "",
      "sources": [
        {
          "url": "https://www.bisnow.com/atlanta/news/data-center/t5-plotting-data-center-campus-in-fairburn-124663",
          "host": "bisnow.com",
          "date": "",
          "published": "",
          "checked": "2026-10-15",
          "date_kind": "publication date not established",
          "label": "Reviewed source"
        },
        {
          "url": "https://t5datacenters.com/locations/t5-atlanta-iv/",
          "host": "t5datacenters.com",
          "published": "",
          "date": "",
          "checked": "2026-10-17",
          "label": "Access-check target"
        },
        {
          "url": "https://t5datacenters.com/locations/",
          "host": "t5datacenters.com",
          "published": "",
          "date": "",
          "checked": "2026-10-17",
          "label": "Reviewed source context"
        }
      ],
      "loc": {
        "lat": 33.81838,
        "lng": -84.47496,
        "precision": "county",
        "basis": "Shown at county level only. The dot is placed inside the county for the map and is not the site, its address or a parcel."
      },
      "reviewed_evidence": [
        {
          "overlay": "national-permit-scope-operator-crosswalks-and-work-resumption-round82-2026-10-15.json",
          "scope": "Named-site context, with limited previews/corridor crosswalks explicitly identified.",
          "fields": {},
          "notes": [
            "Jarred Schenke, Bisnow June 12, 2024 original Fairburn planning-director interview: early T5 proposal near I-85/Gullatt, 495,000 square feet/two buildings, land not yet owned and use permit still needed. Limited corridor crosswalk to inherited Atlanta IV/Palmetto row; exact parcel/city-boundary discrepancy and later 200/300 MW claims not resolved here. Existing Lithia Springs and Coweta proposal are separate campuses. DRI filing/review is not construction approval or current operation.",
            "Not all fields, current operation, precise parcel or critical IT independently certified."
          ],
          "sources": [
            {
              "url": "https://www.bisnow.com/atlanta/news/data-center/t5-plotting-data-center-campus-in-fairburn-124663",
              "host": "bisnow.com",
              "date": "",
              "published": "",
              "checked": "2026-10-15",
              "date_kind": "publication date not established",
              "label": "Reviewed source"
            }
          ],
          "whole_record_certified": false
        },
        {
          "overlay": "encore-2026-10-17-batch2",
          "scope": "Limited source identity and stage review; not whole-record certification, parcel verification or a physical-site census.",
          "fields": {},
          "notes": [
            "The old Atlanta IV URL is unavailable, and the current T5 locations page yielded a category shell without named campus content in the ordinary browser view. Search-index wording is not current captured evidence. No closure is inferred. This attempt receives no freshness credit or stage change."
          ],
          "sources": [
            {
              "url": "https://t5datacenters.com/locations/t5-atlanta-iv/",
              "host": "t5datacenters.com",
              "published": "",
              "date": "",
              "checked": "2026-10-17",
              "label": "Access-check target"
            },
            {
              "url": "https://t5datacenters.com/locations/",
              "host": "t5datacenters.com",
              "published": "",
              "date": "",
              "checked": "2026-10-17",
              "label": "Reviewed source context"
            }
          ],
          "checked": "2026-10-17",
          "whole_record_certified": false
        }
      ],
      "manual_source_reviewed": true,
      "whole_record_certified": false,
      "field_evidence_present": false,
      "inventory_label_retained": true,
      "precision_label": "Exact site not published; shown at county level",
      "summary": "Palmetto · Fulton · Source context reviewed",
      "location_display": {
        "policy": "reviewed-map-references-2026-10-23",
        "decision": "withheld_unreviewed_point",
        "scope": "The available point evidence does not establish a supported site location. No site pin, nearby distance or aerial destination is published. The original coordinate and its provenance remain in research history.",
        "county_display": "13121"
      }
    }
  ],
  "compilation_license": "withheld_pending_owner_decision"
}