Weekly brief · California

What changed in data centers this week.

Atlas research for the week of October 26, 2026, through October 29, 2026. Source review dates and physical events keep their separate meanings.

Complete dated evidence for this brief · All weekly briefs · All upcoming notices · RSS

0research label reviews
0records added to Atlas
3scheduled dates ahead
0concern record checks

Counts describe this research collection. A label review is not a physical transition, an added record is not a new building, and a scheduled date does not establish that an event happened. Method and source rules.

Scheduled dates ahead.

  1. CPUC Resolution E5455 further consideration. Scheduled October 29, 2026.

    The revised October 8 Commission voting results mark Resolution E5455 held to October 29 for further review. This is a scheduled reconsideration reference, not a verified final vote or an approval. The selected result table does not identify a particular project, later agenda placement, future clock or venue.

    ia.cpuc.ca.gov

  2. Board informational report on unsolicited Global Stack outreach. Scheduled October 29, 2026 at 12:30 local time as published.

    The current 19th DAA agenda sets a 12:30 PM Board meeting and lists Global Stack USA under the CEO informational report regarding unsolicited outreach. This is the meeting start, not an exact item time or a development approval vote. An informational entry does not establish an accepted project proposal, signed agreement, planned construction or computing operation.

    earlwarren.com static1.squarespace.com

  3. CEC working group discussion of draft demand forecast and data centers. Scheduled November 4, 2026 at 13:00 local time as published.

    The Demand Analysis Working Group schedules discussion of 2026 IEPR load modifier draft results, including data centers, known loads and related forecast methods. This is a forecast discussion, without a site permit decision or adopted operating demand finding.

    www.energy.ca.gov www.energy.ca.gov

Moratorium and restriction source reviews.

  1. Moratorium record: adopted current status unverified. Sources checked October 28, 2026.

    Extension of the temporary pause on accepting and processing new data center entitlement applications while development standards are prepared.

    Clerk summary verifies reported adoption, not the complete enacted terms or current force. Existing facility operation, exceptions and exact legal term require the full instrument. No expiry calculated.

    www.lake-elsinore.org

Only matched, sourced records are shown. Missing documentation is not proof of no projects, concerns, hearings or local restrictions. Dates in the original sources can precede the Atlas check.