Data CentersAtlas
Weekly brief · United States

What changed in data centers this week.

Atlas research for the week of October 26, 2026, through October 29, 2026. Source review dates and physical events keep their separate meanings.

Complete dated evidence for this brief · All weekly briefs · All upcoming notices · RSS

0research label reviews
10records added to Atlas
37scheduled dates ahead
0concern record checks

Counts describe this research collection. A label review is not a physical transition, an added record is not a new building, and a scheduled date does not establish that an event happened. Method and source rules.

Added to the research collection.

  1. WVNET Morgantown Data Center. Identity review recorded October 26, 2026.

    wvnet.edu wvnet.edu wvnet.edu www.wvhepc.edu morgantownwv.gov

  2. Oregon State Data Center Salem. Identity review recorded October 26, 2026.

    osuosl.org www.oregon.gov cio.oregonstate.edu oregonbuys.gov

  3. Oregon State Kerr Corvallis Data Center. Identity review recorded October 26, 2026.

    osuosl.org facilities.oregonstate.edu cio.oregonstate.edu www.corvallisoregon.gov

  4. Arkansas State Data Center West. Identity review recorded October 26, 2026.

    webftp.blr.arkansas.gov arkleg.state.ar.us adeq.state.ar.us

  5. Arkansas State Data Center MAC. Identity review recorded October 26, 2026.

    sas.arkansas.gov arkleg.state.ar.us adeq.state.ar.us

  6. South Carolina State Data Center Columbia. Identity review recorded October 26, 2026.

    apps.sceis.sc.gov sck12techinit.sc.gov geocoding.geo.census.gov

  7. Colorado State Scott Bioengineering Data Center. Identity review recorded October 26, 2026.

    www.research.colostate.edu www.usengineering.com admissions.colostate.edu www.larimer.gov

  8. Missouri State University Telecommunications Center Data Center. Identity review recorded October 26, 2026.

    design.missouristate.edu ntg.missouristate.edu map.missouristate.edu geocoding.geo.census.gov

  9. Riverbend Technology Center at Former Alton Steel. Identity review recorded October 26, 2026.

    cityofaltonil.gov www.riverbendalton.com www.cityofaltonil.gov

  10. University of Connecticut Gant Data Center. Identity review recorded October 26, 2026.

    updc.media.uconn.edu scheduling.uconn.edu portal.ct.gov its.uconn.edu geocoding.geo.census.gov portal.ct.gov tigerweb.geo.census.gov

Scheduled dates ahead.

  1. CPUC Resolution E5455 further consideration. Scheduled October 29, 2026.

    The revised October 8 Commission voting results mark Resolution E5455 held to October 29 for further review. This is a scheduled reconsideration reference, not a verified final vote or an approval. The selected result table does not identify a particular project, later agenda placement, future clock or venue.

    ia.cpuc.ca.gov

  2. Board informational report on unsolicited Global Stack outreach. Scheduled October 29, 2026 at 12:30 local time as published.

    The current 19th DAA agenda sets a 12:30 PM Board meeting and lists Global Stack USA under the CEO informational report regarding unsolicited outreach. This is the meeting start, not an exact item time or a development approval vote. An informational entry does not establish an accepted project proposal, signed agreement, planned construction or computing operation.

    earlwarren.com static1.squarespace.com

  3. Monarch Cloud Campus virtual air permit participation meeting. Scheduled October 29, 2026 at 18:00 local time as published.

    The agency notice schedules the virtual receipt of oral comments on the proposed off grid generation permit for Monarch Cloud Campus. Registration is required by 4 PM on the hearing day through the official notice. The private participation link is issued after registration. This is a permit participation event, not final authorization, measured emissions or computing operation.

    dep.wv.gov

  4. Northampton joint hearing on proposed data center moratorium. Scheduled October 29, 2026 at 19:00 local time as published.

    Joint Planning Board and Legislative Matters Committee hearing on proposed ordinance26.125. Proposed365day moratorium and definition are not adopted law. Today scheduled hearing has no verified outcome.

    northamptonma.gov northamptonma.gov

  5. PUCN scheduled resource plan hearing continuation October 29. Scheduled October 29, 2026.

    The original Commission calendar expressly lists this additional hearing day for docket 26 05007. Its separate event detail leaves the Time field blank. The October 26 start clock is not transferred; a scheduled continuation does not establish that testimony was heard or a decision reached.

    pucweb1.state.nv.us

  6. San Antonio Council vote on data center zoning proposals. Scheduled October 29, 2026.

    The City release dated October 15 says two proposed Unified Development Code amendments related to data center development are scheduled for a final City Council vote on October 29. It does not give the meeting clock or venue and does not report a result.

    www.sa.gov

  7. Michigan public input deadline on a proposed federal data center framework. Scheduled October 30, 2026.

    The October 1 original congressional release says comments on the proposed data center framework will be accepted through October 30, 2026. It does not supply a closing clock. This is a congressional office public input opportunity, not an introduced bill, committee hearing, vote, binding rule or a submitted response by this research.

    debbiedingell.house.gov

  8. Monarch Cloud Campus air permit written comment deadline. Scheduled October 30, 2026 at 17:00 local time as published.

    The agency notice says written air permit comments must be received before 5 PM on October 30. This is a receipt deadline for the named air proceeding, not the separate state waters proceedings, a completed public response process or final permit. No comment is submitted by this research.

    dep.wv.gov

  9. Comments due on Morrisville to Wishing Star transmission application. Scheduled October 30, 2026.

    The June 29 ruling moves the comment deadline to October 30 in case PUR 2026 00021. The proceeding covers transmission facilities in Fauquier, Prince William and Loudoun counties. No decision or construction outcome is established.

    www.scc.virginia.gov

  10. Boyertown hearing on proposed joint zoning amendments. Scheduled November 2, 2026 at 19:00 local time as published.

    Borough notice schedules a hearing followed by consideration of enactment. The data center use provision concerns special exception use within Colebrookdale Township GI/Q zoning only; separate Boyertown map and other use amendments do not establish Borough data center permission. No adoption or individual project approval inferred.

    www.boyertownborough.org www.boyertownborough.org www.boyertownborough.org

  11. Board consideration of proposed zoning Ordinance 01 2026. Scheduled November 2, 2026 at 18:00 local time as published.

    The notice states an intention to consider and enact the ordinance at the regular monthly meeting beginning at 6 PM, after the 5:30 PM hearing. The clock is the meeting start, not an exact item voting time. Its conditional five days after enactment clause supplies no accomplished effective date.

    www.cherrytreetwp.com www.cherrytreetwp.com

  12. Board hearing on the zoning update and data center curative amendment. Scheduled November 2, 2026 at 17:30 local time as published.

    The original Township notices set a public hearing at 5:30 PM before the separate 6 PM regular meeting. The subject is proposed Ordinance 01 2026, a comprehensive zoning update and curative amendment to provide for data centers. No adoption or individual site approval has occurred in this calendar record.

    www.cherrytreetwp.com www.cherrytreetwp.com www.cherrytreetwp.com

  13. Colebrookdale meeting on joint zoning amendments and data center use. Scheduled November 2, 2026 at 19:30 local time as published.

    Township notice announces a public hearing and consideration of enactment during its November 2 regular meeting. Data center use is proposed by special exception in the Township GI/Q district. The clock belongs to the regular meeting and is not a separately verified hearing opening time. No enactment, Pike hearing day or individual project approval inferred.

    colebrookdale.org www.boyertownborough.org

  14. DeepGreen Cook Inlet preliminary permit comment and competing filing deadline. Scheduled November 2, 2026 at 17:00 local time as published.

    The Federal Register notice for Project 15423 000 sets the deadline for comments, intervention motions, competing applications and notices of intent at 5 PM Eastern Time November 2. The preliminary permit process concerns study priority and does not authorize land disturbance, construction or operation.

    www.govinfo.gov

  15. FERC comments on DeepGreen Cook Inlet preliminary permit request. Scheduled November 2, 2026 at 17:00 local time as published.

    FERC project P15423 concerns a preliminary permit application to study a proposed Cook Inlet tidal power and subsea computing hub. The notice expressly sets November 2 at 5 PM Eastern for comments, intervention motions and competing application filings. A preliminary permit would provide licensing priority and would not authorize construction or establish computing operation.

    www.govinfo.gov

  16. Deer Park Planning and Zoning discussion of data center zoning. Scheduled November 2, 2026 at 18:30 local time as published.

    The Commission agenda lists proposed data center zoning and consideration of confirming a December 1 joint hearing date. Its recommended action says discussion only. The November 2 meeting is scheduled; the December hearing is not treated as confirmed and no zoning adoption or project approval is established.

    legistar1.granicus.com

  17. Grantsville written comments close on proposed data infrastructure conditional use. Scheduled November 2, 2026 at 12:00 local time as published.

    Proposed amendments to Chapters2,8and16 would establish Advanced Technology and Data Infrastructure Center as a conditional use in MG and MG EX districts. Written comment cutoff and hearing are separate. Hearing considers recommendation to Council, not adoption or individual permit approval. Portal21:00 is meeting end, not an exact hearing closing clock.

    www.utah.gov www.utah.gov

  18. Countywide Data Center Policy Working Group meeting. Scheduled November 2, 2026 at 12:30 -05:00.

    The County lists a Countywide Data Center Policy Working Group meeting and invites public participation. Its agenda link leads to the Forward Pinellas document portal, where no agenda attachment was qualified. No specific vote, adopted policy or project permission is established.

    pinellas.gov

  19. Municipal vote on Question 1 concerning specified Eldorado Valley land use. Scheduled November 3, 2026.

    The current City ballot page explicitly places Question 1 in the November 3 Municipal General Election. It asks whether data center facilities should be an approved use within the Eldorado Valley Transfer Area outside the habitat easement. The official explanation distinguishes permission to consider leases from approval of an individual project. No result, polling clock, site lease or City wide data center authorization is inferred.

    www.bcnv.org www.bcnv.org

  20. Deer Park Council workshop on data center zoning. Scheduled November 3, 2026 at 19:00 local time as published.

    The Council workshop lists discussion of changes to zoning for data centers. Action text says discussion only in Workshop. The clock is the workshop start; no ordinance adoption or project authorization is established.

    webapi.legistar.com webapi.legistar.com

17 further entries are in the complete source file.

Moratorium and restriction source reviews.

  1. Moratorium record: action recorded instrument unverified. Sources checked October 26, 2026.

    Official City meeting recap records October20 second reading approval for Ordinance21,Series2026, described as an eighteen month moratorium on acceptance, processing and approval of land use applications or building permits for development or construction of data centers and related land uses.

    The consent agenda containing this item was approved six to zero. This is an official action summary, not the signed ordinance or complete legal text. Effective date, exact termination, definitions, exceptions, later amendments and present legal effect remain unverified. No individual project cancellation or operating status is set.

    www.lafayetteco.gov

  2. Moratorium record: proposed. Sources checked October 26, 2026.

    County agenda proposes a pause on submission and acceptance of new applications for large scale data centers in unincorporated Martin County. The described definition uses a single location with anticipated monthly peak load of at least 50 megawatts, with colocated customers included and different locations not aggregated.

    The agenda recommends adoption at the second hearing, not an accomplished vote. Already complete applications would continue under prior regulations according to the proposal. A prior procedural vote changes hearing timing only. The linked ordinance attachment returned HTTP 410, so full text, exceptions, term, adoption and legal effective day remain unverified. No project status is set.

    martin.legistar.com

  3. Moratorium record: action recorded instrument unverified. Sources checked October 26, 2026.

    August12 minutes record adoption action for Resolution08-12-26-1. The unsigned hosted text would restrict data center construction, installation, replacement and enlargement across the Township, with exclusions for accessory server rooms, ordinary business IT and separately regulated telecommunications facilities, and an exemption for centers existing before adoption.

    Officially hosted text leaves adoption and signature blanks. It states one year with possible earlier Board termination and effectiveness upon adoption, but the executed instrument and later amendments remain unverified. No exact legal expiry or current effect certified. Supporting infrastructure is covered only when principally serving the defined computing use.

    www.avontownshipmn.gov www.avontownshipmn.gov www.avontownshipmn.gov

  4. Ban record: proposed. Sources checked October 26, 2026.

    Draft local law would prohibit data centers, artificial intelligence computing facilities and their supporting uses under the Town zoning code.

    Five page filing form leaves law number and adoption certifications blank. Health care internal computing has a qualified definition exclusion. Supporting infrastructure prohibition is tied to the covered facilities, not every substation or battery. Filing with the Secretary of State is the draft effective condition; no actual filing, adoption or present effect established.

    southbristolny.gov

  5. Moratorium record: proposed. Sources checked October 26, 2026.

    City recap records first reading approval following the third public hearing for a proposed ninety day pause on acceptance, processing and approval of data center applications in the City and its extraterritorial jurisdiction.

    The recap explicitly says this action did not put the pause into effect. Final reading is scheduled November4 and would require three fourths approval. November5 commencement and February3,2027 termination are conditional and are not stored as effective dates. A possible additional ninety days is not an adopted extension.

    www.brownsvilletx.gov

  6. Moratorium record: extended. Sources checked October 28, 2026.

    Council action history records approval of the extension ordinance October 26. The ordinance becomes effective upon adoption, while the extended application pause commences November 6, 2026 and ends no later than October 18, 2027, or upon approval of specified new rules or policies, whichever occurs first. Covered actions are acceptance, processing and approval of new telecommunications and data storage applications within Charlotte and its extraterritorial jurisdiction.

    The posted attachment has an October 26 adoption clause but no executed signature block. The item header still says Agenda Ready; the separate action history records Approve and Pass. Internal support facilities meeting the stated conditions and projects exempt under state law are excluded. No individual exemption, physical shutdown, project cancellation or site stage is determined.

    charlottenc.legistar.com charlottenc.legistar.com

  7. Moratorium record: proposed. Sources checked October 28, 2026.

    Town notice proposes a one year restriction covering computing facility development review, approvals and specified construction or alteration activity within Town of Tyre. Town Board hearing is scheduled October28 at18:30.

    This is a hearing notice summarizing a proposed law, not a signed or adopted instrument. No individual project eligibility, accomplished hearing or current restriction is established.

    tyreny.gov

  8. Moratorium record: proposed. Sources checked October 28, 2026.

    Draft would pause data center commercial development within City municipal boundaries, City CCNs and the Denton Municipal Electric Certificated Service Area, with a stated Chapter 245 exception. Staff schedules December 1 Council consideration of enactment.

    The retained instrument is an unsigned proposal with blank adoption and vote fields. Draft work plan target dates are not accomplished legal dates. Separate development code amendments do not establish moratorium enactment. Exact mapped coverage, individual project eligibility and present operation remain unverified.

    denton-tx.legistar.com denton-tx.legistar.com

  9. Ban record: proposed. Sources checked October 28, 2026.

    Draft permits data centers only in the M1 Industrial Park district with a Specific Use Permit and prohibits them in other zoning districts. It would cover principal and supporting facilities, restrict cooling water sources, require data center funded substations and prevent separate accessory classifications from avoiding the use permit.

    This is a partial zoning prohibition with an M1 permitting exception, not a City wide ban. Draft text is not law in effect. A separate unsigned ordinance proposes calling a December1 joint hearing; blank adoption, vote and signature fields do not establish that call. Individual property eligibility and existing project rights remain unverified.

    legistar1.granicus.com legistar1.granicus.com legistar1.granicus.com legistar1.granicus.com

  10. Ban record: proposed. Sources checked October 28, 2026.

    Both County options would exclude data centers above the stated75kW IT energy load boundary. Option1 expressly permits the smaller defined use in LI and GI through Limited Impact Special Review. Option2 defines the larger use in Article18 and excludes it from General Industrial.

    These are alternative draft approaches, not two adopted laws or a blanket prohibition on every computing use. Incidental server infrastructure is expressly excluded by Option1. The existing temporary moratorium is a separate measure. No October21 recommendation, final Board action or site specific eligibility is verified.

    bouldercounty.gov assets.bouldercounty.gov assets.bouldercounty.gov

  11. Ban record: proposed. Sources checked October 28, 2026.

    The proposed use tables mark hyperscale data centers prohibited and provide review paths for smaller facilities. Draft definitions aggregate peak demand across property phases and operators and put hyperscale at30MW or above.

    The portal summary describes a30MW cap and a category above30MW, creating a boundary discrepancy with the draft definition. Exact treatment at30MW remains unresolved. Neither draft language nor the summary is adopted law. Existing facility modifications have specific provisions; no blanket shutdown or present resource performance is established.

    publicinput.com engage.larimer.gov

  12. Moratorium record: adopted effective day unverified. Sources checked October 28, 2026.

    New data centers and existing center expansions of20percent or more within City boundaries.

    Prior land use approvals excluded. Original instrument not read. No site shutdown, present eligibility or future meeting day inferred.

    www.forestgrove-or.gov

  13. Ban record: proposed. Sources checked October 28, 2026.

    Additional Use route in I1 and I2; other districts excluded. Qualifying subordinate processing of1MWorless exempt.

    Accessory exception also requires exclusive support of a permitted principal use. Not a blanket ban or adopted rule. Blank numbers and future hearing recital remain draft.

    mexicomissouri.net mexicomissouri.net

  14. Moratorium record: adopted current status unverified. Sources checked October 28, 2026.

    City account describes a halt on applications for data center construction inside city limits while zoning rules are reviewed.

    Signed instrument, exceptions and current legal effect unverified. Relative earlier this month wording is not converted to a day. Secondary August31date not used to repair the source. November hearing leads remain unqualified. No individual project halt or operation inferred.

    myemail.constantcontact.com

  15. Ban record: adopted current status unverified. Sources checked October 28, 2026.

    Official title designates data centers nonpermitted in all Township zones. Do not infer closure of an existing facility.

    Final passage notice reports October19 2026 adoption after July13 introduction. Scanned packet page4 inconsistently labels July13 adoption and August17 hearing; page5 has blank final adoption fields. Dates conflict, so no exact adoption or effect day is selected. Current exceptions and operative text completeness unverified.

    downetwpnj.org downetwpnj.org downetwpnj.org

  16. Ban record: adopted current status unverified. Sources checked October 28, 2026.

    Prohibits principal data centers in all zoning districts. Accessory server rooms solely supporting the principal use remain permitted inside its building, limited to10percent of gross floor area or2000squarefeet, whichever is less.

    Original enacted instrument and current exceptions not independently verified. Publication day is not adopted_on. Warehouse, flex and research classifications are not alternative authorization. No existing operating closure inferred.

    www.raritantwpnj.gov

  17. Ban record: proposed. Sources checked October 28, 2026.

    Proposed prohibition on computing facilities assembled from individual modules no larger than 15 by 60 feet, including modules joined to form larger buildings. This is a construction form restriction, not a citywide prohibition on all data centers.

    Six related proposals include district approval routes. Council action date was unset in the October 5 notice; draft legal dates are placeholders. Current adoption and force remain unverified. No individual project outcome inferred.

    www.vermillion.us www.vermillion.us

  18. Moratorium record: adopted current status unverified. Sources checked October 28, 2026.

    Extension of the temporary pause on accepting and processing new data center entitlement applications while development standards are prepared.

    Clerk summary verifies reported adoption, not the complete enacted terms or current force. Existing facility operation, exceptions and exact legal term require the full instrument. No expiry calculated.

    www.lake-elsinore.org

  19. Moratorium record: adopted current status unverified. Sources checked October 29, 2026.

    Reported pause on filing, processing or approving permits for new and expanded data centers above 10 MW in unincorporated county areas.

    News labels ordinance 2026 577 but links to legislative O2026 557. Linked record displays August 27 effective date; this is not assigned across the unresolved identifier conflict. October 20 scheduled hearing is not a completed outcome. Full executed terms and exceptions unreviewed.

    www.piercecountywa.gov online.co.pierce.wa.us

  20. Moratorium record: adopted current status unverified. Sources checked October 29, 2026.

    Hyperscale category covers facilities meeting any one criterion: area at least100000squarefeet, electricity demand above75MW, at least5000servers, or cooling or operational water use above50gallonsperminute.

    Full approved ordinance link returned web403; complete operative clauses and exceptions unreviewed. Criteria are alternatives, not cumulative. No calendar expiry computed or site operation outcome inferred.

    www.cityofdubuque.org

Only matched, sourced records are shown. Missing documentation is not proof of no projects, concerns, hearings or local restrictions. Dates in the original sources can precede the Atlas check.

Explore the map · Community concerns · Data downloads

Updated . What changed: Dated page documentation. Individual source dates remain with the evidence.