Rules and source checks.
The county review below is separate from site-specific conditions and municipal or township zoning. It does not establish parcel permission or current compliance.
Washington County
Policy context found · Checked October 17, 2026.
The county Community Development Code assessment identifies data-center concerns among the issues raised. The published assessment and priorities process provides recommendations, rather than automatically enacting code amendments.
This checked project page does not establish an adopted data-center restriction. County code applies in its jurisdiction; Hillsboro, Beaverton and other municipal laws are separate. The complete code and later ordinance actions were not exhaustively reviewed.
Official source 1
Power and water.
Each figure keeps its measure, basis, date and sources. Forecasts, utility requests, generation and IT capacity are different. These figures are not added into a county total.
No separately typed power or water fact is retained for this county cohort yet. That means unknown, not zero use.
The dated record.
The retained event log distinguishes announcements, scheduled dates and status-source checks. A review date is not an opening day. A target never becomes a completed event merely because time passes.
View 2 status source checks
Status source checks.
- Digital Realty PDX12
Digital Realty currently markets colocation and connectivity services under PDX12. This supports an operating service component in the existing research context, not complete campus delivery, full-building operation, legal ownership, present vacancy or a commissioned IT-load figure.
- Digital Realty PDX10
Digital Realty currently markets colocation and connectivity services under PDX10. This supports an operating service component in the existing research context, not complete campus delivery, full-building operation, legal ownership, present vacancy or a commissioned IT-load figure.