Rules and source checks.
The county review below is separate from site-specific conditions and municipal or township zoning. It does not establish parcel permission or current compliance.
Maricopa County
Policy context found · Checked October 17, 2026.
The county reports adoption of its zoning update on December 10, 2025, effective January 9, 2026. The retained ordinance expressly defines data centers and separately lists data centers with compensatory power generation.
The checked current ordinance is distinct from earlier drafts. District/use-table cells were not adopted here as parcel-specific permissions. Unincorporated county rules are separate from Phoenix, Mesa, Chandler and other municipal codes; no facility approval or compliance is inferred.
Official source 1 · Official source 2 · Official source 3
The dated record.
The retained event log distinguishes announcements, scheduled dates and status-source checks. A review date is not an opening day. A target never becomes a completed event merely because time passes.
Recorded events and announcements.
- EdgeCore Mesa Data Center Campus
EdgeCore announced $235 million ABS financing backed by stabilized, leased PH01 (26 MW reported IT). This is a financing announcement, not a physical opening day, expenditure or incentive.
- Google Redhawk Mesa Data Center Campus
Google announced an Arizona grid-energy agreement and described planned Mesa air cooling. The announcement is not a proved opening day or 430 MW of site IT capacity.
View 5 status source checks
Status source checks.
- Meta Mesa Data Center
Primary source review checked October 16, 2026. The current named Meta factsheet explicitly states on page 2 that Mesa went online in 2025. The year is not converted into an exact opening day. Current delivered capacity, occupied share and completion of all expansion buildings remain unverified; future employment and restoration targets are not actual headcounts or measured offsets.
- Google Redhawk Mesa Data Center Campus
An operating component at the named Mesa campus is supported by Google's 2026 Q2 PUE and annual 2025 operational water reporting, alongside its named first Mesa campus announcement. No opening day, exact parcel, full campus completion, present IT load or present water rate is established.
- EdgeCore Mesa Data Center Campus
Current operator describes operating its Mesa data centers; the July 24, 2025 release identifies stabilized, leased PH01. This supports an operating phase only. Delivery, occupancy and energized share of all five marketed buildings and the 496 MW envelope are not established.
- Digital Realty PHX15
Digital Realty currently markets colocation and connectivity services under PHX15. This supports an operating service component in the existing research context, not complete campus delivery, full-building operation, legal ownership, present vacancy or a commissioned IT-load figure.
- QTS Phoenix 4
Named-site current agency/operator stage, reviewed October 15, 2026