  "schema_version": 1,
  "source_compilation_context": {
    "va": {
      "attribution": {
        "inventory": {
          "name": "Compute Atlas",
          "creator": "Edward Kubiak",
          "url": "https://www.compute-atlas.com/api",
          "license": "CC BY 4.0",
          "license_url": "https://creativecommons.org/licenses/by/4.0/",
          "snapshot_url": "https://www.compute-atlas.com/api/facilities",
          "retrieved": "2026-10-14",
          "sha256": "79ad432dab7c128e428234c9d0dd40933114b415a4a5d697db00095637d50f37",
          "changes": "Added provenance, publication-date distinctions, display-safe wording, quarantine flags and state partitioning. Original source records retained locally."
        },
        "counties": "U.S. Census Bureau county boundaries (public domain)",
        "research": "Field-specific source context. See the linked source and limits on each record."
      },
      "source_data_url": "https://datacentersatlas.com/data/va.json",
      "updated": "2026-10-25"
    }
  },
  "scope": "Retained county context, which can be broad or unresolved. No parcel or municipal jurisdiction is inferred. Research records retain their sources, dates and location limits. Counts are not a census of operating buildings. Company name links alone do not establish ownership or operation.",
  "collection": {
    "kind": "counties",
    "key": "51047",
    "label": "Culpeper County, Virginia"
  },
  "records": [
    {
      "id": "culpeper-brandy-station-va",
      "state": "va",
      "kind": "facility",
      "name": "Culpeper Acquisitions Brandy Station Campus",
      "group": "unknown",
      "status": "Status unclear",
      "raw_status": "",
      "status_field": "",
      "crypto": false,
      "type": "Data center (inventory classification)",
      "counties": [
        "Culpeper"
      ],
      "city": "Brandy Station",
      "address": "",
      "who": "",
      "end_user": "",
      "mw": null,
      "power": "",
      "power_note": "",
      "investment": "",
      "jobs": "",
      "acres": null,
      "utility": "",
      "water": "",
      "incentives": "",
      "note": "Manual source context is available for this inherited inventory record. The inventory label and approximate geography are retained for discovery. This is not certification of current operation, ownership, a separate physical building, technical capacity or a precise parcel. Missing fields remain unknown. Named content personally reviewed; no whole-record certification. Dates and forecasts remain source-specific.. Advocacy700MWto1.8GWrange is prospective estimate with undefined power basis; no current capacity. Hearing notices not outcomes; draft illustrative layout not approved site plan. Subsequent original decisions and current operator disclosures take precedence. Fields can apply to shared campus, regional or historical context; consult source review before assigning to a building.",
      "date": "",
      "events": [],
      "timeline": [],
      "opened": "",
      "tier": "",
      "sources": [
        {
          "url": "https://www.pecva.org/region/culpeper/new-data-center-proposals-in-brandy-station-and-near-the-town-of-culpeper/",
          "host": "pecva.org",
          "date": "2024-05-30",
          "published": "2024-05-30",
          "checked": "2026-10-14",
          "date_kind": "publication",
          "label": "Reviewed source"
        }
      ],
      "loc": {
        "lat": 38.48581,
        "lng": -77.95555,
        "precision": "county",
        "basis": "Shown at county level only. The dot is placed inside the county for the map and is not the site, its address or a parcel."
      },
      "reviewed_evidence": [
        {
          "overlay": "regional-development-review-round24-2026-10-14.json",
          "scope": "Named content personally reviewed; no whole-record certification. Dates and forecasts remain source-specific.",
          "fields": {
            "reported_context": "PEC opposition letter distinguishes Brandy Station XXTech Park request from separate Keyser Farm proposal and earlier withdrawn AttoTek.",
            "independently_verified_current_operating_status": null
          },
          "notes": [
            "Advocacy700MWto1.8GWrange is prospective estimate with undefined power basis; no current capacity. Hearing notices not outcomes; draft illustrative layout not approved site plan.",
            "Subsequent original decisions and current operator disclosures take precedence.",
            "Fields can apply to shared campus, regional or historical context; consult source review before assigning to a building."
          ],
          "sources": [
            {
              "url": "https://www.pecva.org/region/culpeper/new-data-center-proposals-in-brandy-station-and-near-the-town-of-culpeper/",
              "host": "pecva.org",
              "date": "2024-05-30",
              "published": "2024-05-30",
              "checked": "2026-10-14",
              "date_kind": "publication",
              "label": "Reviewed source"
            }
          ],
          "whole_record_certified": false
        },
        {
          "overlay": "orchestra-F1-label-review-2026-10-20",
          "scope": "The Piedmont Environmental Council's May 2024 advocacy letter requests denial of the XX Tech Park proposal. A request to deny is not a recorded government denial. Keyser Farm and the earlier AttoTek proposal remain separate; no current application outcome or physical stage is adopted.",
          "fields": {
            "identity_label_context": {
              "previous_name": "Culpeper Acquisitions Brandy Station Campus (denied)",
              "plain_name": "Culpeper Acquisitions Brandy Station Campus",
              "interpretation": "The Piedmont Environmental Council's May 2024 advocacy letter requests denial of the XX Tech Park proposal. A request to deny is not a recorded government denial. Keyser Farm and the earlier AttoTek proposal remain separate; no current application outcome or physical stage is adopted.",
              "outcome_wording_is_not_identity": true
            }
          },
          "notes": [
            "The Piedmont Environmental Council's May 2024 advocacy letter requests denial of the XX Tech Park proposal. A request to deny is not a recorded government denial. Keyser Farm and the earlier AttoTek proposal remain separate; no current application outcome or physical stage is adopted.",
            "Inherited inventory name: Culpeper Acquisitions Brandy Station Campus (denied). The wording is retained as provenance, not as an independently verified outcome.",
            "An application decision is separate from a current physical stage. No coordinate, address, parcel, company role, technical figure or physical milestone date is changed."
          ],
          "sources": [
            {
              "url": "https://www.pecva.org/region/culpeper/new-data-center-proposals-in-brandy-station-and-near-the-town-of-culpeper/",
              "host": "www.pecva.org",
              "published": "2024-05-30",
              "date": "2024-05-30",
              "checked": "2026-10-20",
              "label": "Piedmont Environmental Council"
            }
          ],
          "checked": "2026-10-20",
          "whole_record_certified": false
        }
      ],
      "manual_source_reviewed": true,
      "whole_record_certified": false,
      "field_evidence_present": true,
      "inventory_label_retained": true,
      "precision_label": "Exact site not published; shown at county level",
      "summary": "Brandy Station · Culpeper · Source context reviewed",
      "location_display": {
        "policy": "reviewed-map-references-2026-10-23",
        "decision": "withheld_unreviewed_point",
        "scope": "The available point evidence does not establish a supported site location. No site pin, nearby distance or aerial destination is published. The original coordinate and its provenance remain in research history.",
        "county_display": "51047"
      }
    },
    {
      "id": "edgecore-culpeper-tech-zone-va",
      "state": "va",
      "kind": "project",
      "name": "EdgeCore Culpeper Data Center Campus",
      "group": "proposed",
      "status": "Operator-listed plan",
      "raw_status": "proposed",
      "status_field": "current_status",
      "crypto": false,
      "type": "Hyperscale data center campus",
      "counties": [
        "Culpeper"
      ],
      "city": "Culpeper",
      "address": "",
      "who": "EdgeCore Digital Infrastructure",
      "end_user": "",
      "mw": null,
      "power": "",
      "power_note": "Current initial two-building forecast with mid-2029 capacity target. Historical initial 216/potential 432 MW plans overlap and are not added. Technical as-of date is not published. No utility, backup-generation or metered-use figure is inferred.",
      "investment": "",
      "jobs": "",
      "acres": null,
      "utility": "",
      "water": "",
      "incentives": "",
      "note": "Manual source context is available for this inherited inventory record. The inventory label and approximate geography are retained for discovery. This is not certification of current operation, ownership, a separate physical building, technical capacity or a precise parcel. Missing fields remain unknown. Personally read named-source context; historical/proposed figures stay attributed. No whole-record certification.. Initial capacity is inside the ultimate plan. Early 2028 power delivery remains a forecast. The water-efficiency benchmark is not measured consumption, and the wider technology zone is not the owned campus. Current original approvals, disclosures and later outcomes take precedence. Fields can apply to shared campus, regional or historical context; consult source review before assigning to a building.",
      "date": "",
      "events": [
        [
          "2024-07-18",
          "EdgeCore announced its Culpeper land purchase and then-current initial 216/potential 432 MW plan. Early 2028 power delivery was a forecast; the current page advertises a different 196 MW plan and mid-2029 capacity target."
        ]
      ],
      "timeline": [],
      "opened": "",
      "tier": "",
      "sources": [
        {
          "url": "https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia",
          "host": "edgecore.com",
          "date": "2024-07-18",
          "published": "2024-07-18",
          "checked": "2026-10-14",
          "date_kind": "publication",
          "label": "Reviewed source"
        },
        {
          "url": "https://edgecore.com/locations/culpeper-data-centers",
          "host": "edgecore.com",
          "published": "",
          "date": "",
          "checked": "2026-10-16",
          "label": "Reviewed operator campus page"
        }
      ],
      "loc": {
        "lat": 38.4989,
        "lng": -77.96984,
        "precision": "county",
        "basis": "Shown at county level only. The dot is placed inside the county for the map and is not the site, its address or a parcel."
      },
      "reviewed_evidence": [
        {
          "overlay": "regional-development-review-round26-2026-10-14.json",
          "scope": "Personally read named-source context; historical/proposed figures stay attributed. No whole-record certification.",
          "fields": {
            "reported_context": "EdgeCore announces a 120-acre Culpeper purchase, initially 216 MW of critical IT and potential expansion to 432 MW.",
            "independently_verified_current_operating_status": null,
            "planned_initial_critical_it_mw": 216,
            "potential_critical_it_mw": 432,
            "planned_initial_power_delivery": "early 2028"
          },
          "notes": [
            "Initial capacity is inside the ultimate plan. Early 2028 power delivery remains a forecast. The water-efficiency benchmark is not measured consumption, and the wider technology zone is not the owned campus.",
            "Current original approvals, disclosures and later outcomes take precedence.",
            "Fields can apply to shared campus, regional or historical context; consult source review before assigning to a building."
          ],
          "sources": [
            {
              "url": "https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia",
              "host": "edgecore.com",
              "date": "2024-07-18",
              "published": "2024-07-18",
              "checked": "2026-10-14",
              "date_kind": "publication",
              "label": "Reviewed source"
            }
          ],
          "whole_record_certified": false
        },
        {
          "overlay": "edgecore-depth-2026-10-16",
          "scope": "Selected operator campus/phase and technical-envelope review; no whole-state refresh, exact location, legal ownership or physical-site count certification.",
          "fields": {
            "market_identity": "EdgeCore Culpeper remains distinct from DataBank Culpeper, Brandy Station and the wider Technology Zone. A shared county or zone is not a same-site identity.",
            "current_initial_plan": {
              "critical_it_mw": 196,
              "building_count_claim": 2,
              "gross_square_feet_claim": 920000,
              "acres_claim": 93,
              "capacity_availability_target": "mid-2029"
            },
            "historical_2024_plan": {
              "announcement_date": "2024-07-18",
              "initial_it_mw": 216,
              "potential_it_mw": 432,
              "gross_square_feet_claim": 1400000,
              "purchased_acres_claim": 120,
              "initial_power_delivery_target": "early 2028"
            },
            "plan_revision_scope": "The current page differs from the 2024 initial/expansion plan and power target. No dated redesign, disposal of land, canceled buildings or accomplished power delivery is established. Historical and current envelopes overlap and are not added.",
            "water_scope": "Below .01 L/kWh is a design WUE rating; no measured use, full-year consumption or independently established operating period is claimed.",
            "identity_review_scope": "Existing named campus matched by brand and published locality/context only. No precise address, title, physical-site census or point correction is adopted."
          },
          "notes": [
            "Campus figures overlap with their components and older plans. Do not sum them or call them available, energized, approved or metered power.",
            "Published/review dates and forecasts are not accomplished construction or opening dates. Existing coordinates and location precision remain unverified and unchanged."
          ],
          "sources": [
            {
              "url": "https://edgecore.com/locations/culpeper-data-centers",
              "host": "edgecore.com",
              "published": "",
              "date": "",
              "checked": "2026-10-16",
              "label": "Reviewed operator campus page"
            },
            {
              "url": "https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia",
              "host": "edgecore.com",
              "published": "2024-07-18",
              "date": "2024-07-18",
              "checked": "2026-10-16",
              "label": "Dated operator announcement"
            }
          ],
          "checked": "2026-10-16",
          "whole_record_certified": false
        },
        {
          "overlay": "Company role source check 20, October 23, 2026",
          "scope": "EdgeCore Digital Infrastructure explicitly describes this named campus or component on its own website. The attributed provider brand relationship is not a finding of the legal operator or owner, independent safety verification, surveyed title or completed construction. No status, location, address, physical milestone, quantity, water use, air permit, measured harm, incentive or tenant identity is promoted. The page explicitly says EdgeCore is developing this campus in the Culpeper Technology Zone. The larger Technology Zone is not the project parcel. Initial availability beginning in mid 2029 is a future company target, not an opening event or inferred exact date.",
          "fields": {
            "company_association": {
              "name": "EdgeCore Digital Infrastructure",
              "role": "developer",
              "identity_scope": "provider_brand_only",
              "scope": "EdgeCore Digital Infrastructure explicitly describes this named campus or component on its own website. The attributed provider brand relationship is not a finding of the legal operator or owner, independent safety verification, surveyed title or completed construction. No status, location, address, physical milestone, quantity, water use, air permit, measured harm, incentive or tenant identity is promoted. The page explicitly says EdgeCore is developing this campus in the Culpeper Technology Zone. The larger Technology Zone is not the project parcel. Initial availability beginning in mid 2029 is a future company target, not an opening event or inferred exact date."
            },
            "provider_role": "developer"
          },
          "notes": [
            "EdgeCore Digital Infrastructure explicitly describes this named campus or component on its own website. The attributed provider brand relationship is not a finding of the legal operator or owner, independent safety verification, surveyed title or completed construction. No status, location, address, physical milestone, quantity, water use, air permit, measured harm, incentive or tenant identity is promoted. The page explicitly says EdgeCore is developing this campus in the Culpeper Technology Zone. The larger Technology Zone is not the project parcel. Initial availability beginning in mid 2029 is a future company target, not an opening event or inferred exact date.",
            "First publication dates are not established. Current retrieval and advertised build out are not physical milestones."
          ],
          "sources": [
            {
              "url": "https://edgecore.com/locations/culpeper-data-centers",
              "host": "edgecore.com",
              "published": "",
              "date": "",
              "checked": "2026-10-23",
              "label": "First party explicitly named campus, scoped provider relationship reviewed"
            }
          ],
          "checked": "2026-10-23",
          "whole_record_certified": false
        }
      ],
      "manual_source_reviewed": true,
      "whole_record_certified": false,
      "field_evidence_present": true,
      "inventory_label_retained": true,
      "precision_label": "Exact site not published; shown at county level",
      "summary": "Culpeper · Culpeper · Source context reviewed",
      "status_scope": "Current operator describes an initial two-building development with capacity availability beginning mid-2029. This is an operator-listed plan, not verified zoning, air or building approval, construction, current service or delivered capacity. Exact technical revision and construction/opening dates are unknown.",
      "event_evidence": [
        {
          "date": "2024-07-18",
          "text": "EdgeCore announced its Culpeper land purchase and then-current initial 216/potential 432 MW plan. Early 2028 power delivery was a forecast; the current page advertises a different 196 MW plan and mid-2029 capacity target.",
          "kind": "announced",
          "sources": [
            {
              "url": "https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia",
              "host": "edgecore.com",
              "published": "2024-07-18",
              "date": "2024-07-18",
              "checked": "2026-10-16",
              "label": "Dated operator announcement"
            }
          ]
        }
      ],
      "typed_power_facts": [
        {
          "measure": "it_capacity",
          "value": 196,
          "unit": "MW",
          "as_of": null,
          "basis": "forecast",
          "scope": "Current initial two-building forecast with mid-2029 capacity target. Historical initial 216/potential 432 MW plans overlap and are not added.",
          "observed_on": "2026-10-16",
          "as_of_basis": "not_published",
          "sources": [
            "https://edgecore.com/locations/culpeper-data-centers"
          ]
        }
      ],
      "location_display": {
        "policy": "reviewed-map-references-2026-10-23",
        "decision": "withheld_unreviewed_point",
        "scope": "The available point evidence does not establish a supported site location. No site pin, nearby distance or aerial destination is published. The original coordinate and its provenance remain in research history.",
        "county_display": "51047"
      }
    }
  ],
  "compilation_license": "withheld_pending_owner_decision"
}