Kentucky · Data center record

Ebon International Big Sandy cryptomining / data processing complex

Status
Denied, withdrawn or closed
Place
Louisa, Kentucky
County
Lawrence
Company
Ebon International (part of Singapore-based Ebang International Holdings)
End user
Ebon International (self-mining: Bitcoin/Ethereum, blockchain and data processing)
Type
crypto/HPC
Utility
Kentucky Power (AEP)
Power
250 MW (225 MW interruptible under demand-response terms)
Investment
250 million dollars (LPM / Kentucky Public Radio); about 50 million dollars on the facility (Utility Dive, citing Kentucky Power)
Jobs
permanent: Up to 100
Incentives
Discounted economic-development / demand-response electric rate contract with Kentucky Power (rejected); state crypto sales-tax exemptions available

Exact site not published; shown at county level. The dot is placed inside the county for the map and is not the site, its address or a parcel.

Open on the Kentucky mapNear me

Dated record.

  1. Kentucky Lantern reports Kentucky Power is asking Franklin Circuit Court to overturn the PSC decision
  2. PSC rejects the contract, citing ratepayer risk
  3. PSC hearing: Kentucky Power witness concedes capacity shortfall from 2026
  4. Contract filed for PSC approval; opposed by Attorney General, KIUC and environmental groups
  5. Kentucky Power and Ebon execute 250 MW discounted supply contract

Sources.

  1. lpm.orglpm.org
  2. www.utilitydive.comwww.utilitydive.com
  3. www.kentuckynewera.comwww.kentuckynewera.com

Nearby records.

Data file updated October 24, 2026. Fields keep their own sources and dates; unknown details stay unknown. Method · Report a correction

Know of a missing project?

Send its name, location and a public source. Submissions are checked before a record changes.

Suggest a project or correction

Review date unrecorded, 3 linked sources. Review dates do not certify current operation or every field. Corrections and record history

Updated . What changed: Dated source for Ebon International Big Sandy cryptomining / data processing complex. This is not a project milestone.

Quick answers

Questions about this record

What stage does this record report?

Denied, withdrawn or closed. This is the sourced Atlas label; it does not independently certify current operation. Compilation dated October 26, 2026. Record data and source links.

How precise is the mapped location?

Exact site not published; shown at county level. A map reference does not independently certify a parcel, roof or facility boundary. Compilation dated October 26, 2026. Record data and source links.

Where can I review the evidence?

3 distinct public source links are retained for this record. Source 1 Source 2 Source 3 Compilation dated October 26, 2026. Record data and source links.